Towns / Granby / Public Building and Capital Project Committee / Oct 14, 2026
Public Building and Capital Project Committee, Oct 14, 2026
Granby Public Building and Capital Project Committee Hide agendas that already have minutesDocuments
| Type | Document | Pages | Open |
|---|---|---|---|
| minutesminutes | Public Building & Capital Project Committee Regular Meeting Minutes | 2 | PDF download · town site |
| agenda | Public Building & Capital Project Committee Regular Meeting | 2 | PDF download · town site |
| packetpacket | Public Building & Capital Project Committee Regular Meeting (packet) Sanitized copy: scripts and attachments were removed and the result checked. The original is kept offline. Not attached: this packet is 32 MB, too large to host here. Use the town site link. |
109 | town site |
Summary of the minutes
AI-generated summary. Each line links to the PDF page it came from; check it before relying on it.
Read the official minutes (PDF, 2 pages) The PDF is the record; this summary is a guide to it.
The committee approved the September 9, 2026 minutes and voted 9-0-0 to hold off on selecting an engineering firm for the athletic field project and the middle school MEP project. Member questions are due to the chair by October 21, 2026, with a final selection planned for the November 12, 2026 meeting.
Decisions (4) · all reported votes
- Approval of PBCPC Regular Meeting Minutes from September 9, 2026
Approved minutes of September 9, 2026 as presented
Vote: Motion by W. Pascucci, seconded by M. Lengvarsky, carried 9-0-0 · p. 1 - Proposal Acceptance - Engineering Firm for Athletic Field Project
Acceptance of proposal delayed; committee to send questions to firms via chair and select firm at November 12, 2026 meeting
Vote: Motion by A. Anderson, seconded by M. Gottlieb, carried 9-0-0 · p. 1 - Proposal Acceptance - Engineering Firm for MEP for Middle School
Acceptance of proposal delayed; all member questions on the two proposals to be sent to M. Neumann by October 21, 2026, forwarded to M. Walsh for distribution to contractors, and firm to be selected at November 12, 2026 meeting
Vote: Motion by A. Anderson, seconded by M. Gottlieb, carried 9-0-0 · p. 1 - Adjournment and next meeting
Committee adjourned at approximately 6:25 p.m.; next regular meeting set for Wednesday, November 12, 2026, at 6 p.m. at the Senior Center
Vote: Motion by A. Anderson, seconded by M. Gottlieb, carried 9-0-0 · p. 2
Also discussed (1)
- Requests for hard copy of proposal materials: A. Anderson and M. Gottlieb requested all proposal materials in hard copy; M. Walsh indicated this would be done · p. 1
Summary of the agenda: Public Building & Capital Project Committee Regular Meeting
AI-generated summary.
This is the agenda for the Granby Public Building & Capital Project Committee special meeting on October 14, 2026, at the Senior Center. Items on the agenda include approval of three sets of prior minutes and proposed acceptance of engineering firm proposals for the athletic field project and the middle school MEP work.
On the agenda (5)
- Approval of PBCPC Regular Meeting Minutes - September 9, 2026 · p. 1
- Approval of PBCPC Special Meeting Minutes - September 16, 2026 · p. 1
- Approval of PBCPC Special Meeting Minutes - September 23, 2026 · p. 1
- Proposal Acceptance - Engineering Firm For Athletic Field Project · p. 1
- Proposal Acceptance - Engineering Firm For MEP For Middle School Project · p. 1
This PDF is a scan; its text was read by OCR and may contain errors.
Full text of the documents
View the minutes PDF on this page (Public Building & Capital Project Committee Regular Meeting Minutes)
Text of the minutes (Public Building & Capital Project Committee Regular Meeting Minutes, 2 pages)
Page 1 · open in PDF
TOWN OF GRANBY PUBLIC BUILDING & CAPITAL PROJECT COMMITTEE REGULAR MEETING MINUTES OCTOBER 14, 2026 PRESENT: Chairman Mark Neumann, Anne Adamson, Peter Anderson, Mark Gottlieb, Christopher Lavigne, Michael Lengvarsky, Kent McCord, William Pascucci and David Peling ALSO PRESENT: Mike Walsh, Town Manager ABSENT: Kent McCord 1. PLEDGE OF ALLEGIANCE 2. MINUTES 2.I. Approval of PBCPC Regular Meeting Minutes from September 9, 2026 ON A MOTION by W. Pascucci, seconded by M. Lengvarsky, the committee voted (9-0-0) to approve the minutes of September 9, 2026, as presented. 3. NEW BUSINESS 3.I. Proposal Acceptance- Engineering Firm for Athletic Field Project M. Walsh, Town Manager, provided an overview of the RFP process to date for both this project and the next agenda item. M. Walsh suggested that committee members take additional time to review the proposals submitted and send questions, via the committee chair, to the firms, and to delay acceptance of a proposal for each project until the next meeting of this committee on November 12, 2026. M. Neumann opened these suggestions to the committee for discussion. Discussion on both proposals ensued. 3.II. Proposal Acceptance- Engineering Firm for MEP for Middle School See above minutes regarding 3.1. ON A MOTION by A. Anderson, seconded by M. Gottlieb, the committee voted (9-0-0) to send all committee member questions on the two above proposals to M. Neumann by October 21, 2026, who would then send them to M. Walsh for distribution to the contractors, and to further discuss the proposals and select an engineering firm at the next regular meeting of this committee on November 12, 2026. An email sent by one contractor supplementing their original RFP submission was shared with the committee. A. Anderson and M. Gottlieb requested all proposal materials be shared with them in hard copy, and M. Walsh indicated that would be done. 4. DISCUSSION OF ACTION ITEMS FOR THE NEXT MEETING The Town Manager and Chairman will create the agenda for the November meeting, which will include discussion of the proposals and any questions sent to the contractors, as well as
Page 2 · open in PDF
any responsive information received. 5. PUBLIC COMMENT None 6. ADJOURNMENT: ON A MOTION by A. Anderson, seconded by M. Gottlieb, the committee voted (9-0-0) to adjourn the meeting at approximately 6:25 p.m. The next regular meeting of the Public Building & Capital Project Committee is scheduled for Wednesday, November 12, 2026, at 6 p.m. at the Senior Center. Respectfully submitted, Stephanie D’Ambrose Recording Secretary
View the agenda PDF on this page (Public Building & Capital Project Committee Regular Meeting)
Text read from the scanned agenda (OCR) (Public Building & Capital Project Committee Regular Meeting, 2 pages)
Page 1 · open in PDF
Join Zoom Meeting https://us02web.zoom.us/j/83482016832?pwd=bHpaXb1faLpO7NAhvYGlCypyGplyoz.1 Meeting ID: 834 8201 6832 Passcode: 902481 TOWN OF GRANBY Public Building & Capital Project Committee Special Meeting Agenda Wednesday, October 14, 2026 6:00 p.m. Senior Center 1. Pledge Of Allegiance 2. Minutes 2.I. Approval Of PBCPC Regular Meeting Minutes - September 9, 2026 Documents: PBCPC MINUTES 09-09-2026.PDF 2.II. Approval Of PBCPC Special Meeting Minutes - September 16, 2026 Documents: PBCPC MINUTES 09-16-2026.PDF 2.III. Approval Of PBCPC Special Meeting Minutes - September 23, 2026 Documents: PBCPC MINUTES 09-23-2026.PDF 3. New Business 3.I. Proposal Acceptance - Engineering Firm For Athletic Field Project Documents: BENESCH SCOPE AND FEE FOR INTEGRATED SERVICES - GRANBY ATHLETIC FIELDS.PDF BSC GROUP PROPOSAL.PDF SLR GRANBY FIELDS PROPOSAL.PDF 3.II. Proposal Acceptance - Engineering Firm For MEP For Middle School Project Documents: BL COMPANIES MEP WORK AT GRANBY MIDDLE SCHOOL.PDF H2M MEP LP262054 GRANBY MS HVAC.PDF 4. Discussion Of Action Items For The Next Meeting 5. Adjournment
Page 2 · open in PDF
The next regular meeting of the Public Building & Capital Project Committee is scheduled for Thursday, November 12, 2026 at 6 p.m. at the Senior Center.
Text of the packet (Public Building & Capital Project Committee Regular Meeting (packet), 109 pages)
Page 1
Join Zoom Meeting https://us02web.zoom.us/j/83482016832?pwd=bHpaXb1faLpO7NAhvYGlCypyGpIyoz.1 Meeting ID: 834 8201 6832 Passcode: 902481 TOWN OF GRANBY Public Building & Capital Project Committee Special Meeting Agenda Wednesday, October 14, 2026 6:00 p.m. Senior Center Pledge Of Allegiance Minutes Approval Of PBCPC Regular Meeting Minutes - September 9, 2026 PBCPC MINUTES 09-09-2026.PDF Approval Of PBCPC Special Meeting Minutes - September 16, 2026 PBCPC MINUTES 09-16-2026.PDF Approval Of PBCPC Special Meeting Minutes - September 23, 2026 PBCPC MINUTES 09-23-2026.PDF New Business Proposal Acceptance - Engineering Firm For Athletic Field Project BENESCH SCOPE AND FEE FOR INTEGRATED SERVICES - GRANBY ATHLETIC FIELDS.PDF BSC GROUP PROPOSAL.PDF SLR GRANBY FIELDS PROPOSAL.PDF Proposal Acceptance - Engineering Firm For MEP For Middle School Project BL COMPANIES MEP WORK AT GRANBY MIDDLE SCHOOL.PDF H2M MEP LP262054 GRANBY MS HVAC.PDF Discussion Of Action Items For The Next Meeting Adjournment The next regular meeting of the Public Building & Capital Project Committee is scheduled for Thursday, November 12, 2026 at 6 p.m. at the Senior Center. 1. 2. 2.I. Documents: 2.II. Documents: 2.III. Documents: 3. 3.I. Documents: 3.II. Documents: 4. 5.
Page 2
Join Zoom Meeting https://us02web.zoom.us/j/83482016832?pwd=bHpaXb1faLpO7NAhvYGlCypyGpIyoz.1 Meeting ID: 834 8201 6832 Passcode: 902481 TOWN OF GRANBY Public Building & Capital Project Committee Special Meeting Agenda Wednesday, October 14, 2026 6:00 p.m. Senior Center Pledge Of Allegiance Minutes Approval Of PBCPC Regular Meeting Minutes - September 9, 2026 PBCPC MINUTES 09-09-2026.PDF Approval Of PBCPC Special Meeting Minutes - September 16, 2026 PBCPC MINUTES 09-16-2026.PDF Approval Of PBCPC Special Meeting Minutes - September 23, 2026 PBCPC MINUTES 09-23-2026.PDF New Business Proposal Acceptance - Engineering Firm For Athletic Field Project BENESCH SCOPE AND FEE FOR INTEGRATED SERVICES - GRANBY ATHLETIC FIELDS.PDF BSC GROUP PROPOSAL.PDF SLR GRANBY FIELDS PROPOSAL.PDF Proposal Acceptance - Engineering Firm For MEP For Middle School Project BL COMPANIES MEP WORK AT GRANBY MIDDLE SCHOOL.PDF H2M MEP LP262054 GRANBY MS HVAC.PDF Discussion Of Action Items For The Next Meeting Adjournment The next regular meeting of the Public Building & Capital Project Committee is scheduled for Thursday, November 12, 2026 at 6 p.m. at the Senior Center. 1. 2. 2.I. Documents: 2.II. Documents: 2.III. Documents: 3. 3.I. Documents: 3.II. Documents: 4. 5.
