East Granby / News / Apr 2, 2025
RFP: Town Campus Sidewalk Connections Project
East Granby news Hide agendas that already have minutes Town newsSummary
AI-generated summary of the post and its attached files, checked against their text (dollar figures). Written Nov 22, 2026; the town may have updated the post since.
The Town of East Granby posted RFP documents and Addendum No. 1 (April 28, 2025) for the Town Campus Sidewalk Connections Project, which builds new 5-foot concrete sidewalks, ramps, landscaping, striping and a bituminous pathway on the town campus. Contractors bidding on this state-funded project must submit sealed bids by May 6, 2025.
- Sealed bids are due May 6, 2025 at 1:00 p.m. at East Granby First Selectwoman's office, 9 Center Street, and will be publicly opened and read.
- Addendum No. 1 states the project received a CT DOT Community Connectivity Grant of $690,000 for construction, contingency and incidental costs.
- Addendum No. 1 revises the Bid Form (pages 1/2 and 2/2) and adds special provision 0219011A Sedimentation Control at Catch Basins; Turf Establishment and Maintenance & Protection of Traffic follow CT DOT Form 819 with no special provisions.
- Approximately 400 square feet of staging area is provided in the Community Center parking lot; any staging areas must be enclosed with a minimum 6-foot chain-link fence with lockable gates.
- The Town will not accept excess fill from the project. No subsurface borings were performed; rock excavation covers boulders over one cubic yard.
Dates mentioned: April 8, 2025 (non-mandatory pre-bid meeting, past); April 28, 2025 (Addendum No. 1 issued); May 6, 2025 at 1:00 p.m. (bid opening)
Attached files (4)
1419 Addendum 1 EG Town Campus 2025 04 28 · PDF, 9 pages
Open the PDF download · town site copy
Text read from the scan by OCR (may contain errors)
1 TOWN OF EAST GRANBY Town Campus Sidewalk Project ADDENDUM No. 1 April 28, 2025 Bidders are hereby informed that the Project Manual and Drawing for the above-mentioned contract are modified, corrected, and/or supplemented as follows and that Addendum No. 1 shall become part of the Contract Documents. C larification: • The Town of East Granby has received a CT DOT Community Connectivity Grant in the amount of $690,000 for the construction, contingency and incidental costs associated with the project. • The Town of East Granby will provide approximately 400 square feet of staging area in the Community Center parking lot. • For those interested in electronic files of the drawings, please email the attached disclosure form to Beth Nesteriak at beth@bbengrs.com. Once received, the DWG files will be sent to the requestor. Q uestions: 1. Wi ll the Town take excess fill from the project? T he Town will not accept any excess fill from the project. 2. I s the intent of spec section 013553 Security Procedures for the contractor to furnish & install construction fencing around work areas? Not really sure of Contractor responsibility of part 1.03.A&B to restrict entrance of persons & vehicles into project site T he Contractor shall be responsible for maintaining a safe, secure, and orderly job site at all times. All open work areas must be adequately barricaded and clearly signed in accordance with CT DOT standards to prevent unauthorized public access, mitigate risks of theft or vandalism, and ensure public and worker safety. Al l designated staging areas shall be enclosed with a minimum 6-foot-high chain-link fence to restrict access. Gates shall be lockable and remain secured when not in use. The Contractor shall ensure compliance with all applicable OSHA regulations, CT DOT guidelines, and local ordinances pertaining to construction site safety and security. 3. P lease provide a Special Provision for 0219011A Sedimentation Control at Catch Basins T he special provision is attached and made part of these contract documents. 2 4. The bid form has the following items as Special Provisions (“A” items) 0940019A Turf Establishment - Lawn, and 0971001A Maintenance & Protection of Traffic. The bid documents do not include these items in the Special Provisions portion. Items 0940019 and 0971001 do not include any special provisions. Form CT DOT 819 should be followed. A revised Bid Form is attached and made part of these contract documents. 5. Bid form has Vinyl Fence as item 0905011 but Special Provisions has a specification for Vinyl Fence as 0905012A Manufactured by Atlas Fence. Is this the only type of Vinyl Fence that is to be installed for this project? All materials used for this work shall conform to the specified requirements or be approved as equal. 6. Note that item 0977001 Traffic Cone has a quantity of 200 each. Is this the intent or a typo? The quantity for traffic cones is 200. 7. Were there any borings performed on this project and if so can that information be made available? We see an item for Rock Excavation (#0202100) and was looking for where it is located throughout the project. No subsurface borings were performed for this project. The Rock Excavation item is included to account for the potential removal of large boulders exceeding one (1) cubic yard in volume, should they be encountered during construction. Page 1 of 2 (Fill In Company Name) AGREEMENT FOR THE TRANSFER OF ELECTRONIC FILES We, B&B Engineering, LLC and/or Accurate Land Surveying, LLC., herein referred to as the "Consultant", agree to forward electronic files for Town of East Granby Town Campus Sidewalk Connections Project to ______________________________________________, herein referred to as the "Recipient". The Recipient agrees that these files are an instrument of service only for their use and only for this project and they further agree to not provide copies of these files to any other party without written consent of the Consultant. These files have been prepared to our current specifications and are based on AutoDesk software. These files may not be compatible with the Recipient's hardware, operating system and/or system specifications/software, and may not convert to your system. We are not responsible for any expenses the Recipient may incur utilizing these files. We are not responsible for any inaccuracies or data that is lost as a result of your use of these files. If the files are not emailed, the media on which they are transferred has a limited unknown life span and we are not responsible for the content of these files on said media 30 calendar days after your receipt. Regardless of the method of file transfer, please review these files within 10 calendar days of your receipt and report to our office any problems you may encounter utilizing these files. We are under no obligation to the Recipient and/or any third party to maintain or retain these files and/or convert them to future software and/or hardware systems unless under separate written agreement. Please review the terms and conditions more specifically noted on the reverse side or attached sheet. Accepted by (Signature) Date Print Name Title Company Email Address J1419 Page 2 of 2 T ERMS AND CONDITIONS FOR THE TRANSFER OF ELECTRONIC FILES 1.0 ACCEPTANCE: Because data stored on electronic media can deteriorate undetected or be modified without the Consultant's knowledge, the Recipient agrees that it will accept responsibility for the completeness, correctness, or readability of the electronic media after an acceptance period of no more than 30 calendar days after delivery of the electronic files, and that upon the expiration of this acceptance period, the Recipient will indemnify and save harmless the Consultant for any and all claims, losses, costs, damages, awards or judgements arising from the Recipients use of the electronic files or output generated from them. The Consultant agrees that it is only responsible for the accuracy of the sealed drawings that may accompany a project’s submittal, and that such accuracy is defined as the care and skill ordinarily used by members of the Consultant's profession practicing under similar conditions, at the same time and in the same locality. The Consultant makes no warranties, expressed or implied, under this agreement or otherwise, in connection with the Consultant's services. 