New school building · Granby

Summarized Nov 23, 2026 covers records through Nov 2, 2026 7 events Check for newer records Follow this topic (RSS)

Read as: A project to build a new school building: planning, cost, site, votes.

AI-generated answer, checked against the pages it cites (dates, boards and dollar figures). It reflects the records as of Nov 23, 2026; things may have changed since. Open the PDF page to confirm.

Granby is weighing school building work, including a possible middle school renovation. The town set the middle school plan aside for now and turned to athletic fields.

Where it stands: In October 2026 a consulting firm presented its school design experience to the Public Building and Capital Project Committee. The outcome of any new school building decision is not in the records yet.

Timeline

  1. Jan 7, 2026

    Board of Education, Granby

    The Board of Education said there was insufficient information to move ahead with middle school renovations, so focus shifted to athletic fields.

    Board of Education, Jan 7, 2026 (PDF p. 2)

  2. Mar 2, 2026

    Board of Selectmen, Granby

    A request was made for the Board of Selectmen to create a Public Building and Capital Project Committee to oversee Board of Education capital projects that may get state reimbursement.

    Board of Selectmen, Mar 2, 2026 (PDF p. 204)

  3. Jun 1, 2026

    Board of Selectmen, Granby

    Appointments were listed for the new Public Building and Capital Project Committee under state and town charter rules.

    Board of Selectmen, Jun 1, 2026 (PDF p. 12)

  4. Aug 17, 2026

    Board of Selectmen, Granby

    The Public Building and Capital Projects Committee was scheduled to meet on September 9, 2026 at the Senior Center.

    Board of Selectmen, Aug 17, 2026 (PDF p. 3); Board of Selectmen, Sep 21, 2026 (PDF p. 5)

  5. Oct 5, 2026

    Board of Selectmen, Granby

    An energy efficiency process was described as tied to a December middle school bond, and no board action was required at that time.

    Board of Selectmen, Oct 5, 2026 (PDF p. 14)

  6. Oct 14, 2026

    Public Building and Capital Project Committee, Granby

    A consulting firm presented its experience with school design and state school construction grant offices.

    Public Building and Capital Project Committee, Oct 14, 2026

  7. Nov 2, 2026

    Board of Selectmen, Granby

    The town had $1,598,921 of school bonds authorized and unissued at June 30, 2026. $1,598,921

    Board of Selectmen, Nov 2, 2026 (PDF p. 91)

Related searches: middle school renovationPublic Building Committeeschool bondGranby school constructionathletic fields

Show the page excerpts this answer is based on (8)
Board of Education, Jan 7, 2026, minutes, page 2
APPROVED ● The cast list for The Little Mermaid has been announced, and rehearsals will begin soon. The production will take place in March and will include an additional performance on Thursday evening. Reports and Discussion: ● Middle School Renovations and Athletic Facility: ○ Chair Monica Logan discussed both items and reviewed the timeline of CPPAC meetings and discussions dating back to Octo
Board of Selectmen, Mar 2, 2026, packet, page 204
… ordinance boards, commissions, departments or offices…” Additionally, upon its creation, this committee shall also be empowered to act as the oversight for Board of Education capital projects where State reimbursement is possible as required by Connecticut General Statutes Chapter (CGS) 173 (Public School Building Projects), Section 10 - 292 (v) . Further, that CGS section requires at least one
Board of Selectmen, Jun 1, 2026, packet, page 12
… ntil the expiration of their elected office or until a successor is appointed and qualified. All appointments are consistent with the following provisions of the Connecticut General Statutes and the Granby Town Charter: Connecticut General Statutes • Connecticut General Statutes § 10-292(v) (Public School Building Project) • Connecticut General Statutes § 9-167a (Minority Representation) Town of
Board of Selectmen, Aug 17, 2026, minutes, page 3
… tudent Liaison Madeline Ayotte) Selectman Neumann announced that the next meeting of the Public Building and Capital Projects Committee is scheduled for September 9, 2026, at 6:00 p.m. at the Senior Center. Student Liaison Madeline Ayotte shared that freshman orientation is August 26, 2026, and the new school year begins on August 27, 2026. 10. PUBLIC SESSION The were no public comments. 11. EXE
Board of Selectmen, Sep 21, 2026, packet, page 5
… tudent Liaison Madeline Ayotte) Selectman Neumann announced that the next meeting of the Public Building and Capital Projects Committee is scheduled for September 9, 2026, at 6:00 p.m. at the Senior Center. Student Liaison Madeline Ayotte shared that freshman orientation is August 26, 2026, and the new school year begins on August 27, 2026. 10. PUBLIC SESSION The were no public comments. 11. EXE
Board of Selectmen, Oct 5, 2026, packet, page 14
… an Energy Efficiency Bid Administration Agreement Communication 1. Town and BOE buildings will enjoy a higher level of energy efficiency 2. Grants and zero interest loans will be secured first, reducing taxpayer replacement costs 3. Work accomplished by this process will stretch the December Middle School bonding if approved by the residents of the Town 4. Efficiency improvements completed now w
Public Building and Capital Project Committee, Oct 14, 2026, packet, page 74
… ode, Energy, and HVAC Improvements – Connecticut General Assembly: Boiler Plant Replacement • Regulatory Agencies: BL Companies has extensive experience coordinating with regulatory bodies such as: – Connecticut Department of Administrative Services (CTDAS) – Bureau of School Facilities / Office of School Construction Grants – Connecticut Department of Energy and Environmental Protection (CTDEEP
Board of Selectmen, Nov 2, 2026, packet, page 91
… (50) NOTE 6 LONG-TERM DEBT (CONTINUED) General Obligation Bonds (Continued) The definition of indebtedness includes bonds outstanding in addition to the amount of bonds authorized and unissued against which debt is issued and outstanding. The Town has $7,572,676 of general purpose and $1,598,921 of school bonds authorized and unissued at June 30, 2026. The total overall statutory debt limit for