Page 3
TOWN OF GRANBY PUBLIC BUILDING & CAPITAL PROJECT COMMITTEE REGULAR MEETING MINUTES SEPTEMBER 9, 2026 PRESENT: Chairman Mark Neumann, Anne Adamson, Peter Anderson, Mark Gottlieb, Christopher Lavigne, Michael Lengvarsky, Kent McCord, William Pascucci and David Peling ALSO PRESENT: Cheri Burke, Superintendent of School and Mike Walsh, Town Manager ABSENT: None 1. PLEDGE OF ALLEGIANCE 2. MINUTES 2.I. Approval of PBCPC Regular Meeting Minutes – August 12, 2026 ON A MOTION by W. Pascucci, seconded by D. Peling, the committee voted (9-0-0) to approve the minutes of August 12, 2026, as presented. 3. NEW BUSINESS 3.I. Subcommittee Recommendations – Engineering Interviews The subcommittee met and selected the six engineering firms to be interviewed by the PBCPC at a special meeting of the full committee on Wednesday, September 16, 2026. The selected firms are: Benesch, BL Companies, BSC Group, H2M, SLR and pHLow. 3.II. Set a Special Meeting for September 16, 2026, at 6 p.m. at the Senior Center ON A MOTION by A. Adamson, seconded by K. McCord, the committee voted (9-0-0) to set a special meeting of the Public Building and Capital Project Committee for Wednesday, September 16, 2026. ON A MOTION by W. Pasucci, seconded by M. Gottlieb, the committee voted (9-0-0) to set a nother special meeting of the Public Bui lding and Capital Project Committee for Wednesday, September 23, 2026, to discuss the inter views and select an engineering firm. 3.III. Agenda Amendment to Set a Special Meeting for September 23, 2026 ON A MOTION by W. Pasucci, seconded by D. Peling, the committee voted (9-0-0) to amend the agenda to include an item to add the special meeting on September 23, 2026, and accept the motion. 4. DISCUSSION OF ACTION ITEMS FOR THE NEXT MEETING The Town Manager and Chairman will create the agenda for the October meeting. 5. PUBLIC COMMENT Curt Johnson, One Fielding Woods, Wes t Granby commented on the capital projects and supports the hiring of an engineering firm.
Page 4
PBCPC Minutes 9/9/26 Page 2 6. ADJOURNMENT: ON A MOTION by D. Peling , seconded by W. Pascucci , the committee voted (9-0-0) to adjourn the meeting at 7:00 p.m. The next regular meeting of the Public Building & Capital Project Committee is scheduled for Wednesday, October 14, 2026, at 6p.m. at the Senior Center. Respectfully submitted, Betsy Mazzotta Recording Secretary
Page 5
TOWN OF GRANBY PUBLIC BUILDING & CAPITAL PROJECT COMMITTEE SPECIAL MEETING MINUTES SEPTEMBER 16, 2026 PRESENT: Chairman Mark Neumann, Anne Adamson, Peter Anderson, Mark Gottlieb, Michael Lengvarsky (via Zoom), Kent McCord and William Pascucci ALSO PRESENT: Cheri Burke, Superintendent of School and Mike Walsh, Town Manager ABSENT: David Peling, Christopher Lavigne 1. PLEDGE OF ALLEGIANCE 2. MINUTES 2.I. None 3. NEW BUSINESS 3.I. Engineering Firm Interviews The committee heard presentations and interviewed the six engineering firms identified by the subcommittee for further consideration and completed scoring sheets for each. The Town Manager will compile the scoring sheets and distribute the summary to the committee before the next meeting. A special meeting of the Public Building and Capital Projects committee will be held on Wednesday, September 23, 2026, at 6:00 p.m. at the Senior Center to review the results and select the firm(s) to engage for the projects. 4. DISCUSSION OF ACTION ITEMS FOR THE NEXT MEETING The Town Manager and Chairman will create the agenda for the October meeting. 5. ADJOURNMENT: ON A MOTION by W. Pascucci, seconded by P. Anderson, the committee voted (6-0-0) to adjourn the meeting at 9:37 p.m. The next regular meeting of the Public Building & Capital Project Committee is scheduled for Wednesday, October 14, 2026, at 6p.m. at the Senior Center. Respectfully submitted, Betsy Mazzotta Recording Secretary
Page 6
TOWN OF GRANBY PUBLIC BUILDING & CAPITAL PROJECT COMMITTEE SPECIAL MEETING MINUTES SEPTEMBER 23, 2026 PRESENT: Chairman Mark Neumann, Anne Adamson, Peter Anderson, Mark Gottlieb, Christopher Lavigne, Michael Lengvarsky, William Pascucci and David Peling ALSO PRESENT: Mike Walsh, Town Manager ABSENT: Kent McCord 1. PLEDGE OF ALLEGIANCE 2. MINUTES 2.I. None 3. NEW BUSINESS 3.I. Engineering Firm Selection – Review Scoring with Discussion The committee discussed the scoring and the six engineering firms interviewed at the PBCPC meeting on September 16, 2026. The following motions were made at the conclusion of the group discussion. ON A MOTION by M. Lengvarsky, seconded by M. Gottlieb, the Public Building and Capital Project Committee voted ( 7-0-1) to return to the engineering firms of Benesch, BSC Group and SLR with a detailed Request for Proposal on the settling issue related to the high school athle tic fields and to request a proposed solution and an est imated cost. C. Lavigne did not participate in the interviews and therefore abstained from the vote. ON A MOTION by M. Gottlieb, seconded by A. Adamson, the Public Building and Capital Project Committee voted (7-0-1) to recommend the engineering firm of Benesch as the on-call engineering firm for use by the Town of Granby for projects including the pickleball courts and bathroom at Salmon Brook Park. The agreement would not include the high school athletic fields, MEP services for the middle school or the sewer project. C. Lavigne did not participate in the interviews and therefore abstained from the vote. ON A MOTION by M. Lengvarsky, seconded by A. Adamson, the Public Building and Capital Project Committee voted ( 7-0-1) to return to the engineering firms of BL Companies and H2M and request a detailed report on their MEP capabilities. C. Lavigne did not participate in the interviews and therefore abstained from the vote. ON A MOTION by W. Pascucci , seconded by M. Gottlieb , the Public Building and Capital Project Committee voted ( 7-0-1) to recommend pHlow as the on -call engineering firm for use by the Town of Granby for sewer projects. C. Lavigne did not participate in the interviews and therefore abstained from the vote. 4. DISCUSSION OF ACTION ITEMS FOR THE NEXT MEETING Town Manager Mike Walsh will provide an update to the committee on the follow up requests for the high school athletic fields project and the MEP services.
Page 7
PBCPC Minutes 9/23/26 Page 2 5. ADJOURNMENT: ON A MOTION by D. Peling, seconded by M. Lengvarsky, the committee voted (8-0-0) to adjourn the meeting at 7:02 p.m. The next regular meeting of the Public Building & Capital Project Committee is scheduled for Wednesday, October 14, 2026, at 6p.m. at the Senior Center. Respectfully submitted, Betsy Mazzotta Recording Secretary
Page 8
Page 9
200 Glastonbury Blvd., Suite 201 Glastonbury, CT 06033 www.benesch.com P 860-633-8341 October 13, 2026 Mr. Mike Walsh Granby Town Manager 15 North Granby Road Granby, CT 06035 RE: Proposal for Integrated Design Services Athletic Fields at The High School Complex Granby, Connecticut Dear Mr. Walsh: Alfred Benesch & Company (Benesch) is pleased to submit this proposal to the Town of Granby, and specifically the Public Building and Capital Project Committee (PBCPC) for integrated design services in support of the renovation of the track and fields at the Granby Memorial High Schools at your property at 313 Salmon Brook Street, Granby, Connecticut. This proposal has been prepared to present our proposed scope of services and associated fee in support of the project as your land use consultant and site/civil engineer. We have prepared this proposal based upon the following understanding of your needs and circumstances which have defined the scope of services. 1. Our base scope of services includes base mapping, geotechnical engineering, site/civil engineering, landscape architecture, land use permitting, and construction phase services. The proposal has been segregated into two (2) main components, as requested: Phase 1 – Investigation Phase 2 – Design and Engineering 2. The town constructed the high school track and field in approximately 2013. Around 2020, the track and field started experiencing local sinking/depressions. The issue has become so extreme that no track meets are being held at the facility and if the existing sink holes on the field expand it is possible the field will be unusable for high school competition events. In the last couple years, geotechnical subsurface exploration and analysis have been performed. 3. The proposed development includes the following: • The renovation of the high school track/field, as well as converting the existing stadium lights to LED. • The renovation of the synthetic turf practice field adjacent to the stadium field. The conversion of the grass baseball field to a synthetic turf baseball/softball/soccer multipurpose field. 4. Based on a review of Town GIS mapping, a 100-year floodplain is located on the northern portion of the property and does not appear to encroach into the areas proposed for development. If any portion of the
Page 10
Mike Walsh Page | 2 project encroaches into the floodplain, the design will need to account for the local floodplain requirements. 5. Town GIS mapping indicates wetland existing along the northern portion of the property line. The project will therefore require wetlands delineation and associated permitting through the Town Inland Wetlands Commission. 6. The CT DEEP Natural Diversity Database Area Map for Granby indicates that there may be State or Federal Listed Species or Significant Natural Communities on the Site. A formal NDDB review by CT DEEP will be required by DEEP as part of their General Stormwater Construction Permit. Archeological and/or Listed Species studies may be required by DEEP. If required, these studies will be provided as an add service. 7. Based upon our site walk and associated discussion with the Town on October 2, 2026, we have thought about possible ways to bring value to this project, which may not have previously been considered by the PBCPC. We have briefly summarized them below and will discuss them in more detail with the PBCPC should we be selected to design this project. Synthetic Turf Practice Field – there are not apparent sink holes/depressions or any known drainage issues with this field. Since this was constructed in approximately 2013, and it is functioning as designed, there is no reason to believe it needs a full replacement. It may be prudent to simply replace the existing synthetic turf and infill and leave the aggregate base, drainage and concrete nailer curb in place. Typically the infill needs to be replaced every seven (7) years or so, and the turf itself needs to be replaced every 14 to 15 years. By replacing only the turf, and not the entirety of the field, this could save the town up to $1M. Alternates – although not specified in the RFQ/RFP, it may be prudent to consider additional site items beyond the fields. This will be a state-of-the-art high school athletic complex so the items below may want to be considered. We have built an Add Services Scop and Fee into our proposal, which captures the design effort required to design these additional items. These items could be bid as Alternates, and, at the very least, the utility infrastructure could be put in place to allow the future construction of these items without damaging the new fields. If the funds are not available to construct some or all of these items, the design would be in place so that they could be constructed in the future. Following are alternate design items for consideration: Connectivity of all the fields and the school. Restrooms for the stadium field. Restrooms for the baseball/softball/soccer field. Lighting for the baseball/softball/soccer field. Dugouts for the baseball/softball field. Moveable fencing for baseball and softball to provide outfield fencing for each of these sports during games. We describe our approach to these items in detail in Section 2.6 - Alternate Design Approach and Scope of this proposal. We have not provided a fee for this alternate design. If the PBCPC wanted to pursue this alternate design, we could negotiate a scope and fee, based on PCBPC direction. Furthermore, at the end of this scope and fee, we have provided a sample design packet to help you understand our design process and the potential for community excitement and fundraising opportunities.