2.0 OWNERSHIP OF CADD FILES The information on the electronic media is considered part of the Consultant's instrument of service and shall not be used on other projects, for additions to this project, or for completion of this project or portion thereof by another design professional, except by agreement in writing with appropriate compensation and legal protection provided to the Consultant. 3.0 RIGHT/ABILITY TO ALTER/EDIT FILES Any use or reuse of altered files by the Recipient or others, without written verification or CADD adaptions by the Consultant for the specific purpose intended, will be at the Recipient's risk and full legal responsibility. Furthermore, the Recipient will, to the fullest extent permitted by law, indemnify and hold the Consultant harmless from any and all claims, suits, liability, demands, judgements, or costs arising out of or resulting therefrom. Any verification of such adaption by the Recipient will entitle the Consultant to additional compensation. J1419 0219011A - 1 SEDIMENTATION CONTROL AT CATCH BASIN ITEM 0219011A - SEDIMENTATION CONTROL AT CATCH BASINS Description: This work shall consist of furnishing, installing, cleaning, maintaining and removing sedimentation control at catch basins at the locations and as shown on plans and as directed by the engineer. Materials: The sediment control device shall be manufactured from a specially designed woven polypropylene geotextile sewn by a double needle machine, using a high strength nylon thread. The sediment control device shall be manufactured by one of the following or an approved equal: Siltsack® SI Geosolutions: www.sigeosolutions.com (800)621-0444 Dandy Sack™ Dandy Products Inc. P.O. Box 1980 Westerville, Ohio 43086 Phone: 800-591-2284 Fax: 740-881-2791 Email: dlc@dandyproducts.com Website: www.dandyproducts.com FLeXstorm Inlet Filters Inlet & Pipe Protection 24137 W. 111th St - Unit A Naperville, IL 60564 Telephone: (866) 287-8655 Fax: (630) 355-34 The sediment control device will be manufactured to fit the opening of the catch basin or drop inlet. The sediment control device will have the following features: two dump straps attached at the bottom to facilitate the emptying of sack and lifting loops as an integral part of the system to be used to lift sack from the basin. The sediment control device shall have a restraint cord approximately halfway up to keep the sides away from the catch basin walls, this cord is also a visual means of indicating when the sediment control device should be emptied. Once the strap is covered with sediment, the sediment control device should be emptied, cleaned and placed back into the basin. 0219011A - 2 SEDIMENTATION CONTROL AT CATCH BASIN Construction Methods: Installation, removal, and maintenance shall be per manufacturer instructions and recommendations. Method Of Measurement: Sedimentation Control at Catch Basin will be measured as each installed, cleaned, maintained, accepted, and removed. There will be no separate measurement for maintenance or replacement associated with this item Basis Of Payment: Sedimentation Control at Catch Basin will be paid for at the contract unit price each complete in place and accepted, which price shall include all materials, equipment, tools, and labor incidental thereto. Pay Item Unit Sedimentation Control at Catch Basin Ea. 0201001A Clearing and Grubbing 1 L.S. 0202000 Earth Excavation 225 C.Y. 0202100 Rock Excavation 100 C.Y. 0202351 Unsuitable Material Excavation 150 C.Y. 0202529 Cut Bituminous Concrete Pavement 400 L.F. 0212000 Subbase 140 C.Y. 0219003 Sedimentation Control Filter Fabric Fence System 750 L.F. 0219011A Sedimentation Control at Catchbasin 15 E.A. 0406172 HMA S0.375 12 Ton 0814005 Reset Granite Curved Stone Curbing 15 L.F. 0815001 Bituminous Concrete Lip Curbing 230 L.F. 0921001 Concrete Sidewalk 11,590 S.F. 0921002A Monolithic Concrete Sidewalk and Curb 200 S.F. 0921005 Concrete Sidewalk Ramp 550 S.F. 0921048 Detectable Warning Surface 140 S.F. 0922501 Bituminous Concrete Driveway 40 S.Y. 0944000 Furnishing and Placing Topsoil 3,010 S.Y. 0940019 Turf Establishment-Lawn 3,010 S.Y. 0949846 Acer Saccharum Sugar Maple 2"-2 1/2" cal. 1 E.A. 0971001 Maintenance and Protection of Traffic 1 L.S. BID FORM Town Campus Sidewalk Connections Project East Granby, Connecticut (Note: All prices must be clearly written in ink or typed, in words as well as figures, for the entire bid.) Item No. Brief Description Unit Price in Figures Total In WordsEstimated Quantity Total in Figures Contractor Name: Contractor Contact & Email: 1/2 Revised Via Addendum #1 Town Campus Sidewalk Connections Project East Granby, CT BID FORM Town Campus Sidewalk Connections Project East Granby, Connecticut (Note: All prices must be clearly written in ink or typed, in words as well as figures, for the entire bid.) Item No. Brief Description Unit Price in Figures Total In WordsEstimated Quantity Total in Figures Contractor Name: Contractor Contact & Email: 0975003 Mobilization 1 L.S. 0977001 Traffic Cone 200 E.A. 0970006A Trafficperson (Municipal Police Officer) 1 ALLOW $60,000.00 $60,000.00 Sixty thousand dollars 0970007A Trafficperson (Uniformed Flagger) 150 HR. 0978002 Traffic Drum 25 E.A. 0980020 Construction Surveying 1 L.S. 1206023A Removal and Relocation of Existing Signs 7 E.A. 1206090A Relocate Wooden Sign 1 E.A. 1210105 Epoxy Resin Pavement Markings, Symbols and Legends 1,480 S.F. 0905012A Vinyl Fence 50 L.F. 1220027A Construction Signs 200 S.F. 1302061A Adjust Gate Box (Water) 2 E.A. 1302062A Adjust Gate Box (Gas) 1 E.A. Base Bid Total in Words Note: All quantities are estimated and used for comparison of bids. It is understood that the various unit prices bid will control in any contract which may be awarded arising from this Bid. In the event of any discrepancies between numerical values and the corresponding written amounts, the Town reserves the right to use the values that result in the least cost to the Town. This includes any mathematical or clerical errors. The Owner reserves the right to delete any Item of Work. Bidder agrees that the Work will be substantially completed and completed on or before the dates or within the number of days indicated in the Agreement. Bidder accepts the provisions of the Agreement as to liquidated and special damages in the event of failure to substantially complete the Work on time. Base Bid Total in Figures 2/2 Revised Via Addendum #1 Town Campus Sidewalk Connections Project East Granby, CT \\10.0.0.21\b&b\Job Data\1400-1499\1419\Bidding\2025 04 07 Pre Bid Sign In.xlsx [tbl-0.md](tbl-0.md) * PLEASE BE SURE TO PRINT LEGIBLY - IF POSSIBLE, LEAVE A BUSINESS CARD Pre-Bid Meeting Date: Page _____ of _____ Town of East Granby | Town Campus Sidewalk Pre-Bid Meeting
