Summarized Nov 23, 2026 covers records through Nov 3, 2026 14 events Check for newer records Follow this topic (RSS)

Read as: Town projects to build, repair, or fund sidewalks: planning, cost, location, votes.

AI-generated answer, checked against the pages it cites (dates, boards and dollar figures). It reflects the records as of Nov 23, 2026; things may have changed since. Open the PDF page to confirm.

East Granby is building and repairing sidewalks around Town Hall, School Street, East Street and Granbrook Park. Most of the money comes from state and regional grants.

Where it stands: The latest record is a town plan draft from November 3, 2026. The outcome is not in the records yet.

Timeline

  1. Apr 2, 2025

    Town news, East Granby

    The town posted a request for bids for the Town Campus Sidewalk Connections Project.

    Town news, Apr 2, 2025

  2. Apr 28, 2025

    Economic Development Commission, East Granby

    The Economic Development Commission said the Town Campus sidewalk project was out to bid, with a June start hoped for.

    Economic Development Commission, Apr 28, 2025 (PDF p. 1)

  3. Dec 22, 2025

    Economic Development Commission, East Granby

    The Town Hall campus sidewalks were listed as completed under a state connectivity grant, and a School Street realignment and pedestrian project was about 90% designed.

    Economic Development Commission, Dec 22, 2025 (PDF p. 1)

  4. Feb 10, 2026

    Planning & Zoning Commission, East Granby

    The planning commission's plan update included a section on transportation, sidewalks and trails.

    Planning & Zoning Commission, Feb 10, 2026 (PDF p. 1)

  5. Mar 11, 2026

    Board of Selectmen, East Granby

    The Board of Selectmen said the Town applied for a $1.5 million state grant for sidewalks on East, Nicholson and Route 20. $1.5million $828,000

    Board of Selectmen, Mar 11, 2026 (PDF p. 1)

  6. Mar 11, 2026

    Board of Selectmen, East Granby

    A $240,000 connectivity grant will fund sidewalks from School Street and South Main up to Sanford Ridge. $240,000

    Board of Selectmen, Mar 11, 2026 (PDF p. 1)

  7. Mar 23, 2026

    Economic Development Commission, East Granby

    The Economic Development Commission noted a sidewalk connection grant extending to new development on East Street.

    Economic Development Commission, Mar 23, 2026 (PDF p. 2)

  8. Apr 22, 2026

    Board of Selectmen, East Granby

    Sidewalk concept designs for the remaining connectivity grant funds were completed and sent to the State, and the $1.5 million East Street grant decision was expected in May. 1.5 million

    Board of Selectmen, Apr 22, 2026 (PDF p. 1)

  9. Apr 27, 2026

    Economic Development Commission, East Granby

    The planner said the town applied for $1.5 million for sidewalks connecting the town center to nearby and future housing. $1.5 million

    Economic Development Commission, Apr 27, 2026 (PDF p. 1)

  10. May 18, 2026

    Economic Development Commission, East Granby

    A $1.5 million grant to finish the sidewalk connections was recommended and went to a regional executive committee for final approval. $1.5 million

    Economic Development Commission, May 18, 2026 (PDF p. 1)

  11. May 27, 2026

    Board of Selectmen, East Granby

    The Town said survey work for the East Street sidewalk project was being scheduled.

    Board of Selectmen, May 27, 2026 (PDF p. 1)

  12. Sep 1, 2026

    School Town Building Committee, East Granby

    The school building committee reviewed low bids and moved to appropriate up to $250,000 to pave Granbrook Park and East Granby Farms parking lots and sidewalks. $250,000

    School Town Building Committee, Sep 1, 2026 (PDF p. 1)

  13. Sep 8, 2026

    Planning & Zoning Commission, East Granby

    The planning commission reviewed a draft transportation chapter that includes a sidewalk connectivity plan map.

    Planning & Zoning Commission, Sep 8, 2026 (PDF p. 1)

  14. Nov 3, 2026

    Town news, East Granby

    A draft town plan for 2026 was posted for a public hearing.

    Town news, Nov 3, 2026

Related searches: sidewalk grantLOTCIP grantSchool Street sidewalksConnectivity GrantEast Street sidewalk