Page 11
Mike Walsh Page | 3 1.0 SCOPE OF SERVICES Benesch’s scope of services for the project has been segregated into the following phases: • Phase 1 – Investigation • Phase 2 – Design & Engineering Our scope of services for each of these phases is presented below. PHASE 1 – INVESTIGATION We have reviewed the previously performed geotechnical studies, as well as the subsurface exploration requirements that will be necessary for design and construction of both the track/field and the baseball field. It is our opinion that the previous studies do not provide enough information for us to be comfortable designing a reconstruction. Following are the reasons we feel the previous studies are not complete: • The existing borings don't have any density or consistency info (i.e. no SPT blow counts in the borings) which are typically used to determine the potential for consolidation of the sand and silt fill and natural materials encountered • 3 (HA-5, HA-6, and GP-22) of the 27 borings didn't get through the existing fill, to depth of 10 to 15 feet below existing grade, so depth of fill could be deeper at these locations which would impact the potential depth of remediation of unsuitable soils • With as much as 15'+ of existing fill (HA-6), additional depth of drilling into the natural soils, potentially through the glaciofluvial deposit, and sampling/testing would be needed to determine the condition of the underlying natural soils to determine potential future settlement if all existing fill was removed and replaced with controlled earth fill. Using GZA as our subconsultant, following is our project approach to geotechnical exploration, analysis and design for both the baseball field and the track/football field: Baseball Field Project Approach We understand that the existing baseball field has natural grass turf and will be converted to a synthetic turf field. We are not aware of any below-grade issues with the existing field. Therefore, we will perform a series of test borings at the existing baseball field to evaluate the depth to native soil and the suitability to support the proposed structures. GZA will also collect soil samples for laboratory testing to evaluate surface water infiltration. We propose to drill three days of test borings. In three days, we anticipate drilling 16 test borings with a track- mounted drill rig using hollow stem augers: eight borings in the baseball field, four borings at proposed light poles, two borings at the proposed dugouts and two borings at the proposed restrooms. The borings in the field will be drilled to depths of 6 feet below grade or refusal. If loose soil, organics, or wood are encountered at 6 feet, the borings may extend deeper. If shallow refusal is encountered before target depth, an offset will be performed as time allows. The test borings for the proposed structures will be drilled to depths of 15 to 20 feet below grade, or refusal. GZA personnel will log and monitor the subsurface explorations. Soil samples will be classified based on the Modified Burmister classification system. The field engineer will locate the explorations by line of sight and tape
Page 12
Mike Walsh Page | 4 measurements from existing site features. Surface elevations will be interpolated from existing topographic plans or publicly available topographic data. Selected soil samples will be submitted to a subcontracted geotechnical laboratory to confirm visual classification and provide engineering parameters for design. Testing will include six (6) sieve and hydrometer analysis. We will organize and interpret the subsurface data, perform geotechnical analyses, and prepare an electronic copy of the Geotechnical Engineering Report in PDF format. The engineering recommendations for design and construction presented in the report will be based on the current Connecticut Building Code (2021 International Building Code with the 2022 Connecticut State Amendments). Note, the Connecticut Building Code was scheduled to be revised to the 2024 IBC with amendments on July 1, 2026, but currently the new Code is awaiting approval by the Legislative Regulation Review Committee of the Connecticut General Assembly. Therefore, the effective date of the new Code has been delayed. The Geotechnical Engineering Report will include. • A subsurface exploration location plan and logs of explorations; • Narrative interpretation of the subsurface soil and groundwater conditions observed and their implications for the project; • Laboratory testing including grain size and hydrometer analyses; • Recommendations for shallow foundations, including bearing strata, ground improvement (if applicable), allowable bearing stresses, minimum embedment for frost protection, and estimated total and differential settlement, subgrade preparation, and any other geotechnical parameters that may be required for foundation design; • Recommendations for light pole foundations; • Recommended coefficient of friction between cast-in-place concrete and soil for resistance to lateral loads; • Recommendations for slabs-on-grade, including subgrade modulus and subgrade preparation; • Geotechnical seismic Site class and liquefaction potential based on the Building Code; • Recommendations for permanent groundwater control (underdrain or waterproofing), if applicable, • Recommendations for excavation slope stability, support-of-excavation (if required), and dewatering/temporary groundwater control during construction; • Recommendations for the new field, footing and slab subgrade preparations; • Recommended backfill materials; and • Recommendations for re-use of excavated materials. Track/Football Field Project Approach We understand that the existing track and synthetic turf field have settled and the worst settlement is occurring along the eastern side of the track. Based on the “Subsurface Data and Geotechnical Considerations Report”’ dated November 8, 2022 and “Subsurface Conditions and Geotechnical Data Report”, dated July 28, 2025 by Haley and Aldrich (H&A), we understand that the current track was constructed between 2012 and 2013. HA was engaged to evaluate the settlement and performed thirty-four (34) geoprobe explorations around the track. The subsurface explorations found a relatively thick layer of Fill which contained wood, topsoil and organic soil in the northeast corner of the track. The subsurface explorations extended up to 15 feet below grade, and some explorations did not penetrate the Fill. GZA assumes that the settlement in this area is likely caused by decomposition of the organic material in the Fill, very loose fill, or the migration of soil into void spaces between oversized material in the Fill such as cobbles, boulders, stumps, or logs. The Geoprobe sampler used during the H&A explorations has a relatively small diameter, does not provide data regarding soil density, and does not
Page 13
Mike Walsh Page | 5 provide a representative sample of the Fill or the materials in the Fill which could be causing the settlement (i.e. stumps, logs, etc.). Therefore, GZA recommends two test pits along the east side of the Site to evaluate the Fill and whether deleterious materials are present. We also propose test borings to evaluate the thickness of the Fill, density of the fill and depth to naturally deposited soil. The test borings will be completed both in the area of settlement (eastern side of track) and non-settled areas (western side) to help identify the cause of the settlement. We propose two days of test borings and one day of test pits at the existing turf field and track. In two days, we anticipate drilling four test borings with a track-mounted drill rig using hollow stem augers and two test pits in the vicinity of observed settlement. The borings will be drilled to depths of 20 feet or to naturally deposited soil, whichever is deeper. If shallow refusal is encountered before target depth, an offset will be performed as time allows. Groundwater observations will be recorded on the exploration logs. Split-spoon sampling and Standard Penetration Testing (SPT) will be performed in general accordance with ASTM D-1586. Samples will be obtained semi-continuously. Groundwater depths will be measured in the borehole prior to backfilling. We will hire a synthetic turf contractor to remove and restore the turf at the test pit locations. The test pits will be excavated up to 8 feet or refusal, whichever occurs first. Test pits will be backfilled with spoils in compacted 1-foot lifts. We assume turf subgrade will be restored to existing conditions by the synthetic turf contractor. GZA personnel will log and monitor the subsurface explorations. Soil samples will be classified based on the Modified Burmister classification system. The field engineer will locate the explorations by line of sight and tape measurements from existing site features. Surface elevations will be interpolated from existing topographic plans or publicly available topographic data. Selected soil samples will be submitted to a subcontracted geotechnical laboratory to confirm visual classification and provide engineering parameters for design. Testing will include six (6) sieve and hydrometer analysis. We will organize and interpret the subsurface data, perform geotechnical analyses, and prepare an electronic copy of the Geotechnical Engineering Report in PDF format. The Geotechnical Engineering Report will include. • A subsurface exploration location plan and logs of test borings; • Our narrative interpretation of the subsurface soil and groundwater conditions observed and their implications for the project including an evaluation of the track and field settlement identifying the likely cause of the failure. • Laboratory testing including grain size and hydrometer analyses; • Identification and analyses of key geotechnical issues associated with design and construction; • Recommendations for subgrade preparations; • Recommendations for drainage of the new track and field; • Recommendations for materials and compaction requirements; and • Recommendations for reuse of on-site materials.
Page 14
Mike Walsh Page | 6 PHASE 2 – DESIGN & ENGINEERING Task 2.1 – Base Mapping Task 2.1.1 – Wetlands Delineation Using our subconsultant, Martin Brogie, Inc. (MBI) will conduct field investigations to identify and delineate local and state defined resource areas. Delineations will be performed within the project site in accordance with state methodology [Connecticut Inland Wetlands and Watercourses Act (Section 22a-36 to 22a-45 as amended, of the Connecticut General Statutes), and the Town of Granby, CT Inland Wetlands and Watercourses Regulations.] An Onsite Soil Investigation Report will be prepared. The report will contain the following: • Wetland boundary delineation methodology. • Site description. • Wetland and upland soil description. Task 2.1.2 – Survey Benesch will prepare base mapping sufficient for design, permitting and construction. We will prepare an A2 boundary survey for the northeast corner of the site, where the baseball field is relatively close to the property line. We will prepare T2 topography on the portions of the site that will be utilized for new construction. Scope items in the phase include the following: • Research Town and State records for title information, existing mapping and easements. • The mapping and survey will be performed in accordance with the “Regulations of Connecticut State Agencies, Sections 20-300b-1 thru 20-300b-20”, and the “Minimum Standards for Surveys and Maps in the State of Connecticut” endorsed by the Connecticut Association of Land Surveyors, Inc. on September 26, 1996. - The type of survey will be a “Boundary - Topographic Survey”. 1. Boundary and Horizontal control will conform to Class A-2 accuracy. 2. Vertical control will conform to Class V-2 accuracy. 3. Topographic and General Location Survey conform to Class T-2 accuracy. • Horizontal control will be recovered in Connecticut State Plane Coordinate system – North American Datum of 1983 (NAD ’83). Control will be established based on the best avilable Control Points recovered from State of Connecticut DOT or municipal sources. Otherwise, control will be established using GPS survey procedures. • Vertical control will be Established in National Geodetic Vertical Datum of 1988. (NAVD ’88) • A sufficient amount of horizontal and vertical control points with ties will be established in the project area for use during future construction projects. • All visible surface improvements will be field located and depicted on the plan. - Indicate encroachments and easements onto or off the property. - Indicate individual lot lines and lot block numbers; indicate street numbers if available. - Indicate location and dimensions of all existing structures on the subject lot. - Indicate names of owners of adjacent property. - Label surface materials, i.e. grass, bituminous, gravel etc.
Page 15
Mike Walsh Page | 7 - Complete topographic survey with contours at one (1) foot intervals and spot grades to the nearest tenth (0.1) of a foot within area indicated on the attached drawing(s). - The location of utility surface structures, along with paving and improvements aboveground and belowground. - The field survey will include obtaining top of frame elevations on utility structures as well as critical building structures. - Field survey of wetlands flags. Limit of Survey
Page 16
Mike Walsh Page | 8 Task 2.2 - Design Benesch will prepare a site design, which will be utilized for permitting and construction documents. The design will generally consist of the following: • The renovation of the high school track/field, as well as converting the existing stadium lights to LED. • The renovation of the synthetic turf practice field adjacent the stadium field. The conversion of the grass baseball field to a synthetic turf baseball/softball/soccer field. We will perform the following scope items in this phase: • We will visit the site to observe existing conditions, verify design considerations and assess design layouts relative to existing conditions. • We will review the local zoning regulations and prepare a zoning analysis table that will be utilized for design and permitting. • Benesch will provide a site plan that considers your programming requirements, zoning requirements, site topography and stormwater management. • The design package will consist of the following: - Site Preparation and Erosion Control - Site Plan (materials, layout, landscaping) - Grading and Drainage - Details • After approval of the local land-use permits, we will advance the plans to construction document level. • We will prepare front end specifications and technical specifications. • We will coordinate with you and other members of your design team in an ongoing manner throughout the design process via telephone and e-mail to exchange general information, evolving design layouts, and other pertinent information. • Using a professional, 3 rd party cost estimator, Pan American Consulting, we will provide a comprehensive construction cost estimate for both the schematic design-level documents, as well as the construction- level documents. Task 2.3 - Permitting Task 2.3.1 - Inland Wetlands and Watercourse Permit As required by the Town of Granby Inland Wetlands and Watercourses Regulations, we will perform the following scope items for this permitting effort: • Preparation of the wetland’s application, as required by the Regulations, including the following: - Application Form - Alternatives Assessment - Abutters List - DEEP Reporting Form The Inland Wetlands Commission has the discretion of requiring additional information when the proposed work is considered a “significant impact.” We have assumed the proposed work will not be considered a “significant impact” by the commission and we have therefore not included the additional information required by the regulations as part of our wetland permitting services. Additional information may include, but not be limited to, the following:
Page 17
Mike Walsh Page | 9 - Development and implementation of a water quality testing program. - Comprehensive written environmental impact statement report. - Analysis of chemical or physical characteristics of fill material. - Maps and descriptions that identify downstream and downgradient regulated areas. - Engineering reports and analyses and additional drawings to fully describe the proposed activity. - Site specific, high intensity soils mapping. Task 2.3.2 – Site Plan Approval/Special Permit Our land-use permitting effort for the Site Plan Approval/Special Permit will include the following: • We will attend a pre-application meeting with Town staff to review the Permit Drawings and discuss the permitting process. • We will prepare a Stormwater Management Report as part of the permitting process to include: - Hydrologic analysis and computations to ensure proposed peak flows do not exceed those required by the Town’s regulations. - Hydraulic analysis and computations to ensure sizing of on-site stormwater facilities (manholes, catch basins, piping, etc.) is sized to meet Town requirements. - Water quality computations that conform to the Connecticut Stormwater Quality Manual. • We will prepare the required applications and associated reports, supplemental data, design narratives, etc. • We will be prepared to discuss any safety concerns the public may have during our public meetings. • We will prepare colored renderings, as required, of the proposed site for use in presenting the project to the Town Planning and Zoning Commission. Task 2.3.3 - Meetings and Response to Comments We will attend public meetings, as required by the permitting process, including but not limited to: • Informal town staff meetings. • Site walks. • Night meetings with commissions. As part of the permitting effort, we will provide follow-on services to respond to comments, requests for information, or requested design changes during the permitting process. These services may consist of, but are not limited to, the following: • Telephone communications, letters/memorandums and/or e-mails. • Transmittal of supplemental information. • Revisions to the submitted reports or supplemental reports. • Plan revisions as a result of commission comments or conditions. • Preparation of easements.