RFP Project Manual Published 1419 Town Campus Sidewalk Specification · PDF, 260 pages
Open the PDF download · town site copy
Text of the file
PR OJECT MANUAL FOR Town Campus Sidewalk Connections Project CCGP Project Number: 0170-3513GR P repared for: Town of East Granby 9 Center Street East Granby, Connecticut 06026 (860) 6 53-2576 Town campus is to be maintained by the Town of East Granby. The State of Connecticut Department of Transportation Standard Specifications for Roads, Bridges, Facilities and Incidental Construction (Form 819) and all supplements thereto shall govern this project. Prepared by: 15 R esearch Drive, Suite 3 Woodbridge, Connecticut 06525 Phone: (203) 881-8145 www.bbengrs.com Job No. 1419 TOC-1 Town Campus Sidewalk Connections Project Town of East Granby 9 Center Street East Granby, Connecticut Table of Contents Section Title DIVISION 00 – PROCUREMENT AND CONTRACT REQUIREMENTS 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 41 53 Bid Form 00 45 00 Bidder’s Affidavit 00 45 13 Bidder’s Qualification Statement 00 45 19 Non-Collusive Bidding Certification 00 45 33 Non-Discrimination Laws/Executive Orders 00 45 36 Equal Employment Opportunity 00 45 43 Certified Copy of Resolution of Board of Directors 00 45 70 CHRO Contract Compliance Regulations 00 52 13 Agreement 00 61 00 Bid Bond 00 61 13.13 Performance Bond 00 61 13.16 Payment Bond 00 62 76 Applications for Certification for Payment 00 70 00 General Conditions 00 73 00 Supplementary General Conditions Attachments to Supplementary Conditions A. Connecticut State Wage Rates B. Contractors Wage Certification Form C. Notice to Contractor D. Construction Contracts-Required Contract Provisions (state funded only contracts) DIVISION 01 – GENERAL REQUIREMENTS 01 11 00 Summary of Work 01 13 00 Obligations of Contractors to Owners 01 14 00 Work Restrictions 01 32 13 Scheduling of Construction 01 33 00 Submittal Procedures 01 35 53 Security Procedures 01 55 26 Traffic Control 01 60 00 Product Requirements TOC-2 *The numbers and titles presented above utilize The Construction Specifications Institute MasterFormat 2016 Edition Numbers and Titles. I NDEX TO SPECIAL PROVISIONS I NTRODUCTION TO THE SPECIAL PROVISIONS S ECTION 1.08 Prosecution and Progress ITEM #0201001A Clearing and Grubbing ITEM #0921002A Monolithic Concrete Curb and Sidewalk ITEM #0970006A Traffic person (Municipal Police Officer) ITEM #0970007A Traffic person (Uniformed Flagger) ITEM #1206023A Removal and Relocation of Existing Signs ITEM #1206090A Relocate Wooden Sign ITEM #1220027A Construction Signs ITEM #1302061A Adjust Gate Box (Water) ITEM #1302062A Adjust Gate Box (Gas) ITEM #0905012A Vinyl Fence DRAW INGS Drawing No. Series Drawing Title 01-01 Cover Sheet 03-01 – 03-02 Existing Conditions Plans 11-01 – 11-02 Site Layout Plans 12-01 – 12-02 Grading Plans 18-01 – 18-02 Soil Erosion & Sediment Control Plans 19-01 – 19-12 Construction Details E ND OF SECTION TOWN CAMPUS SIDEWALK CONNECTIONS PROJECT D IVISION 00 00 00 PR OCUREMENT AND CONTRACTING REQUIREMENTS 00 11 13 - 1 TOWN OF EAST GRANBY EAST GRANBY, CONNECTICUT Town Campus Sidewalk Connections ADVERTISEMENT FOR BIDS Sealed Bids for the Town Campus Sidewalk Connections Project will be received by the Town of East Granby, First Selectwoman’s office at, 9 Center Street, East Granby, Connecticut 06026 until May 6, 2025 at 1:00 p.m. local time at which time they will be publicly opened and read. The project consists of the construction of new 5’ wide concrete sidewalks within the town campus along Center Street, Veterans Memorial Drive, and portions of South Main Street and Turkey Hill Road. The project includes landscaping, striping, and pedestrian facilities including accessible ramps. There will be several connections to existing concrete and asphalt sidewalks . The work also consists of replacement of an existing gravel parking connection path with a bituminous pathway . The foregoing is a general description only and shall not be construed as a complete description of the Work to be performed for this Project. Bidding and Contract Documents may be viewed and downloaded on the Town’s website, www.eastgranbyct.org Partial sets of Bidding and Contract Documents will not be available. The Town of East Granby will not be responsible for full or partial sets of Contract Documents, including any addenda, obtained from other sources. The project is funded by the Community Connectivity Grant Program (CCGP) from the State of Connecticut, which is administrated by the Connecticut Department of Transportation. The State Project Number is 0170- 3513GR The contractor who is selected to perform this State funded project must comply with Sections 4a -60 and 4a- 60a of the Connecticut General Statutes and An Affirmative Action Plan must be filed with and approved by the Commission on Human Rights and Opportunities prior to the commencement of construction. State law requires a minimum of 25 percent of the state-funded portion of the contract for award to subcontractors holding current certification from the Connecticut Department of Administrative Services (“DAS”) under the provisions of CONN. GEN STAT. 4a-60g. as amended. (25% of the work with DAS certified Small and Minority owned businesses and 25% of that work with DAS certified Minority, Women and/or Disabled owned businesses.) The contractor must demonstrate good faith effort to meet the 25% set-aside goals. For municipal public works contracts and quasi-public agency projects, the contractor must file a written or electronic non-discrimination certification with the Commission on Human Rights and Opportunities. Forms can be found at http://www.ct.gov/opm/cwp/view.asp?a=2982&q=390928&opmNav_GID=180 Contractor must coordinate directly with CHRO. 00 11 13 - 2 PRE-BID MEETING A non-mandatory Pre-Bid meeting of bidders will be held in regards to this project. This meeting will take place on Tuesday, April 8, 2025 at 11:00 a.m. local time at the East Granby Town Hall, Town Meeting Room, 9 Center Street, East Granby, Connecticut 06026. BID SECURITY Bid security in the amount of five (5) percent of the bid must accompany each bid in accordance with the Instructions to Bidders. The successful bidder must furnish a Performance Bond and Payment Bond in the amount of 100% of the Project bid cost. QUALIFICATIONS OF BIDDERS Bidders will be required to furnish information regarding their qualifications to perform the work as set forth in the Instructions to Bidders. The attention of bidders is called to the requirements of non -discrimination in employment practices, conditions of employment, and prevailing wage rates to be paid. The Town of East Granby will not knowingly conduct business with providers of goods or services that are known to discriminate. The Town of East Granby encourages responses to its purchasing needs from Women -owned and Minority- owned enterprises. The Town of East Granby is an Equal Opportunity Employer. No Bidder may withdraw his Bid within ninety (90) calendar days after the date set for the receipt thereof. In the event that the Town of East Granby requires more than ninety (90) calendar days