Show the page excerpts this answer is based on (13)
Town news, Apr 2, 2025, news post, page 1
RFP: Town Campus Sidewalk Connections Project. 1419 Addendum 1 EG Town Campus 2025 04 28 Download RFP Project Manual Published 1419 Town Campus Sidewalk Specification Download RFP 1419 Town Campus Sidewalk Connections Maps Full Set March 7 2025 Download 20250507111955711 Download
Economic Development Commission, Apr 28, 2025, minutes, page 1
… League’s networking event in March at Dudleytown Brewing was very successful.  PZC recently approved a permanent entrance sign for the Bramble Bush Multi-family Development.  A text amendment was approved to allow food trucks under specific circumstances on businesses in the Business Zone.  The Sidewalk Campus project is out to bid. Bid opening is next week. We hope to kick off the project in
Economic Development Commission, Dec 22, 2025, minutes, page 1
… . 3. Minutes: Chairman Iannucci tabled approving the minutes till the January meeting. 4. Discussion with public: N/A ~ no one here or on ZOOM 5. Communications: Economic Development Activities Report received from Robin Newton, Town Planner:  CT Connectivity Grant ~ completion of Town Hall Campus sidewalks;  LOTCIP ~ prelim design phase on School Street realignment and pedestrian improvement;
Planning & Zoning Commission, Feb 10, 2026, minutes, page 1
… & Johneil Clarke from Tyche on ZOOM; Absent: Tom Derlinga & Alternates Bill Hearn & Joel Strong. 2. POCD: a. Vision Statement: Johneil Clarke shared the draft of the vision statement with some updates. It is divided into 4 sections: 1. Economic Development/Housing 2. Transportation/Public Utilities/Sidewalks/Trails 3. Environment/Development/Open Space/Conservation 4. Design Standards/Historic R
Board of Selectmen, Mar 11, 2026, minutes, page 1
… ident commented about the truck traffic on East Street. 3. CORRESPONDENCE – None 4. MINUTES – Selectperson Thompson made a motion to accept the minutes as presented. Seconded by Selectwoman Wimpfheimer. Selectperson Thompson Abstained. Motion Approved. 5. OLD BUSINESS – a. School Street Realignment Project – The Concept Plan for the new School Street location is nearly complete. The Town applied
Economic Development Commission, Mar 23, 2026, minutes, page 2
… en Vincunas- for safety reasons.  School Street realignment and grant requirements  Warehouses are currently under litigation; hence a stay in construction.  Granbrook Park updates – playscape, fountain and mister being installed to facilitate holding summer camps there again.  LOTCIP grant for sidewalk connectivity extending to new development on East Street • New Business discussion: Chair
Board of Selectmen, Apr 22, 2026, minutes, page 1
… 5. b. East Street LOTCIP Grant Update – First Selectperson Hayes gave an update on the LOTCIP Grant application for the 1.5 million, we expect to hear if we have been awarded the grant the first week of May. First Selectperson Hayes also gave an update on the Connectivity Grant, he stated that the sidewalk concept designs have been completed and submitted to the State, utilizing the remaining fu
Economic Development Commission, Apr 27, 2026, minutes, page 1
… otes in favor were unanimous, motion carried 4. Discussion with public: N/A ~ no one here or on ZOOM 5. Communications: • Planner Report: Justin LaFountain shared the current updates:  1 Gateway Blvd PZC approval for Phase 1 construction of plaza with drive thru.  LOTCIP applications to CRCOG for sidewalks connecting Town center to neighboring & future residential developments; will find out i
Economic Development Commission, May 18, 2026, minutes, page 1
… PA 25-1.  Also, working on updating application forms for PZC & IWCC. Our fee schedules do not align with other towns & should be re-evaluated.  Town Kiosks have been installed along trails, working with the Conservation Commission.  MS4 annual permit with DPW  $1.5 million grant to finish the sidewalk connectivity has been recommended and now goes to CRCOG’s executive committee, to finalize
Board of Selectmen, May 27, 2026, minutes, page 1
… the original estimate was to grout 7–9 joints, work has expanded to 21 joints so far. Crews will return to Bradley Park Road next week to complete the remaining grouting work. b. East Street LOTCIP Grant – First Selectperson Hayes stated plans are moving forward to schedule the survey work for this sidewalk project. 6. NEW BUSINESS – a. Set Town Meeting Call, Time & Date – Selectperson Thompson
School Town Building Committee, Sep 1, 2026, minutes, page 1
… nimously. 4. OLD BUSINESS a. Consider and Act Upon a proposal to pave Granbrook Park and East Granby Farms as presented. The Committee reviewed bids with Ed Hubbard and Paul Gegetskas which included both the cost and scope of work proposed for the Granbrook Park and East Granby Farms Parking Lots & Sidewalks. There also was a discussion about the extreme volatility of petroleum-based product pri
Planning & Zoning Commission, Sep 8, 2026, minutes, page 1
… this. A draft is ready for review, she has provided a link. 4. POCD: a. Chapter 11 ~ Transportation: Johneil Clarke presented the chapter to the commission. Commission members reviewed it with some minor edits. Suggestions for some more visual graphs & maps; labeling of roadways on the sample map; sidewalk connectivity plan map. Additionally, some photos of town sections, bike path, etc. Brian O
Town news, Nov 3, 2026, news post, page 1
Draft POCD – Town of East Granby 2026. East Granby POCD 2026 Final Layout for Hearing Download