Page 18
Mike Walsh Page | 10 Task 2.3.4 – CT DEEP General Stormwater Permit It is assumed the total disturbed project area will exceed five (5) acres. Therefore, the Connecticut General Permit for the Discharge of Stormwater and Dewatering Wastewaters from Construction Activities (“General Permit”) will be required. Following are items required by the permit, which we will prepare and submit: • NDDB Application (as required by the permit) • General Permit Registration • Stormwater Pollution Control Plan We have not included the cost of on-going erosion control inspections as required by the permit, as we assume your contractor will perform those. Task 2.4 - Bid Services We assume we will provide the town with our plans and technical specifications and the town will incorporate them into their front-end documents, and this will comprise the entire bid package. Benesch will provide support to the project for site/civil and landscape elements during bidding, including the following: • Attendance at a Prebid walkthrough. • Response to Bid RFIs. • Issuance of Bid Addenda. • Review and compilation of bids. • Attendance at scope review meetings with the two (2) lowest qualified bidders. • Collaboration with the town and recommendation of bid award. Task 2.5 - Construction Phase Services Benesch will provide support to the project for site/civil and landscape elements during construction, including the following: • Review/processing of contractor submittals relative to our design scope for conformance to requirements of the Contract Documents. • Attendance at Owner-Architect-Contractor (OAC) meetings to discuss progress, schedule and any concerns. We assume these will occur every other week. • Site visits to observe construction in progress and confirm that work relative to our design scope is proceeding in general conformance with the Contract Documents. We have assumed weekly site visits in our fee. • We have included up to 40 hours for our geotechnical engineers to perform service during this phase. It will be critical that they coordinate with the contractor during the excavation and earthwork phase of the project, in order to establish a stable base for the proposed improvements. • As needed/ongoing communications with the contractor by telephone and e-mail. • Respond to contractor requests for information (RFI). • Review of contractor Change Order Proposals. • Preparation of supplemental specifications, sketches, and design modifications to clarify intent or accommodate changes in the work. • Project close-out services, consisting of final site observations, punch list preparation, preparation of a certificate or substantial completion, and final acceptance of work.
Page 19
Mike Walsh Page | 11 Our fee for construction services is based upon the assumption of a construction timeline of up to 8 months. We therefore assume 34 site visits and 17 OAC meetings. Task 2.6 – Alternate Design Approach and Scope At the Town’s direction and upon separate authorization, Benesch will develop alternate site improvements coordinated with the base athletic-field renovations. The work will evaluate pedestrian circulation between the school, athletic fields and tennis courts; accessible routes; spectator access; and interfaces with proposed grading, drainage, utilities and field safety clearances. Design may require additional survey and geotechnical exploration, and will identify improvements that may be constructed with the base project or implemented in subsequent phases. Alternate landscape architectural services may include the campus walking circuit, plazas, woodland classroom, amphitheater seating, and a baseball–softball plaza incorporating concessions and batting cages. For the improvements selected by the Town, the agreed scope will establish the required layout, grading, paving, planting, site furnishings and associated details. Proposed locations and configurations will be evaluated against existing conditions, maintenance access, athletic operations, accessibility requirements and applicable land-use regulations. The design supplement illustrates preliminary concepts; final dimensions, materials and limits of work will be established through the authorized design process. Additional alternate improvements may include restrooms serving the stadium and baseball/softball/soccer field, lighting for the baseball/softball/soccer field, dugouts and moveable outfield fencing. Restroom design will be coordinated with a licensed architectural subconsultant and appropriate building-system engineers, considering prefabricated facilities where suitable and including applicable code requirements, utility availability, water and sanitary connections, and utility-provider coordination. Infrastructure associated with future improvements will be evaluated for installation during initial construction where practical, with the intent of limiting subsequent disturbance to completed athletic facilities. No fee for the alternate services described in this section is included in the base proposal. Before proceeding, Benesch and the Town will establish the selected improvements, design deliverables, consultant requirements, permitting responsibilities, schedule and associated fee through written authorization. That authorization will also define whether the improvements are to be incorporated as alternate bid items or documented for future construction, together with any required estimating, bidding and construction-phase services. The illustrative design supplement does not expand the authorized base scope or establish a commitment to construct all improvements shown. 2.0 ADDITIONAL SERVICES AND FEES The following services are not included as a part of our scope of services. These services may become necessary based upon the conclusions derived from the performance of the proposed services. If required, these services will be performed for an additional fee in accordance with a change order. 1. Design of off-site roadway improvements are excluded. 2. Archeological and/or listed species studies, as may be required by DEEP, are not included. We will not know if DEEP will require these until they perform their initial review of the site location. 3. Traffic services are excluded as it is our assumption that this project will not generate additional trip generation.
Page 20
Mike Walsh
Page | 12
4. Geotechnical Assumptions
Clear and unobstructed access to the exploration locations will be provided prior to mobilization, including
removal of equipment, materials, or other obstructions, as necessary.
Field services will be performed during normal weekday working hours, generally between 7:00 a.m. and
5:00 p.m. Work required outside these hours, including evenings, weekends, or extended workdays, may
result in additional fees.
Drilling equipment may remain at the Site during non-working hours for the duration of the exploration
program. We will coordinate with the owner for a location.
Test borings will be backfilled with drill spoils. Minor surficial disturbance is expected during the
investigation including ruts and holes at the ground surface. Matting will be used to minimize rutting. We
have assumed only minimal repair will be required, including backfilling the explorations with spoils.
Settlement at the subsurface exploration locations should be anticipated. Excess spoils (if any) will be left
on site.
The subcontractor fees do not include prevailing wage rates.
3.0 SCHEDULE FOR SERVICES
Benesch will work closely with your team to develop a project schedule based on project permitting requirements
and your needs. It is our understanding that you wish to engage a consultant in November after the referendum
passes. Assuming authorization to proceed in November, we anticipate it will require 6-8 months to survey, design
and permit the project. Typically, the local land use permitting is the most restrictive time component, especially
since this project will require permits from both the Inland Wetlands Commission and the Planning & Zoning
Commission. We anticipate there will be public opposition due to public concern about the nature of synthetic
turf and this could slow down the permitting process. After receipt of both permits, the project typically requires
up to four (4) to six (6) weeks to compile a formal bid package and then up to eight (8) weeks of bidding.
4.0 FEES FOR SERVICES
Benesch will perform the scope of services for Phase 1 for a lump sum for labor fee of $70,000 and Phase 2 for a
lump sum for labor fee for $410,000 Direct expenses [plan reproduction, mileage, shipping, abutter mailings,
public hearing sign costs, etc.] will be billed with no markup. We suggest you budget $4,000 for direct expenses.
The fee is segregated as follows:
Phase 1 – Investigation $70,000
Phase 2 – Design & Engineering
Base Fees
Task 2.1 – Base Mapping $ 30,000
Task 2.2 - Design $240,000
Task 2.3 - Permitting $ 40,000
Task 2.4 – Bid Services $ 10,000
Task 2.5 – Construction Phase Services $ 90,000
Total Lump Sum Fee $410,000
Total Estimated Direct Expenses $ 4,000
Page 21
Mike Walsh
Page | 13
Alternate Fees
Task 2.6 – Full Campus Design To be Negotiated, if desired by the PBCPC
In the event that the fee for the scope of services defined herein will be exceeded due to changes in the scope of
services, we will notify you to discuss and evaluate the work and related fees. We will not exceed the authorized
fees presented in this proposal without your authorization. Changes in fees will be mutually revised by written
amendment.
If you have any questions about this information, please call or e-mail me at 860-494-4359 or
wwalter@benesch.com . We look forward to providing our services on this exciting project.
Sincerely,
Alfred Benesch & Company
Will Walter, PE
Senior Project Manager
Page 22
GRANBY / DESIGN DISCUSSION Alternate Design Services Imagining a connected landscape. Cultivating a deeper sense of belonging. VICTORY PLAZA / What if this became the heart of school pride, gathering and everyday connection? Granby already holds all the natural ingredients of an unforgettable campus: a school at its core, fields alive with energy, quiet wooded edges, and a community that naturally comes together. What if these athletic updates are simply the spark that inspires us to link these pieces into one continuous home field? As stewards of the land, the landscape architects at Benesch help guide this vision—transforming functional field upgrades into a rich, cohesive campus worth coming back to. Research shows that high- performing green spaces can dramatically boost student well -being and academic outcomes —over a 20- year period, green campus investments can deliver net costs up to 381% lower compared to asphalt and gray infrastructure due to increased attendance, improved test scores, and energy savings. What if every path between destinations felt just as intentional as the games themselves, showing everyone in Granby how much our shared environment impacts daily success? Before the big games begin, what if we plant the idea of shaping this common ground as a shared playbook? Imagine if the connections between our daily spaces —the walk from classroom to kickoff, the shady spot where teammates regroup, the sidelines where parents catch up—were designed by the community’s own rhythm. Thoughtful paths, shade trees, seating, and outdoor hubs could organically stitch these moments together, creating an accessible foundation built to sustain both daily student life and future athletic achievements. Within this shared picture, what if each corner of campus reveals its own purpose? What if Victory Plaza welcomes both the high-energy excitement of Friday night lights and the quiet reflection of an ordinary afternoon? What if The Claw becomes the meeting point everyone naturally names, while The Den grows into an open- air classroom and event hub? From a comfortable baseball –softball plaza to a woodland Nature Classroom and seamless tennis links, warm brick, stone, timber, and planting can give these community-driven ideas a unified home character. What if the true measure of success isn't just what we build, but the everyday moments that take root here? Picture a teacher spontaneously moving a lesson outdoors, a grandparent finding a welcoming bench, students choosing to stay past the final bell, or a neighbor taking a quiet evening walk. Strong visual storytelling and renderings don’t just look appealing—they help us rally support and visualize the victory together, making fundraising initiatives and campus improvements significantly more impactful. When a clear vision starts as a shared community seed, every future step naturally builds toward that common dream. As this idea grows from within Granby, each project becomes a natural extension of our collective spirit. By planting these 'what if' possibilities today, we invite the entire community to take ownership of the game plan. Build the home field around shared vision and belonging, and the lasting victories will always belong to the Granby community. BENESCH / GRANBY MEMORIAL HIGH SCHOOL
Page 23
Page 24
Page 25
GRANBY / PLACES ALONG THE CAMPUS LOOP MEMORIAL STADIUM Baseball–Softball Plaza What if arrival at the upper fields felt like a natural homecoming? Brick paving, shaded seating, concessions, and batting cages invite players and families to gather and linger. Terraced seating opens up views for spectators and friends, seamlessly anchor ing the upper loop of our shared walking circuit. THE CLAW The campus meeting point What if a central junction organically transformed daily foot traffic into a vibrant social hub? Direct paths, low planting, and stone -and-timber benches keep movement effortless while offering a natural landmark to meet. Linked directly to the active fiel ds, The Claw becomes a natural center for student life. NATURE CLASSROOM Learning at the woodland edge What if learning naturally expanded into the surrounding woods? Along the quiet southwest edge, a simple seating circle creates space for outdoor lessons, group discussion, and personal discovery. It keeps quiet moments grounded in the larger rhythm of campus life. TENNIS CONNECTION Complete the campus circuit What if every corner of our athletic landscape felt effortlessly tied together? A welcoming pedestrian link brings the tennis courts into the core campus loop, complete with shade trees and restful pauses along the way, harmonizing daily traffic with pedestrian safety.