after the actual date of the receipt of Bids and the selected, qualified Bidder does not grant an extension of time, the Town reserves the right to award the Contract to another qualified Bidder who does grant an extension of time to award. Bidders are required to personally inspect the job site area to ascertain information on site conditions. Bidder is required to self-perform a minimum of 50% of the total contract value. Contract commencement and completion time will be in accordance with Article 3 of the Agreement , located within the project manual. RIGHT TO REJECT BID The right is reserved to reject any or all bids, in whole or in part, to award any items, group of items or total bid, and to waive any informality or technical defects, if it is deemed to be in the best interest of the Town of East Granby. The Town reserves the right to reject any or all bids pursuant to Section 16 of Connecticut Special Act No. 77-98, as amended. Eden Wimpfheimer First Selectwoman Town of East Granby, CT Date: April 3, 2025 END OF SECTION 00 21 13-1 INSTRUCTIONS TO BIDDERS SECTION 00 21 13 INSTRUCTIONS TO BIDDERS 1. DEFINED TERMS Terms used in these Instructions to Bidders have the meanings assigned to them in the General Conditions. Certain additional terms used in the Bidding Documents have the meanings indicated below which are applicable to both the singular and plural thereof: 1.1. Bidder—one who submits a Bid to Owner as distinct from a sub- bidder, who submits a Bid to a Bidder. 1.2. Apparent Low Bidder —that Bidder whose Bid as offered in the Bid Form represents the lowest total. 1.3. Engineer – Individual or entity named as such in the Agreement. 1.4. Owner – the Town of East Granby. 1.5. Successful Bidder—lowest, responsible and responsive qualified Bidder to whom Owner (on the basis of Owner's evaluation as hereinafter provided) makes an award. 2. BIDDING DOCUMENTS 2.1. Complete sets of Bidding Documents must be used in preparing Bids. Neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from use of incomplete sets of Bidding Documents. 2.2. Bidding Documents made available on the above terms are only for the purpose of obtaining Bids for the Work and shall not be used for any other purpose. 3. QUALIFICATIONS OF BIDDERS 3.1. Bidders shall be experienced in the kind of Work to be performed, shall have the necessary equipment therefore, and shall possess sufficient capital to properly execute the Work within the time allowed. 3.2. To demonstrate qualifications to perform the Work, Bidder shall submit, within 5 days of Owner's request, written evidence such as financial data, previous experience, present commitments, and other such data as may be called for below. 3.3. Each Bid must contain evidence of Bidder's qual ification to do business in Connecticut or covenant to obtain such qualification prior to contract award. 3.4. Nothing indicated herein will prejudice Owner's right to seek additional pertinent information as is provided in Article 22 BASIS OF AWARD; AWARD OF CONTRACT. 3.5. Bidders shall have experience with similar construction projects, including excavation, trenching, storm drainage and utility installation, roadway and parking lot installations, and landscaping. 3.6. Bidders are advised that Section 12-430(7) of the Connecticut General Statutes, as amended, puts certain responsibilities on parties that enter into agreements with 00 21 13-2 INSTRUCTIONS TO BIDDERS non-resident contractors. Any bidder which is a “non- resident contractor” as the term is defined in section 12- 430(7) of the Connecticut General Statutes shall be required to file a bond with the Connecticut Department of Revenue Service s to ensure compliance with the Act. 3.7. All Contracts that exceed $100,000 for construction, renovations or repai rs must follow Section 31- 53b of the Connecticut General Statutes, as amended , “Construction Safety Training”. 4. PREBID MEETING 4.1. A non-mandatory Pre-Bid meeting, for Bidders only, will be held at 1 1:00 a.m. on April 8, 202 5. The Bidders will meet at the East Granby Town Hall , 9 Center Street, East Granby, Connecticut 06026. 5. LICENSE REQUIREMENTS 5.1. Contractors and Subcontractors, in order to perform public work in the State of Connecticut, are required to hold prior to award of contract State of Connecticut Contractor's Licenses of the class required to perform the specified Work. 6. EXAMINATION OF CONTRACT DOCUMENTS AND SITE 6.1. It is each Bidder's responsibility, before submitting a Bid, to: 6.1.1. Examine thoroughly the Bidding Documents and other related data identified in the Bidding Documents. 6.1.2. Inspect the site to become familiar with and satisfy Bidder as to the general, local, and site conditions that may affect cost, progress, performance, or furnishing of the Work. 6.1.3. Consider federal, state, and local Laws and Regulations that may affect cost, progress, performance, or furnishing of the Work. 6.1.4. Study and carefully correlate Bidder's knowledge and observations with the Bidding Documents and such other related data. 6.1.5. Promptly notify Engineer of all conflicts, errors, ambiguities, or discrepancies, which Bidder has discovered in or between the Bidding Documents and such other related documents. 6.2. Reference is made to the Supplementary Conditions for identification of: 6.2.1. Those reports, if any, of explorations and tests of subsurface conditions at the site which have been utilized by Engineer in preparation of the Bidding Documents. 6.2.2. Those drawings, if any, of physical conditions in or relating to existing surface and subsurface structures (except Underground Facilities) which are at or contiguous to the site which have been utilized by Engineer in preparation of the Bidding Documents. 6.3. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders on subsurface conditions, other physical conditions and Underground Facilities, and possible changes in the Contract Documents due to differing or unanticipated conditions appear in paragraphs 4.02 through 4.04 of the General Conditions. 00 21 13-3 INSTRUCTIONS TO BIDDERS 6.4. Before submitting a Bid, each Bidder will be responsible to make or obtain such additional or supplementary examinations, investigations, explorations, tests, studies, and data concerning conditions (surface, subsurface, and Underground Facilities) at or contiguous to the site or otherwise and which may affect cost, progress, performance, or furnishings of the Work and which Bidder deems necessary to determine its Bid. 6.5. Reference is made to the General Requirements for identification of the general nature of work that is to be performed at the site by Owner or others and that relates to Work for which a Bid is to be submitted. On request, Owner will provide to each Bidder, for examination, access to or copies of contract documents (other than portions thereof related to price) for such work by others. 6.6. The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this article; that without exception the Bid is premised upon performing and furnishing the Work required by the Bidding Documents and applying the specific means, methods, techniques, sequences, or procedures of construction (if any) that may be shown or indicated or expressly required by the Bidding Docu
Only the beginning is shown here; the whole file is searchable. Open the PDF for the rest.
RFP 1419 Town Campus Sidewalk Connections Maps Full Set March 7 2025 · PDF, 21 pages
Open the PDF download · town site copy
Text read from the scan by OCR (may contain errors)
TOWN CAMPUS SIDEWALK CONNECTIONS TOWN CAMPUS EAST GRANBY, CONNECTICUT LOCATION MAP SCALE: 1"=500' TOWN CAMPUS SIDEWALK CONNECTION, EAST GRANBY, CONNECTICUT Land Surveying, Professional Engineering & Land Use Consultants 15 Research Drive Suite 3 Woodbridge , CT 06525 P: (203) 881-8145 www.bbengrs.comE N G I N E E R I N G DRAWING LIST SHEET NUMBER 01-01 03-01 - 03-02 11-01 - 11-02 12-01 - 12-02 18-01 - 18-02 19-01 - 19-12 SITE ENGINEER B&B ENGINEERING LLC 15 Research Drive Suite 3 Woodbridge, Connecticut 06525 T: (203) 881-8145 DRAWING TITLE COVER SHEET EXISTING CONDITIONS PLANS SITE LAYOUT PLANS GRADING PLANS SOIL EROSION AND SEDIMENT CONTROL PLANS CONSTRUCTION NOTES & DETAILS BOARD OF SELECTMEN Eden Wimpfheimer, First Selectwoman Nicole Sokolowski, Executive Assistant Steven Hall, Selectman Amanda Thompson, Selectman TOWN OF EAST GRANBY 9 Center Street East Granby, Connecticut 06026 P: (860)-653-2576 COMMUNITY CONNECTIVITY GRANT PROGRAM PROJECT #0170-3513GR GENERAL SURVEY NOTESGENERAL ENGINEERING NOTES 01-01 PLANNING & ZONING DEPARMENT Robin Newton, AICP, CZEO Director of Planning & Economic Development 10000 10100 000 100 200 300 400 500 600 700 00 900 1000 1100 1111 MAP REFERENCES GENERAL SURVEY NOTES TOWN CAMPUS SIDEWALK CONNECTION, EAST GRANBY, CONNECTICUT 15 9060300 SCALE: 1"=30' Land Surveying, Professional Engineering & Land Use Consultants 15 Research Drive Suite 3 Woodbridge, CT 06525 P: (203) 881-8145 www.bbengrs.comE N G I N E E R I N G OF TOWN CAMPUS SIDEWALK CONNECTIONS PREPARED FOR TOWN OF EAST GRANBY 9 CENTER STREET EAST GRANBY, CONNECTICUT 06026 DRAWING LIST 03-01 EXISTING CONDITIONS PLAN I LEGEND ( ( ( ( ( L:\Job Data\1400-1499\1419\Cadd Data\Sheet Set\1419 SHEET EX CONDITIONS.dwg, 2/7/2025 1:05:20 PM, ARCH full bleed D (36.00 x 24.00 Inches) 20000 20100 20200 20300 20400 20500 20600 20700 2000 20900 21000 21100 21200 21272 10000 10100 10200 10300 10400 10500 10536 700 00 900 1000 GENERAL SURVEY NOTES MAP REFERENCES TOWN CAMPUS SIDEWALK CONNECTION, EAST GRANBY, CONNECTICUT 15 9060300 SCALE: 1"=30' Land Surveying, Professional Engineering & Land Use Consultants 15 Research Drive Suite 3 Woodbridge, CT 06525 P: (203) 881-8145 www.bbengrs.comE N G I N E E R I N G OF TOWN CAMPUS SIDEWALK CONNECTIONS PREPARED FOR TOWN OF EAST GRANBY 9 CENTER STREET EAST GRANBY, CONNECTICUT 06026 DRAWING LIST 03-02 EXISTING CONDITIONS PLAN II LEGEND ( ( ( ( ( L:\Job Data\1400-1499\1419\Cadd Data\Sheet Set\1419 SHEET EX CONDITIONS.dwg, 2/7/2025 1:05:29 PM, ARCH full bleed D (36.00 x 24.00 Inches) CARL ALLGROVE SCHOOL POST OFFICE EAST GRANBY TOWN HALL EAST GRANBY COMMUNITY & SENIOR CENTER RETAIL 10000 10100 000 100 200 300 400 500 600 700 00 900 1000 1100 1111 GENERAL NOTES TOWN CAMPUS SIDEWALK CONNECTION, EAST GRANBY, CONNECTICUT 15 9060300 SCALE: 1"=30' Land Surveying, Professional Engineering & Land Use Consultants 15 Research Drive Suite 3 Woodbridge, CT 06525 P: (203) 881-8145 www.bbengrs.comE N G I N E E R I N G LEGEND OF TOWN CAMPUS SIDEWALK CONNECTIONS PREPARED FOR TOWN OF EAST GRANBY 9 CENTER STREET EAST GRANBY, CONNECTICUT 06026 DRAWING LIST 11-01 SITE DEVELOPMENT PLAN I L:\Job Data\1400-1499\1419\Cadd Data\Sheet Set\1419 SHEET SDP.dwg, 2/7/2025 1:05:45 PM, ARCH full bleed D (36.00 x 24.00 Inches) EAST GRANBY TOWN HALL EAST GRANBY COMMUNITY & SENIOR CENTER AMBULANCE STATION EAST GRANBY TOWN HALL EAST GRANBY FIRE HOUSE/ POLICE DEPARTMENT RETAIL 20000 20100 20200 20300 20400 20500 20600 20700 2000 20900 21000 21100 21200 21272 10000 10100 10200 10300 10400 10500 10536 00 900 1000 GENERAL NOTES TOWN CAMPUS SIDEWALK CONNECTION, EAST GRANBY, CONNECTICUT 15 9060300 SCALE: 1"=30' Land Surveying, Professional Engineering & Land Use Consultants 15 Research Drive Suite 3 Woodbridge, CT 06525 P: (203) 881-8145 www.bbengrs.comE