Page 26
GRANBY / THE OPPORTUNITY AHEAD What if we imagine a campus worth coming back to… THE CAMPUS VISION / What if athletics, learning, landscape and community grew as one? The athletic renewal is an exciting opportunity in its own right, but what if we see it as a springboard for something deeper? What if this moment inspires us to elevate every place where students train, learn, and grow together? Studies demonstrate that v ibrant, nature-integrated schoolyards yield long-term educational and financial dividends. By pairing strong visualizations with data-backed planning, we invite partners and donors to clearly see the winning play and join the team. What if this broader vision unfolds naturally from our shared values? A connected walking loop, welcoming plazas, outdoor learning spots, and native shade trees can weave our school and fields into a complete community landscape—giving athletes, students, families, and neighbors a space that feels uniquely their own. What if Granby brings this home-field vision to life step by step, cultivating ideas that feel entirely our own? Together, we can build an environment celebrated not just for its top-tier athletic facilities, but as an extraordinary place of belonging, community spirit, and shared pride.
Page 27
10/13/2026 www.bscgroup.com Michael P. Walsh Town Manager Town of Granby 15 N. Granby Road Granby, CT 06035 RE: Granby Athletic Field Engineering Proposal Dear Mr. Walsh and members of the Public Building and Capital Project Committee, BSC Group, Inc. (BSC) is pleased to submit this proposal for engineering and design services related to investigation, engineering and design of athletic facility improvements at Granby Memorial High School located at 54 N. Granby Road. The proposed services shall include Phase 1 - Investigation and Phase 2 - Design and Engineering. Project Understanding The Town of Granby is considering comprehensive improvements to the athletic facilities at the Granby Memorial High School and Middle School campus. The anticipated program includes reconstruction of Stadium Field and the running track, replacement of the synthetic turf at Field Two, and conversion of the existing baseball field into a synthetic turf facility capable of supporting baseball, softball, and compatible overlay uses. The existing Stadium Field and track have experienced recurring settlement, depressions, and sinkholes associated with variable fill containing organic materials and buried wood. Previous investigations identified unsuitable materials at varying depths across the facility, including deeper fill near portions of the track. The Town has received a proposed post- tensioned concrete solution intended to span the unsuitable soils. Full excavation and replacement, ground improvement, structural bridging, and hybrid approaches may also be technically feasible. BSC will serve as the Town’s independent engineering advisor. Our work will confirm the project program, evaluate the subsurface conditions, compare viable improvement strategies, establish realistic project costs and schedules, and advance the Town’s selected solution through design, permitting, bidding, and construction. SCOPE OF SERVICES Phase 1 – Investigation, Alternative Evaluation, and Project Definition Task 1.1 – Project Initiation and Program Confirmation • BSC will initiate the project with a kickoff meeting involving the Town, Board of Education, Public Building and Capital Project Committee, school facilities staff, athletic representatives, and other identified stakeholders. The purpose of the meeting will be to confirm the Town’s objectives, establish decision-making and communication protocols,
Page 28
review the available project budget, and define the improvements to be included in the base project. • The discussion will address Stadium Field and the running track, Field Two, and the baseball/softball facility, as well as related needs such as drainage, utilities, lighting, accessibility, bathrooms, storage, bleachers, press facilities, and athletic equipment. BSC will work with the Town to distinguish required improvements from discretionary enhancements or bid alternates. Athletic seasons, school activities, construction access, and acceptable facility downtime will also be considered when establishing the preliminary project schedule. BSC and its subconsultants will review the available design, construction, maintenance, and investigation records associated with the athletic complex. We will review available project information, including: o Original 2012–2013 design and construction documents. o Record drawings, shop drawings, submittals, change orders, testing reports, and closeout documents. o Previous geotechnical investigations and recommendations. o Available survey, utility, drainage, and campus mapping. o FieldTurf and other vendor concepts, proposals, budgets, and warranties. o Athletic facility master-planning documents. o Prior repair and maintenance records. o Stormwater and drainage information. o Existing permits and regulatory approvals. o Capital-program budgets and CPPAC materials. o Applicable Town, school, CIAC, NFHS, accessibility, and building-code requirements. The review will focus on understanding the original construction, the progression of the settlement and sinkhole conditions, the effectiveness of prior repairs, and the assumptions supporting the currently proposed improvements. BSC will identify discrepancies, missing information, and issues that require confirmation through field investigation or additional testing. Task 1.2 – Existing Conditions Survey and Base Mapping • BSC will review available survey information and perform supplemental survey as needed to establish a coordinated base map for the project. The survey will document the athletic fields, track, pavement, walkways, fencing, bleachers, buildings, lighting, drainage structures, utilities, accessible routes, and other features that may affect design or construction. Surface elevations will be collected to document existing grading and observable areas of settlement. • BSC will prepare an Existing Conditions Plan under the direction of a Connecticut- licensed Land Surveyor. The Existing Conditions Plan will depict the Site boundaries,
Page 29
locations of site improvements, utilities, and topography. We will generate a triangulated irregular network (TIN) for the surveyed area and depict contour lines at a Site- appropriate interval (1 or 2 feet) with spot elevations at surface structures and in other areas as may be appropriate. Final prints will bear the signature and seal of a Connecticut-licensed Land Surveyor. We will provide the completed Existing Conditions Plan to you in both print and digital (Portable Document Format; .pdf). • BSC will delineate the boundaries of jurisdictional wetlands and watercourses on the Site. Delineation will be conducted by a soil/wetland scientist who meets the definition of a “Soil Scientist” in accordance with Connecticut General Statutes Title 22a, Chapter 440, Inland Wetlands and Watercourses Act. The Soil Scientist will delineate the boundaries of inland wetland areas with sequentially numbered flagging tape placed at regular intervals. To document the wetlands delineation work, a letter report will be prepared which summarizes the field work and results. • BSC will conduct a field assessment of Stadium Field, the running track, Field Two, and the baseball/softball area. The assessment will document the condition of the turf, track surfacing, pavement, drainage, fencing, backstops, ball-control netting, gates, athletic equipment, lighting, electrical service, spectator areas, and accessible circulation. Existing water, irrigation, and stormwater infrastructure will be reviewed to the extent that it is visible or documented. • The assessment will identify facilities that may remain in service, elements requiring modification, and components that should be replaced. BSC will also evaluate emergency access, maintenance access, construction staging, material-storage areas, and other site constraints that may influence project cost and implementation. Task 1.3 – Supplemental Geotechnical Investigation and Analysis • BSC’s geotechnical subconsultant (Down to Earth Consulting, LLC) will review the existing 2022 and 2025 exploration programs and determine whether the available information is sufficient to evaluate the potential ground-support alternatives. Where data gaps remain, the geotechnical engineer will prepare and implement a targeted supplemental investigation program. • The targeted supplemental investigation includes additional explorations within Stadium Field and the running track where existing data require clarification. Investigations will also be performed at Field Two and the baseball/softball field to determine whether similar variable fill or unsuitable materials are present beneath those facilities. We have included three days of geotechnical borings. • The boring program will include borings, Standard Penetration Tests (SPT) semi- continuously up to ten feet and at five-foot intervals thereafter, groundwater observations, and laboratory testing. If explorations reveal that the subsurface soils are compressible, additional explorations and laboratory testing may be required for foundation design. • We propose completing engineering index testing consisting of up to three Atterburg Limits Tests and up to five Water Content Tests. We will correlate the proposed laboratory testing results with published subsurface data to support our geotechnical analysis. • The investigation will result in a geotechnical report documenting the subsurface conditions, relevant design parameters, preliminary settlement analyses, and recommendations for the improvement alternatives carried forward for evaluation.
Page 30
• BSC and its geotechnical subconsultant will initially screen the potential support strategies based on the available subsurface information, site constraints, anticipated performance and order-of-magnitude cost. Alternatives that do not demonstrate reasonable technical or economic viability will be documented and eliminated from further consideration. The detailed comparison will focus on the limited number of solutions that warrant serious consideration by the Town. • The evaluation will include the proposed post-tensioned concrete track and field system, as well as full excavation and replacement of unsuitable materials. Other methods such as rigid inclusions, controlled-modulus columns, lightweight fill, or hybrid systems will be considered where the subsurface conditions and anticipated facility loading support their use. • Each viable alternative will be evaluated for its ability to control total and differential settlement and its compatibility with the running track, synthetic turf, drainage systems, utilities, lighting, fencing, walkways, and other site improvements. The analysis will also consider construction cost, schedule, athletic downtime, excavation and disposal requirements, groundwater impacts, specialty-contractor availability, testing and quality- control requirements, warranty coverage, expected service life, future resurfacing and turf replacement, repairability, and lifecycle cost. Task 1.4 – Athletic Complex Concept Development • BSC will prepare concept-level plans illustrating how the athletic complex could be reconstructed using the viable ground-support strategies. The concept plans will coordinate the improvements to Stadium Field and the running track, Field Two, and the baseball/softball facility as one campus system. • The concepts will address facility layout, grading, stormwater management, subsurface drainage, utility routing, accessible circulation, maintenance access, emergency access, fencing, gates, backstops, ball-control netting, lighting, scoreboards, and athletic equipment. Where applicable, the plans will also identify potential locations or accommodations for bathrooms, concessions, storage, bleachers, and press facilities. • Attention will be given to shared infrastructure and opportunities to reduce costs or avoid future conflicts. BSC will also consider construction access, material storage, phasing, and methods for minimizing disruption to school and athletic activities. • BSC will prepare a conceptual owner’s cost estimate for each viable project alternative. The estimate will include the anticipated site and athletic-facility construction, ground improvement or structural support, drainage and utility improvements, contractor mobilization and general conditions, testing and inspection, escalation, and appropriate design and construction contingencies. The estimate will reconcile the project scope against the previous vendor budgets and identify exclusions, allowances, or unresolved conditions that could create additional cost exposure for the Town. BSC will separately identify discretionary improvements and potential bid alternates so that the Town can establish a base project that remains aligned with the bond authorization. • BSC will update the preliminary schedule addressing investigation, design, permitting, bidding, construction, long-lead materials, and seasonal limitations.