N G I N E E R I N G LEGEND OF TOWN CAMPUS SIDEWALK CONNECTIONS PREPARED FOR TOWN OF EAST GRANBY 9 CENTER STREET EAST GRANBY, CONNECTICUT 06026 DRAWING LIST 11-02 SITE DEVELOPMENT PLAN II L:\Job Data\1400-1499\1419\Cadd Data\Sheet Set\1419 SHEET SDP.dwg, 2/7/2025 1:05:54 PM, ARCH full bleed D (36.00 x 24.00 Inches) CARL ALLGROVE SCHOOL POST OFFICE EAST GRANBY TOWN HALL EAST GRANBY COMMUNITY & SENIOR CENTER RETAIL 10000 10100 000 100 200 300 400 500 600 700 00 900 1000 1100 1111 GENERAL NOTES TOWN CAMPUS SIDEWALK CONNECTION, EAST GRANBY, CONNECTICUT 15 9060300 SCALE: 1"=30' Land Surveying, Professional Engineering & Land Use Consultants 15 Research Drive Suite 3 Woodbridge, CT 06525 P: (203) 881-8145 www.bbengrs.comE N G I N E E R I N G LEGEND OF TOWN CAMPUS SIDEWALK CONNECTIONS PREPARED FOR TOWN OF EAST GRANBY 9 CENTER STREET EAST GRANBY, CONNECTICUT 06026 DRAWING LIST 12-01 GRADING PLAN I EAST GRANBY TOWN HALL EAST GRANBY COMMUNITY & SENIOR CENTER AMBULANCE STATION EAST GRANBY TOWN HALL EAST GRANBY FIRE HOUSE/ POLICE DEPARTMENT RETAIL 20000 20100 20200 20300 20400 20500 20600 20700 2000 20900 21000 21100 21200 21272 10000 10100 10200 10300 10400 10500 10536 00 900 1000 GENERAL NOTES TOWN CAMPUS SIDEWALK CONNECTION, EAST GRANBY, CONNECTICUT 15 9060300 SCALE: 1"=30' Land Surveying, Professional Engineering & Land Use Consultants 15 Research Drive Suite 3 Woodbridge, CT 06525 P: (203) 881-8145 www.bbengrs.comE N G I N E E R I N G LEGEND OF TOWN CAMPUS SIDEWALK CONNECTIONS PREPARED FOR TOWN OF EAST GRANBY 9 CENTER STREET EAST GRANBY, CONNECTICUT 06026 DRAWING LIST 12-02 GRADING PLAN II LEGEND CARL ALLGROVE SCHOOL POST OFFICE EAST GRANBY TOWN HALL EAST GRANBY COMMUNITY & SENIOR CENTER RETAIL 10000 10100 000 100 200 300 400 500 600 700 00 900 1000 1100 1111 GENERAL NOTES TOWN CAMPUS SIDEWALK CONNECTION, EAST GRANBY, CONNECTICUT 15 9060300 SCALE: 1"=30' Land Surveying, Professional Engineering & Land Use Consultants 15 Research Drive Suite 3 Woodbridge, CT 06525 P: (203) 881-8145 www.bbengrs.comE N G I N E E R I N G LEGEND OF TOWN CAMPUS SIDEWALK CONNECTIONS PREPARED FOR TOWN OF EAST GRANBY 9 CENTER STREET EAST GRANBY, CONNECTICUT 06026 DRAWING LIST 18-01 SOIL EROSION & SEDIMENT CONTROL PLAN I EAST GRANBY TOWN HALL EAST GRANBY COMMUNITY & SENIOR CENTER AMBULANCE STATION EAST GRANBY TOWN HALL EAST GRANBY FIRE HOUSE/ POLICE DEPARTMENT RETAIL 20000 20100 20200 20300 20400 20500 20600 20700 2000 20900 21000 21100 21200 21272 10000 10100 10200 10300 10400 10500 10536 700 00 900 1000 GENERAL NOTES LEGEND TOWN CAMPUS SIDEWALK CONNECTION, EAST GRANBY, CONNECTICUT 15 9060300 SCALE: 1"=30' Land Surveying, Professional Engineering & Land Use Consultants 15 Research Drive Suite 3 Woodbridge, CT 06525 P: (203) 881-8145 www.bbengrs.comE N G I N E E R I N G LEGEND OF TOWN CAMPUS SIDEWALK CONNECTIONS PREPARED FOR TOWN OF EAST GRANBY 9 CENTER STREET EAST GRANBY, CONNECTICUT 06026 DRAWING LIST 18-02 SOIL EROSION & SEDIMENT CONTROL PLAN II INLET PROTECTION WITH SILTSACK TEMPORARY SOIL STOCKPILE DETAIL SILT FENCE REMOVE BURLAP FROM TOP 1/3 OF BALL OF ALL TREES & SHRUBS PLANTING BED DETAIL CONCRETE SIDEWALK CONCRETE MONOLITHIC CURB & SIDEWALKSEDIMENTATION & SOIL EROSION SPECIFICATIONS GENERAL NOTES TOWN CAMPUS SIDEWALK CONNECTION, EAST GRANBY, CONNECTICUT 15 9060300 SCALE: 1"=30' Land Surveying, Professional Engineering & Land Use Consultants 15 Research Drive Suite 3 Woodbridge, CT 06525 P: (203) 881-8145 www.bbengrs.comE N G I N E E R I N G OF TOWN CAMPUS SIDEWALK CONNECTIONS PREPARED FOR TOWN OF EAST GRANBY 9 CENTER STREET EAST GRANBY, CONNECTICUT 06026 DRAWING LIST 19-01 CONSTRUCTION NOTES AND DETAILS I GENERAL NOTES: 1. SEE CONCRETE SIDEWALK RAMPS GUIDE SHEETS FOR PEDESTRIAN RAMPS TYPES. 