Page 31
• We will submit a draft version of the completed Conceptual Design package to the Town for review. Based on feedback received, we will revise/update the design package accordingly as part of Phase 2 (see below). • In addition to the kick-off meeting, BSC will attend two (2) meetings with the Town and stakeholders during Conceptual Design to review the design documents. Our scope of services assumes that these meetings will be “virtual meetings” using BSC’s Teams platform or similar technology. Task 1.5 – Phase 1 Recommendations and Decision Workshop • BSC will organize the findings into an alternatives matrix comparing the viable solutions against evaluation criteria established with the Town. The criteria are anticipated to include settlement performance, initial cost, lifecycle cost, schedule, facility downtime, constructability, maintainability, warranty coverage, environmental impacts, and overall owner risk. • BSC will conduct a decision workshop with the Town and school representatives to review the findings, discuss the tradeoffs among the alternatives, and develop a recommended project approach. The recommendation will identify the proposed base project, suggested bid alternates, preliminary budget, anticipated schedule, permitting requirements, and remaining design risks. • The findings and recommendations will be documented in a Phase 1 report and presented to the designated Town committee, Board of Education, and other public bodies as requested. Phase 2 will proceed following the Town’s acceptance of the Phase 1 recommendation and written authorization to advance the selected alternative. Phase 1 Deliverables Phase 1 will result in a coordinated existing-conditions base map, facility-condition assessment, supplemental geotechnical report, concept-level athletic complex plans, ground- improvement alternatives analysis, permitting matrix, conceptual cost estimate, preliminary project schedule, and investigation and recommendations report. BSC will also prepare the graphics and presentation materials needed to communicate the recommendations to the Town. Phase 2 – Design, Engineering, Permitting, and Construction Services Task 2.1 – Design Development • Following authorization by the Town, BSC will advance the selected concept to approximately 30 percent design. The design-development package will establish the proposed demolition limits, athletic-facility layout, track geometry, field elevations, grading, drainage, utilities, accessible routes, fencing, gates, netting, lighting improvements, athletic equipment, and preliminary construction phasing. • The geotechnical design for the selected ground-support system will be advanced sufficiently to confirm the proposed design criteria, construction limits, anticipated specialty work, and testing requirements. BSC will also establish the performance
Page 32
requirements for the synthetic turf and running-track systems and identify proposed bid alternates. • Design Meetings - We will attend one (1) meeting with the Town and stakeholders during this task. Our scope of services assumes that these meetings will be “virtual meetings” using BSC’s Teams platform or similar technology. Task 2.2 – 60% Construction Documents Upon acceptance of the design-development package, BSC will prepare coordinated 60 percent construction documents. Utilizing comments received from the Design Development review meeting, BSC will prepare 60% construction document drawings. We will develop the following drawings: o Cover Sheet o Existing Conditions Plan o Site Preparation and Demolition Plan o Materials Plans o Layout Plans o Sports Field Layout Plans o Grading and Drainage Plans o Utility Plans o Details • BSC will update the Opinion of Probable Construction Cost based on the 60% Construction Document drawings. • BSC will prepare a Stormwater Management Report to document the evaluations, stormwater management requirements, and engineering design of the stormwater conveyance and management systems for the projects. The report will be prepared in accordance with Town and State standards, and will discuss existing conditions, hydrology, definition of needs, the design of proposed stormwater management facilities, and operations and maintenance of proposed stormwater management facilities. • We will submit a draft version of the completed 60% Construction Documents package to the Town for review. Based on feedback received, we will revise/update the design package accordingly in the next task. • Design Meetings - We will attend one (1) meeting with the Town and stakeholders during this task. Our scope of services assumes that these meetings will be “virtual meetings” using BSC’s Teams platform or similar technology. Task 2.3 – 90% Construction Documents • BSC will incorporate the Town’s consolidated review comments and advance the plans and specifications to approximately 90 percent completion. At this stage, the design team will resolve remaining technical and interdisciplinary coordination issues, finalize construction details, confirm permitting requirements, and refine the bid alternates, allowances, testing requirements, and warranty provisions.
Page 33
• BSC will update the Opinion of Probable Construction Cost based on the 60% Construction Document drawings. • We will submit a draft version of the completed 90% Construction Documents package to the Town for review. Based on feedback received, we will revise/update the design package accordingly in the next task. • Design Meetings - We will attend one (1) meeting with the Town and stakeholders during this task. Our scope of services assumes that these meetings will be “virtual meetings” using BSC’s Teams platform or similar technology. Following the meeting, BSC will prepare a written response describing how the consolidated comments will be addressed in the final documents. Task 2.4 – Permitting BSC will prepare the permit applications and supporting materials and will coordinate submissions with the applicable local and State agencies. Based on our project understanding, we anticipate the project will require the following: • BSC will attend a pre-application development team meeting with Town staff to discuss the permitting process. • We will prepare a Town of Granby Application to Appear Before the Granby Planning and Zoning Commission for Site Plan review along with the required supporting materials. We will submit the application package to the Town to be put on the agenda for the appropriate Planning and Zoning Commission meeting. • We will attend up to a total of (2) meetings to present the project and answer technical questions regarding the design before the Planning and Zoning Commission. • BSC will prepare an Inland Wetlands and Watercourses Commission Application for Inland Wetlands and Watercourses Activity along with the required supporting materials. • We will submit the application package to the Town to be put on the agenda for the appropriate Inland Wetland and Watercourses Commission meeting. • We will attend up to a total of (2) meetings to present the project and answer technical questions regarding the design before the Inland Wetlands and Watercourses Commission. • Based on the review of the anticipated project site, we assume disturbance will be greater than 1 acre and less than 5 acres and will be locally approved, therefore, will need to be registered under CT DEEP General Permit for the Discharge of Stormwater and Dewatering Wastewaters from Construction Activities (DEEP-WPED-GP-015). BSC will prepare and register the project. • Following the Town’s submissions and meetings, BSC will provide follow-on services to respond to comments, requests for information, conditions of approval, or requested design changes during the permitting process. Our Lump Sum fee includes minor plan revisions for purposes of clarification, telephone discussions, and basic e-mail communications. Extensive plan revisions, design changes, re-printing of documents, site visits, meetings, and appeals are not included in our lump sum fee and will be performed as an additional service.
Page 34
Task 2.5 – Final Construction and Bid Documents • Using the Town approved 90% construction document drawings, BSC will prepare final technical specifications and design drawings (100% Construction Documents). The drawings will include additional information, notes and details as necessary to clearly define the scope of site work to be completed by prospective contractors. • BSC will prepare technical specifications for the project to supplement the design information indicated on the drawings. Technical specifications will be prepared using Construction Specifications Institute (CSI) MasterFormatTM 2020 Edition Numbers and Titles. • BSC will work with your finance department and provide technical information to be used for soliciting bids. Bid Documents will include the following: o Drawings: “Issued for Bid” drawings. o Project Manual o Bidding Materials (Coordinated with the town). o Agreement and General Conditions. o Supplementary conditions. o Division 1 General Requirements. o Technical Specifications. • Meetings – We will attend one meeting with the town to review and coordinate the bidding documents. Our scope of services assumes that these meetings will be “virtual meetings” using BSC’s Teams platform or similar technology. Task 2.6 – Bidding Assistance BSC will provide the following bidding assistance services: • BSC will coordinate and host a pre-bid meeting at the project site so potential bidders can view the project area. • BSC will prepare bid addenda and responses to bid questions as may be required during bidding for the purposes of clarification or interpretations of the Bidding Documents. • Once bids are received, BSC will assist the Town in evaluating bids and make a recommendation regarding award. This will include evaluation of the bids, verification of bid items, evaluation of bidder qualifications, and reference checks. We will prepare and submit a Bid Recommendation Letter to the Town documenting our review of the bids and recommendation for award to the lowest qualified bidders. • BSC will coordinate and host a scope review with the Town and apparent low bidder to 1) verify that their bid includes all required elements of the project, 2) confirm their understanding of the scope of the work, and 3) confirm the post-bid requirements for executing an agreement (bonds, insurance, etc.). • Following the bidding period BSC will prepare a set of Construction Documents/Contract Documents incorporating the Bid Documents, Addenda, supplemental drawings, clarifications, executed contract, and other additional information developed during the bidding period. These materials will be marked “Issued for Construction”.
Page 35
Task 2.7 – Construction Phase Services BSC will provide the following construction phase services: • BSC will attend a pre-construction conference (construction kick-off meeting) with the Town and the contractor/subcontractor(s). • BSC will provide technical feedback to the contractor during the mobilization process. It is assumed that this will be completed by telephone and e-mail. • Submittals/Shop Drawings. BSC will review/process technical submittals/shop drawings required by the plans and specifications. This will also include material/product substitution requests. • Requests for Information. BSC will prepare narrative responses, supplemental specifications, and narrative design clarifications in response to Requests for Information (RFIs) by the contractor. • Design Services During Construction. BSC will provide design services during construction on an as-needed basis. The design services could include supplemental drawings or design changes/plan changes and will be conducted on an hourly basis. • BSC will conduct periodic site visits at a nominal rate of one (1) per week to observe/document construction in progress and confirm that work observed is proceeding in general conformance with the Contract Documents. Depending on the work being performed, additional visits may be conducted. We have assumed twelve (12) months for the construction phase, excluding winter shut down, with a total of thirty (30) visits. A Field Observation Report will be prepared for each site visit. • BSC will maintain periodic telephone and/or e-mail contact with the contractor throughout the project for coordination purposes. • BSC will facilitate weekly construction progress meetings for the duration of construction. We will work with the Town to prepare a standardized agenda for these meetings. For each meeting, BSC will prepare and distribute summary meeting minutes using a standard format. These meeting could be either be on site of virtual. • BSC will evaluate contractor change order proposals. • BSC will review monthly contractor Applications for Payment and advise the Town if the requested payment is commensurate with the completed work. • BSC will conduct one (1) initial close-out inspection of the work and prepare a Punch List. • BSC will review as-built drawings, O&M manuals, warranties, and certifications applicable to the work. • BSC will prepare a Certificate of Substantial Completion or similar document to confirm that the contractor has achieved substantial completion. • BSC will conduct one (1) final close-out inspection to observe final work and items that were addressed as part of the punch list process. • BSC will prepare a Certificate of Final Acceptance or similar document at the completion of the project. • Additional site visits specific to closeout will be conducted on an as-need/as-requested basis, on an hourly basis.
Page 36
2.0 ADDITIONAL SERVICES The following services are not included as a part of this Proposal. These services may become necessary based upon the conclusions derived from the performance of the proposed scope above. If required, these services will be performed for an additional fee to be paid on an hourly basis in accordance with the attached BSC Fee Schedule. • Activities related to the collection, handling, or treatment of hazardous materials. • Plan implementation and routine inspections associated with the Connecticut DEEP General Permit for the Discharge of Stormwater and Dewatering Wastewaters from Construction Activities. • Retaining wall design and any associated structural calculations, if required. • Participation in meetings, hearings, and coordination beyond the estimates provided above. • Major revisions of previously approved drawings or specifications to accomplish changes requested by the Client or Owner. • Providing services required because of significant changes in the project including, but not limited to size, quality, complexity, the Client’s schedule, or the method of bidding or negotiating and contracting for construction. • Off-site flow analysis for stormwater drainage. It is assumed that the existing system has sufficient capacity to meet the needs of the project. • Providing additional plan set submissions. • Reproduction services of any kind. • Clerk of the Works or Resident Engineer services. 3.0 SCHEDULE FOR SERVICES BSC proposes to begin the services identified in Section 1.0 of this Proposal upon receipt of written authorization to proceed. Our proposed schedule for the completion of the task(s) described in Section 1.0 of this Proposal. 4.0 FEE FOR SERVICES 4.1 BSC proposes to provide the services described in Section 1 of this Proposal for the lump sum fee of $ Three Hundred Fifteen Thousand Four Hundred Twenty ($315,420) Dollars including all direct expenses. Periodic billing shall be based upon percentage of work completed. 4.2 Fees shall be billed monthly as applicable. Payment is due upon receipt of invoices. Failure to comply with the payment terms of this Proposal shall be cause for the Consultant to terminate services. 4.3 The Client shall provide BSC with any specific billing format required for prompt payment of invoices. The mailing address for all payments is:
Page 37
BSC Group, Inc. 1 Mercantile St. Suite 610 Worcester, MA 01608 4.4 The following is a breakdown of the estimated fee described in Section 1.0 of this Proposal. The budget for individual tasks shall not be construed to be separate limiting fees. Phase 1 – Investigation, Alternative Evaluation, and Project Definition Task 1.1 – Project Initiation and Program Confirmation $5,544 Task 1.2 – Existing Conditions Survey and Base Mapping $24,540 Task 1.3 – Supplemental Geotechnical Investigation and Analysis $33,652 Task 1.4 – Athletic Complex Concept Development $19,780 Task 1.5 – Phase 1 Recommendations and Decision Workshop $10,805 Phase 2 – Design, Engineering, Permitting, and Construction Services Task 2.1 – Design Development $42,354 Task 2.2 – 60% Construction Documents $34,684 Task 2.3 – 90% Construction Documents $24,644 Task 2.4 – Permitting $16,157 Task 2.5 – Final Construction and Bid Documents $19,680 Task 2.6 – Bidding Assistance $4,815 Task 2.7 – Construction Phase Services $78,765 Total: $315,420 5.0 GENERAL CONSIDERATIONS 5.1 This proposal is valid for a period of thirty (30) days.
Page 38
BSC welcomes the opportunity to provide professional services for this project. If you should have any questions or require additional information, please contact me at jharris@bscgroup.com or 860-652-8227. Sincerely, BSC Group, Inc. Jesse A. Harris, Project Manager Attachment(s): Project Schedule
Page 39
2026 Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct 1.1 Project Initiation and Program Confirmation 1.2 Existing Conditions Survey and Base Map 1.3 Supplemental Geotechnical Investigation and Analysis 1.4 Athletic Complex Concept Development 1.5 Phase 1 Recommendations 2.1 Design Development 2.2 60% Construction Documents 2.3 90% Construction Documents 2.4 Permitting 2.5 Final Construction and Bid Documents 2.6 Bidding Assistance 2.7 Construction Phase Services M Phase 1 recommendation M M Final bid documents M M Bidding complete M M Construction services begin M M Anticipated completion M * Permitting duration does not include a public hearing. Schedule durations exclude weekends and holidays. Feb 5, 2027 Aug 6, 2027 Sep 10, 2027 Oct 1, 2027 Oct 1, 2028 Apr 26–Jul 16, 2027* Jul 19–Aug 6, 2027 Aug 9–Sep 10, 2027 Oct 1, 2027–Oct 1, 2028 KEY MILESTONES Jan 25–Feb 5, 2027 PHASE 2 DESIGN ENGINEERING PERMITTING AND CONSTRUCTION SERVICES Feb 8–Mar 5, 2027 Mar 8–Apr 2, 2027 Apr 5–23, 2027 PHASE 1 INVESTIGATION ALTERNATIVES EVALUATION AND PROJECT DEFINITION Dec 14–18, 2026 Dec 14–31, 2026 Dec 28, 2026–Jan 15, 2027 Jan 4–22, 2027 Granby Memorial High School Athletic Facilities Preliminary project schedule | December 2026 through October 2028 COLOR KEY Blue Phase 1 Green Design Gold Permitting Light Blue Bidding Gray Construction support 2027 2028 TASK ACTIVITY SCHEDULE
Page 40
SLR International Corporation 99 Realty Drive, Cheshire, Connecticut, 06410 1 October 13, 2026 Mr. Mike Walsh Town Manager Town of Granby 15 North Granby Road Granby, CT 06035 SLR Project No.: 141.P51644.00001 SLR Client No.: 12712 RE: Investigation and Design Services for Athletic Field Improvements Stadium Field, Track, Field Two, and Baseball Field at the Granby Memorial High School Complex Granby, Connecticut Dear Mr. Walsh, SLR International Corporation (SLR) is pleased to submit this narrative describing our approach to assisting the Town of Granby (Town) with the evaluation, design, and renovation of the outdoor athletic facilities at Granby Memorial High School located at 313 Salmon Brook Street. As requested, this narrative is organized into two distinct phases, each outlining the proposed scope of services and associated fees. Phase 1 will focus on the investigations necessary to evaluate existing site conditions and establish a basis for design for the Stadium Track and Field. These services include determining the root causes of deficiencies within the Stadium Field and Running Track; completing topographic surveys for the three project areas; delineating wetland and watercourse boundaries in the vicinity of each site; conducting limited, minimally invasive testing of the existing synthetic turf systems to assess their suitability for reuse and to inform anticipated removal, disposal, and recycling costs; and excavating a series of shallow test pits within the baseball/multipurpose field to quantify topsoil management requirements and evaluate existing subsurface drainage characteristics. Phase 2 will consist of the development of detailed engineering and construction documents for the proposed improvements. This phase includes preparation of permit applications and presentations required for review by local land use commissions, development of technical specifications, and preparation of opinion of probable construction cost estimates. Upon completion of both phases, the Town will possess the information, approvals, and construction documents necessary to advance one or more of the proposed improvement projects through the public bidding process and into implementation.
Page 41
Town of Granby Investigation and Design Services for Athletic Field Improvements October 13, 2026 SLR Project No.: 141.P51644.00001 2 Overall Project Approach Phase 1 Investigation – Stadium Track and Field Our team believes there is value in stepping back from the options currently being discussed for the Memorial High School stadium, including full soil removal across the track and field and construction of a full post-tensioned concrete slab. While soil borings are a valuable resource for any site improvement project, they can be limited in depicting the full range of conditions, particularly in a built environment that has been altered several times over multiple decades with limited records. The Town is currently experiencing localized subsurface instability, manifested as sinkholes, within a confined area of the synthetic turf field and track, with only speculation as to what the future may hold for currently unaffected areas. As our in-house geotechnical, civil, and structural engineers reviewed the available soil investigations with our landscape architects, we identified several items that led us to question whether full soil removal is warranted and whether additional geotechnical data could help reduce the stadium reconstruction costs or allow for reallocation of funding to include additional facility amenities. Our review of the 2022 geoprobe soil logs indicated a fairly consistent difference in fill conditions across the stadium, primarily as the probes moved from east to west. On the west side of the stadium, the logs generally indicate track or field construction materials placed over native soils. On the east side, the improvements appear to have been constructed over varying depths of fill. A pocket of fill was also noted on the west side at GP-22, as shown in the graphic below. These differences suggest that full soil removal across the site may not be warranted. They are also consistent with the issues occurring along the east side of the field and track interface.
Page 42
Town of Granby Investigation and Design Services for Athletic Field Improvements October 13, 2026 SLR Project No.: 141.P51644.00001 3 Granby High School stadium 2022 Geoprobe location map with general fill conditions noted. Note the approximate 50/50 split of areas of fill (east side) versus native subsoils (west side).
Page 43
Town of Granby Investigation and Design Services for Athletic Field Improvements October 13, 2026 SLR Project No.: 141.P51644.00001 4 Our team proposes focusing the investigative phase of the stadium project on an evidence- based program to determine the true boundaries of the soil deficiency to minimize reconstruction efforts and potentially allow for the inclusion of additional amenities, including a restroom building, lighting, or scoreboards. To maximize the value of the investigation, we propose using continuous imaging and linear excavation techniques rather than the standard “spot” investigations associated with traditional borings or isolated test pits. As the previous geoprobe program showed, subsurface conditions can vary significantly between the limited footprints of individual boring locations. To establish a continuous profile of existing soil conditions without the prohibitive cost of widespread exploratory drilling, we propose a combination of the following linear and spatial investigation techniques: • Electrical Resistivity Imaging (ERI): This nondestructive method measures variations in subsurface electrical resistance to generate continuous cross-sectional profiles of the field’s underlying strata. The ERI system injects a direct electrical current into the ground through a linear array of steel electrodes and measures the resulting voltage differences. Specialized inversion software then processes the data to generate two-dimensional or three-dimensional subsurface profiles. At a site with heterogeneous fill and sinkholes, anomalies can appear as distinct contrasts in resistivity. Air pockets, saturated soils, and highly variable materials—including construction debris, mixed soils, and trash—may be visible. • Drone-Derived Photogrammetry and Topographic Mapping: High-resolution aerial drone surveys can capture microtopographic variations and subtle surface expressions. Monitoring these subtle surface depressions provides a critical predictive layer to align with the subsurface data. • Targeted Linear Trenching: Rather than using a grid of speculative and destructive test pits, the ERI screening results will guide highly targeted, localized trenching. We anticipate trenching in rows spaced 25 to 50 feet on center, to a depth of 4 feet below existing grades and an approximate width of 2 feet. Trenches will be backfilled with compacted excavated material, and surfaces will be restored in kind. This approach allows physical soil sampling and subgrade inspections to be focused on where anomalies are identified. Through collaboration with SLR staff and our proposed advanced diagnostic framework, the Town can move from a position of speculation to one of clarity, ensuring public funds are deployed efficiently and effectively. Stadium Feasibility Study and Budget Alignment As part of the investigative phase, our team will prepare a comparative "Red/Green Report," evaluating available design and construction approaches for both the athletic field and running track improvements providing a side-by-side comparison of each improvement scenarios’ pros and cons. Unlike firms committed to a single design philosophy or proprietary product, our recommendations will be driven entirely by the Town’s vision, the site investigation results, and the available budget, including long-term maintenance considerations. Using precedent projects and comparable facilities—including the SLR-led athletic complex in Westfield, Massachusetts, completed in 2026—the Town will gain a clear understanding of what can be achieved under a range of construction and budget scenarios.
Page 44
Town of Granby Investigation and Design Services for Athletic Field Improvements October 13, 2026 SLR Project No.: 141.P51644.00001 5 11.1-million-dollar Westfield High School Stadium project completed by SLR, opened October 2026. The project includes a new multi-sport stadium with synthetic field, track, and restroom/concession building This process will help establish realistic expectations, identify opportunities for enhanced value, and determine the most effective path toward achieving the Town's long-term athletic facility goals. The Red/Green report will include side-by-side evaluations of: • Partial reconstruction focused on priority improvement areas • Full reconstruction of the athletic field and track • Post-tensioned concrete track with conventional field reconstruction • Full post-tensioned concrete (PT) track and field base system Each scenario will include initial construction costs, lifecycle costs, expected service life, and operational impacts associated with each option.
Page 45
Town of Granby Investigation and Design Services for Athletic Field Improvements October 13, 2026 SLR Project No.: 141.P51644.00001 6 Lifecycle Cost and Maintenance Analysis For each reconstruction scenario, our team will provide a detailed assessment of anticipated maintenance requirements and associated long-term costs. This evaluation will allow Town officials to consider not only initial construction expenditures but also the long-term financial implications of each alternative. The analysis will include: • Annual maintenance requirements • Major repair and replacement cycles • Expected facility lifespan • Lifecycle cost comparisons • Operational considerations and risk factors Maximizing Available Funding The feasibility and alternatives analysis will demonstrate opportunities to stretch available capital dollars and potentially incorporate additional amenities that may otherwise be excluded from the project. Potential enhancements could include: • Electronic scoreboards • Restroom and concession facilities • Dugouts and team areas • Batting cages • Storage facilities • Spectator amenities • Site lighting and utility improvements By identifying the relative costs and benefits of various construction approaches, the Town can make informed decisions regarding facility priorities and project enhancements. Planning for Future Improvements The investigative phase will also establish a long-range master plan that allows future improvements to be implemented efficiently as funding becomes available. This planning effort may include: • Reserving space for future amenities and facility expansion • Strategic utility planning and installation of empty conduits • Installation of foundations and infrastructure for future lighting systems • Utility stub-outs for future buildings or site improvements • Phased implementation strategies that minimize the need for future reconstruction or rework Through proper planning and infrastructure coordination, future improvements can be added with significantly less disruption and cost. Decision-Making Framework At the conclusion of the investigative phase, the Town will receive a comprehensive reference document that clearly outlines facility needs, construction alternatives, maintenance implications, budget scenarios, and implementation strategies.