2. ALL CURBING SHALL BE INSTALLED AS OTHER PRECAST OR CAST IN PLACE AS DIRECTED. PEDESTRIAN ACCESS ROUTE OVER A MANHOLE WITH GRATE 1. HORIZONTAL OPENINGS IN GRATES AND JOINTS MUST NOT BE MORE THAN 1/4 HOT. 2. ELONGATED OPENINGS IN GRATES MUST BE PLACED SO THAT THE LOAD DIMENSION IS PERPENDICULAR TO THE DIRECTION OF TRAVEL 5' PASSING SPACE FOR 4' WIDE SIDEWALK PLAN PASSING SPACES SHALL BE PROVIDED AT INTERVALS OF 200' MAXIMUM FOR SIDEWALKS LESS THAN 5' IN WIDTH 5' WIDE SIDEWALK PLAN VERTICAL SURFACE DISCONTINUITIES VERTICAL SURFACE DISCONTINUITIES MUST BE DEVELOPED TO A HEIGHT HOT GREATER THAN 1/4 HOT. THE BEND MUST BE THE ENTIRE WIDTH OF THE DISCONTINUITY 5' PASSING SPACE FOR 4' WIDE SIDEWALK SECTION [tbl-0.md](tbl-0.md) A2050 6/8 1/2010 [tbl-1.md](tbl-1.md) [tbl-2.md](tbl-2.md) TOWN OF CAMPFIELD, RIDGEWALK, CONNECTICUT, JOHN G. GRANBY, CONNECTICUT BITUMINOUS CONCRETE DRIVEWAY PLAN ELEVATION SECTION A BITUMINOUS CONCRETE SIDEWALK BITUMINOUS CONCRETE DRIVEWAY WITH A PEDESTRIAN SIDEWALK SETBACK PLAN ELEVATION SECTION B BITUMINOUS CONCRETE DRIVEWAY BITUMINOUS CONCRETE DRIVEWAY WITH PEDESTRIAN SIDEWALK AT THE CURB PLAN ELEVATION SECTION C COMMERCIAL BITUMINOUS CONCRETE DRIVEWAY [tbl-0.md](tbl-0.md) DRAWING NUMBER: 19-03 [tbl-1.md](tbl-1.md) CONSTRUCTION NOTES AND DETAILS III TOWN CAMPUS SIDEWALK CONNECTIONS TOWN OF EAST GRANBY 9 CENTER STREET EAST GRANBY, CONNECTICUT 06026 [tbl-2.md](tbl-2.md) [tbl-3.md](tbl-3.md) TOWN CAMPUS SIDEWALK CONNECTICUT, EAST GRANBY, CONNECTICUT REVISIONS DESCRIPTION TWO DIRECTIONAL PERPENDICULAR RAMP WITH A GRADE BREAK TO BACK OF CURB OF 5' OR LESS (TYPE 1) TWO DIRECTIONAL PERPENDICULAR RAMP WITH A GRADE BREAK TO BACK OF CURB OF 5' OR LESS WITH NON-WALKING SURFACE (TYPE 3) TWO DIRECTIONAL PERPENDICULAR RAMP WITH GRADE BREAK TO BACK OF CURB GREATER THAN 5' (TYPE 2) TWO DIRECTIONAL PERPENDICULAR RAMP WITH A GRADE BREAK TO BACK OF CURB GREATER THAN 5' WITH NON-WALKING SURFACE (TYPE 4) BLENDED TRANSITION WITH TURNING SPACE AT TOP (TYPE 5) GENERAL NOTES: 1. SIDEWALK RAMPS SHALL HAVE A COARSE BECOM-RAIN TRANSVERSE TO THE SLOPE OF THE RAMS. 2. VERTICAL SURFACE DISCONTINUING AT JOINTS SHALL NOT EXCEED 1/4 INCH. 3. REMOVAL OF SIDEWALK SIDEWALK FOR NEW RAMP INSTALLATIONS SHALL BE TO THE NEAREST EXPANSION OR COMPACTION JOINT. 4. THE DRAWING SLOPE OF THE CURB RAMP SHALL BE CENTERED MAXIMUM BUT SHALL NOT REQUIRE THE RAMP UNLESS TO EXCEED 1/2 FEET. 5. DETECTABLE WARNING SURFACES SHALL BE INSTALLED ON SIDEWALK RAMPS AT PEDESTRIAN STREET CROSSING. PEDESTRIAN BRIDGE BLAKES AND BALBEGAS CROSSINGS ALONG DENSITUDE HIGHWAYS. 6. DETECTABLE WARNING SURFACES SHALL EXTEND LONG VAIN. IN THE DIRECTION OF PEDESTRIAN TRAVEL AND DRAIN THE ENTIRE RAMP OPENING. 7. ALL CASSIDYED VALVES COMPLY WITH PROHIBITED LIMITS OF CLASSIFIABLE DEVICES CALLED AND BE MADE TO COMPLY WITH PROHIBITED RAIL RULE ONCE OFFICIALLY THE LAW. 8. CYLIST DESIGN STANDARDS USE THE PUBLIC BODY OF ANY ACCESSIBILITY GUIDELINES, (REFUNDS) SEE ENGINEERING DIRECTOR 60-30-9.7. 9. CURB RAMPS SHALL BE CONSTRUCTED SO THAT WATER WILL NOT ACCULATE WITHIN THE PEDESTRIAN ACCESS ROUTE. [tbl-0.md](tbl-0.md) [tbl-1.md](tbl-1.md) [tbl-2.md](tbl-2.md) TOWN CAMPUS SIDEWALK CONNECTIONS, JOINT GRANDF, CONNECTICUT PERPENDICULAR RAMP WITH 48" BY-PASS (TYPE 8) PARALLEL RAMP WITH TURNING SPACE CONSTRAINED ON TWO (2) OR MORE SIDES (TYPE 9) GENERAL NOTES: 1. SIDEWALK RAMPS SHALL HAVE A COARSE BROOM FINISH TRANSVERSE TO THE SLOPE OF THE RAMP. 2. VERTICAL SURFACE DISCONFINDRIES AT JOINTS SHALL NOT EXCEED ¼ INCH. 3. REMOVAL OF EXISTING SIDEWALK FOR NEW RAMP INSTALLATIONS SHALL BE TO THE NEAREST EXPANSION OR CONTRACTION JOINT. 4. THE RUNNING SLOPE OF THE CURB RAMP SHALL BE 8.20 PERCENT MAXIMUM BUT SHALL NOT REQUIRE THE RAMP LENGTH TO EXCEED 15 FEET. 5. DETECTABLE WARNING SURFACES SHALL BE INSTALLED ON SIDEWALK RAMPS AT PEDESTRIAN STREET CROSSINGS, PEDESTRIAN REFUSE BLAKES AND RAILROAD CROSSINGS ALONG STREETS OR HIGHWAYS. 6. DETECTABLE WARNING SURFACES SHALL EXTEND 2 FEET MIN. IN THE DIRECTION OF PEDESTRIAN TRAVEL AND SPAN THE ENTIRE RAMP OPENING. 7. ALL OVEREXIST VALVES COMPLY WITH PROWAG GRANT 203 GUIDELINES. UPDATED VALVES WILL BE MADE TO COMPLY WITH PROWAG RINK RULE ONCE OFFICIALLY THE LAW. 8. CTOCE DESIGN STANDARD USE THE PUBLIC RIGHT-OF-WAY ACCESSIBILITY GUIDELINES (PROWAG) SEE ENGINEERING DIRECTIVE 05-2014.7. 9. CURB RAMPS SHALL BE CONSTRUCTED SO THAT WATER WILL NOT ACCUMULATE WITHIN THE PEDESTRIAN ACCESS ROUTE. PARALLEL RAMP WITH TURNING SPACE CONSTRAINED ON ONE SIDE (TYPE 10a) PARALLEL RAMP WITH TURNING SPACE CONSTRAINED ON TWO (2) OR MORE SIDES (TYPE 10b) [tbl-0.md](tbl-0.md) [tbl-1.md](tbl-1.md) CONSTRUCTION NOTES AND DETAILS V TOWN CAMPUS SIDEWALK CONNECTIONS TOWN OF EAST GRANBY 9 CENTER STREET EAST GRANBY, CONNECTICUT 06026 [tbl-2.md](tbl-2.md) [tbl-3.md](tbl-3.md) TOWN CAMPUS SIDEWALK CONNECTICUT, EAST GRANBY, CONNECTICUT 06026 REV. DATE REVISION DESCRIPTION PERPENDICULAR RAMP WITH NON-WALKING SURFACE (TYPE 11) PERPENDICULAR RAMP WITH SIDEWALK CURB AND NON-WALKING SURFACE (TYPE 12) PERPENDICULAR RAMP WITH NON-WALKING SURFACE (TYPE 13) GENERAL NOTES: 1. SIDEWALK RAMP SHALL HAVE A COARSE BROOM FINISH TRASH FREE TO THE SLOPE OF THE RAMP. 2. VERTICAL SURFACE DISCOMPATIBLE AT JOINTS SHALL NOT EXCEED 1/4 INCH. 3. REMOVAL OF EXISTING SIDEWALK FOR NEW RAMP INSTALLATIONS SHALL BE TO THE NEAREST EXPANSION OR CONSTRUCTION JOINT. 4. THE RUNNING SLOPE OF THE CURB RAMP SHALL BE 6.25 PERCENT MAXIMUM BUT SHALL NOT REQUIRE THE RAMP LENGTH TO EXCEED 12 FEET. 5. DETECTABLE WARNING SURFACES SHALL BE REPLACED ON SIDEWALK RAMPS AT PEDESTRIAN CABLE CROSSINGS, PEDESTRIAN BRIDGE GUARDS AND RAILROAD CROSSINGS ALONG STREETS ON HIGHWAYS. 6. DETECTABLE WARNING SURFACES SHALL EXTEND 3 FEET MAX. IN THE DIRECTION OF PEDESTRIAN TRAVEL AND UPON THE EXPIRE RAMP OPENING. 7. ALL SLIDESWIDE VALVES COMPLY WITH PROMISE GRANT 2013 GUIDELINES UPDATED VALUES WILL BE BASED TO COMPLY WITH PROMISE FINAL FIELD PRICE OFFICALLY PER LAW. 8. EFFECT DESIGN STANDARDS USE THE PUBLIC RIGHT-OF-WAY ACCESSIBILITY GUIDELINES (PROMISE SEE ENGINEERING DIRECTIVE 02-2014). 9. CURB RAMPS SHALL BE CONSTRUCTED SO THAT WATER WILL NOT ACCOLATE WITHIN THE PEDESTRIAN ACCESS ROUTE. [tbl-0.md](tbl-0.md) [tbl-1.md](tbl-1.md) CONSTRUCTION NOTES AND DETAILS VI TOWN CAMPUS SIDEWALK CONNECTIONS DESIGNED FOR TOWN OF EAST GRANBY 9 CENTER STREET EAST GRANBY, CONNECTICUT 06026 [tbl-2.md](tbl-2.md) [tbl-3.md](tbl-3.md) TOWN CAMPUS SIDEWALK CONNECTIONS: EAST GRANBY, CONNECTICUT TOWN CAMPUS SIDEWALK CONNECTIONS: EAST GRANBY, CONNECTICUT SINGLE DIRECTION PERPENDICULAR RAMP GRADE BREAK TO THE BACK OF CURB GREATER THAN 5' (TYPE 14) SINGLE DIRECTION PERPENDICULAR RAMP WITH GRADE BREAK TO THE BACK OF CURB THAT IS 5' OR LESS (TYPE 15) SINGLE DIRECTION PERPENDICULAR RAMP RETURN CURB WITH NON-WALKING SURFACE (TYPE 16) SINGLE DIRECTION PERPENDICULAR RAMP NO CURB WITH NON-WALKING SURFACE (TYPE 17) GENERAL NOTES: 1. SIDEWALK RAMPS SHALL HAVE A COARSE BROOM FINISH TRANSVERSE TO THE SLOPE OF THE RAMP. 2. VERTICAL SURFACE DISCONTRUITIES AT JOINTS SHALL NOT EXCEED 1/4 INCH. 3. REMOVAL OF EXISTING SIDEWALK FOR NEW RAMP INSTALLATIONS SHALL BE TO THE NEAREST EXPANSION OR CONTRACTION JO
Only the beginning is shown here; the whole file is searchable. Open the PDF for the rest.
20250507111955711 · PDF, 1 page
Open the PDF download · town site copy
Text read from the scan by OCR (may contain errors)
RFP Town Campus Sidewalk Connections Project East Granby Town Hall May 6, 2025 1:00pm | COMPANY | BID | | --- | --- | | Pontes Construction LLC Northwindham, CT | $621,250.00 | | Detour Construction Ludlow, MA | $405,860.00 | | Mather Corporation Bloomfield | $598,000 | | Nunes Connecticut, Inc. | $533,125 | | Four Seasons Landscaping Inc. | $440,425 | | B&W Paving & Landscaping LLC | $599,055 |
Text of the post itself (1 paragraph)
1419 Addendum 1 EG Town Campus 2025 04 28 Download RFP Project Manual Published 1419 Town Campus Sidewalk Specification Download RFP 1419 Town Campus Sidewalk Connections Maps Full Set March 7 2025 Download 20250507111955711 Download
From the town's website: https://eastgranbyct.org/rfp-town-campus-sidewalk-connections-project/.