Page 46
Town of Granby Investigation and Design Services for Athletic Field Improvements October 13, 2026 SLR Project No.: 141.P51644.00001 7 This document will serve as a defensible decision-making tool that provides elected officials, staff, stakeholders, and the public with a clear understanding of the options available and the rationale behind future investment decisions. The result is a data-driven roadmap that positions the Town to move forward confidently when funding opportunities arise while ensuring that all recommendations are made in the best long-term interest of the community. Phase 1 – Site Survey, Wetland Delineation, Drainage and Soil Investigations, and Geotechnical Investigations for Field Lighting Wetland Delineation SLR soil scientists will delineate and flag wetlands and watercourses adjacent to the project sites, including Kendall Brook. A wetland delineation report will summarize field observations and document jurisdictional resource boundaries for use in project planning, design, and permitting. Topographic Surveys SLR survey crews will complete detailed topographic surveys of Field Two and the Baseball Field project areas. The survey information will be used to prepare accurate base mapping and support development of the proposed design and construction documents. The drone-derived photogrammetry and topographic mapping for the Stadium Track and Field will be reconciled with the field topographic surveys. Drainage and Soil Investigations SLR engineers will evaluate the existing drainage infrastructure serving the Stadium Track and Field complex, including both surface and subsurface drainage systems. As part of this effort, SLR will arrange for closed-circuit television (CCTV) inspections of accessible drainage piping to assess pipe condition, functionality, and potential deficiencies. SLR will retain a qualified third-party sports field testing laboratory to perform limited, non- invasive investigations of the existing synthetic turf systems at both the Stadium Field and Field Two. Testing will include localized access through the turf carpet to evaluate the permeability and condition of the underlying aggregate base materials and determine their suitability for reuse. The testing laboratory will also measure existing infill depths to assist in developing removal, disposal, and recycling cost estimates. SLR will arrange for and observe the excavation of a series of shallow test pits within the proposed baseball field area. Information obtained through these investigations will be used to quantify existing topsoil depths and estimate the volume of material that may require removal or relocation during construction. Should the Town elect to keep this facility grass in lieu of converting to synthetic turf, soil samples will be collected and submitted for particle size and nutrient analyses to determine appropriate amendments necessary to establish an optimal growing medium for natural turf. The test pits will also be used to characterize underlying soil conditions and evaluate subsoil permeability, groundwater indicators, and drainage characteristics that may influence the design of the proposed field drainage system. Findings from the investigation will help refine drainage design concepts and associated construction cost estimates. No additional analytical soil testing is proposed as SLR will rely on the recent testing completed by Weston & Sampson, Inc., which demonstrated that excess soils may be disposed of off site without additional characterization. The overall assessment will provide recommendations regarding rehabilitation, reconstruction, or phased implementation strategies and will serve as a technical basis for future planning,
Page 47
Town of Granby Investigation and Design Services for Athletic Field Improvements October 13, 2026 SLR Project No.: 141.P51644.00001 8 budgeting, funding requests, and design decisions. The information collected during these investigations will support the development of practical and cost-effective grading and drainage solutions tailored to existing site conditions. This information will support the development of practical and cost-effective site grading and drainage solutions tailored to the existing conditions of the facility. Geotechnical Investigation for Field Lighting For the Baseball Field, SLR will perform geotechnical borings to evaluate subsurface conditions at the proposed lighting structure locations. Based on previous project experience, we anticipate that six light poles will be required to achieve high-school-level athletic lighting standards. SLR will perform geotechnical engineering analyses and prepare a geotechnical report summarizing subsurface conditions encountered during drilling. The report will identify geotechnical considerations associated with the proposed lighting system and provide foundation design and construction recommendations for the project. Upon completion of all Phase 1 investigations and analyses, SLR will compile available records, field observations, survey information, and subsurface investigation findings into a comprehensive Existing Conditions Assessment Memorandum. The memorandum will summarize existing site conditions, identify key opportunities and constraints, and provide the technical foundation for subsequent planning, design, permitting, and cost estimating efforts. Phase 1 – Investigation Estimated Fees SLR estimates the fee range for Phase 1 to be $100,000 to $112,000. Below is a simple breakdown of our estimated fee for Phase 1 assessments and investigations: SLR’s Estimated Fees Estimated Staff Hours SLR Subcontractors Geotechnical Investigation - Stadium $30,000 - $40,000 Influenced by extent of soil trenching needed 150 – 200 GPR Clearance, Driller/Excavator, ERI Stadium Feasibility Study $10,000 - $12,000 Influenced by options the town may want explored 50 – 60 None Wetland Delineation $6,500 40 None Topographic Survey $22,000 100 None Drainage and Soil Investigations $11,500 40 Video Inspection, Third-Party Lab Testing Geotechnical Investigation – Lighting $20,000 60 GPR Clearance, Driller/Excavator Total Estimated Fee: $100,000 - $112,000 Phase 1 – Investigation Timeline The timeline provided below assumes that the Town will select SLR at the Public Building and Capital Project Committee (PBCPC) meeting on October 14. Following selection, SLR will prepare a detailed scope of services for the Town's review and approval, either prior to or at the subsequent PBCPC meeting. Upon approval of the scope and successful contract negotiations,
Page 48
Town of Granby Investigation and Design Services for Athletic Field Improvements October 13, 2026 SLR Project No.: 141.P51644.00001 9 the Town and SLR will execute a professional services agreement by the end of the month, allowing Phase 1 activities to commence immediately thereafter. Please note that should the Town and PBCPC be able to expedite the contract process SLR is prepared to start immediately upon the approval of the detailed scope of services. We would anticipate a 2-week process to negotiate an agreed-upon scope and fee. November 2026 (See Note 1 below) December 2026 January 2027 Geotechnical Investigation - Stadium Stadium Feasibility Study Wetland Delineation Topographic Survey Drainage and Soil Investigations Geotechnical Investigation – Lighting Note 1: Should the Town desire to kickstart the contract prior to the resolution vote, SLR is available to provide a reduced initial scope focused solely on the Stadium Field and Track investigative phase. This approach can provide the Town and PBCPC with a clear path forward to detailed design, bidding, and construction, regardless of the December resolution vote. We anticipate an early November start date could be achieved under this scenario. This would also more likely allow for the investigative work to be conducted prior to winter weather delays. Note 2: Phase 1 field investigations are dependent upon suitable weather and site conditions. Should winter conditions occur earlier than anticipated, significant snow cover or frozen ground conditions may delay or limit SLR's ability to perform survey, environmental, geotechnical, and subsurface investigation activities. Should SLR be selected, a contingency plan to progress the project during winter weather can be coordinated as the detailed scope of services is finalized. Phase 2 – Design and Engineering Approach for the Stadium Field, Running Track, Field Two, and the Baseball Field: A. Design Development a. Following completion of the geotechnical, drainage, survey, and environmental investigations, SLR will develop design documents for the reconstruction of the Stadium Field and Running Track, replacement of the Field Two synthetic turf system, and construction of a new synthetic turf baseball/multipurpose field at the location of the existing baseball field. Design solutions will incorporate the findings and recommendations of the Phase 1 investigations and will address grading, drainage, stormwater management, accessibility, and other site-specific requirements. SLR will begin by preparing new conceptual design plans,
Page 49
Town of Granby Investigation and Design Services for Athletic Field Improvements October 13, 2026 SLR Project No.: 141.P51644.00001 10 incorporating the requested improvements at each site. Once these plans have been reviewed and approved by the PBCPC, we will advance the plans to a level of design suitable for review and approval by Town land use commissions. B. Permitting Assistance a. SLR will assist the Town with the preparation and submission of applications to the Inland Wetlands and Watercourses Commission and the Planning and Zoning Commission, as required. Services will include preparation of supporting exhibits and technical documentation, attendance at public meetings, and presentation of the proposed improvements to facilitate regulatory review and approval. C. Final Construction Documents a. Following receipt of all required approvals, SLR will finalize the construction documents and incorporate any conditions imposed during the permitting process. The final bid package will include signed and sealed engineering drawings, technical specifications, and other documents necessary to publicly bid the work and secure qualified construction contractors. D. Opinions of Probable Construction Cost a. Throughout the design process, SLR will prepare and update Opinions of Probable Construction Cost for each individual project component, including the Stadium Field and Track, Field Two, and Baseball Field. SLR will also prepare a consolidated cost estimate evaluating the full program of improvements, allowing the Town to assess potential phasing strategies and establish project budgeting priorities. In accordance with the Town’s request for information limited to the development of a bid-ready project, bid-phase and construction-phase services are excluded from the scope and fee presented herein. SLR is available and fully qualified to provide these services should the Town require them in the future. Phase 2 – Design and Engineering Estimated Fees for the Stadium Field, Running Track, Field Two, and the Baseball Field: SLR estimates the fee range for Phase 2 to be $425,000 to $485,000. Below is a simple breakdown of our estimated fee for Phase 2 assessments and investigations: SLR’s Estimated Fees Estimated Staff Hours SLR Subcontractors Design Development $125,000 -$150,000 600 – 750 Electrical Engineer Permitting Assistance $15,000 - $25,000 70 – 120 None Final Construction Documents $275,000 - $325,000 1,300 – 1,600 Electrical Engineer Opinions of Probable Construction Costs $10,000 50 None Total Estimated Fee: $425,000 - $485,000
Page 50
Town of Granby
Investigation and Design Services for Athletic Field Improvements
October 13, 2026
SLR Project No.: 141.P51644.00001
11
Phase 2 – Design and Engineering Timeline for the Stadium Field, Running Track,
Field Two, and the Baseball Field:
Upon completion of the Phase 1 investigations and subsequent authorization to proceed, SLR
proposes the following schedule for design and engineering services. This timeline assumes
that Phase 1 activities are completed in accordance with the previously outlined schedule and
that the PBCPC authorizes Phase 2 services shortly thereafter, allowing the project to advance
without interruption.
January
2027
February
2027
March
2027
April
2027
May
2027
June
2027
Preliminary
Design
Permitting
Assistance*
Final
Design
Opinions of
Probable
Construction
Costs
* Permitting review and approval schedules are controlled by the applicable regulatory commissions and
are outside of SLR's control. While SLR may proceed with final design concurrent with permit review to
maintain project momentum, doing so carries risk as permit conditions or agency comments may require
design revisions, resulting in additional effort, cost, and schedule impacts before the project is ready for
bidding.
Deliverables Summary
Phase 1:
• Stadium Field and Track Geotechnical Report Including Electrical Resistivity Imaging
(ERI) And Linear Trenching Results
• Stadium Field and Track Drone Based Photogrammetry and Topographic Mapping
• Stadium Field and Track Red/Green Report
• Stadium Field and Track Turf Assessment, Removal and Recycling Data
• Field 2 And Baseball Field Topographic Survey Base Mapping
• Baseball Field Soil Assessment
• Baseball Field Lighting Geotechnical Report
• Drainage Assessment – All Fields
• Wetland Delineation Report
Phase 2:
• Detailed Design Plans – Preliminary and Final Design
• Permitting Assistance Including Applications and Presentation Exhibits
• Technical Specifications
• Opinions Of Probable Construction Costs– Three Submissions Assumed
Page 51
Town of Granby Investigation and Design Services for Athletic Field Improvements October 13, 2026 SLR Project No.: 141.P51644.00001 12 Exclusions And Limitations Please note that the following services have not been considered when preparing this project service narrative and, therefore, have not been accounted for in our estimated fees: 1. Boundary survey 2. Archaeology studies 3. Design of offsite improvements and/or offsite drainage capacity analysis 4. Traffic impact studies 5. Building design 6. Mechanical, plumbing, and fire safety engineering 7. Design and engineering of any additional items beyond the scope of the preliminary design effort described herein 8. Bid assistance 9. Construction-phase services SLR and Granby SLR's proposed approach is designed to provide the Town with the technical information, planning framework, and cost certainty necessary to make informed decisions regarding future improvements to its athletic facilities. Through a comprehensive program of site investigations, field assessments, engineering analyses, and stakeholder coordination, we will establish a clear understanding of existing conditions, opportunities, and constraints. The resulting deliverables will position the Town to advance confidently into design, permitting, and construction while minimizing risk, controlling costs, and supporting successful project implementation. We will be the Town’s experts and can confidently assure the Town and Building Committee that a successful outcome will be achieved. By selecting SLR, you will be gaining a strategic partner with all critical services provided by in-house experts, allowing us to better control schedule, response times, and quality. We are committed to our clients and will provide Granby with the information necessary to build high-quality athletic facilities that showcase the thoughtfulness, ingenuity, and fiscal responsibility of Town staff and Town residents alike. We sincerely appreciate the opportunity to assist the Town with this transformational project. Should you require any additional information, please do not hesitate to contact either of the individuals listed below. Regards, SLR International Corporation Kevin Fuselier, PLA, LEED GA Senior Principal / Team Leader, Landscape Architecture kkuselier@slrconsulting.com Michael T. Doherty, PLA North America Practice Leader, Landscape Architecture mtdoherty@slrconsulting.com 141.12712.p0007.o1326.prop
Page 52
REQUEST FOR PROPOSAL Town of Granby MEP Work at Granby Memorial Middle School October 13, 2026
Page 53
BL Companies Table of Contents Section I Letter of Interest Section II Firm Overview Section III Project Approach Section IV Relevant Project Experience Section V Fee Proposal
Page 54
SECTION I Letter of Interest
Page 55
October 13, 2026 Mr. Michael Walsh Town Manager Town of Granby 15 North Granby Road Granby, CT 06035 Re: Granby Memorial Middle School - MEP Engineering Proposal Dear Mr. Walsh, BL Companies Connecticut, Inc. (“BL Companies”) is pleased to submit our qualifications and fee proposal for MEP Engineering Services for the HVAC investigation and design services at Granby Memorial Middle School. With our extensive in-house capabilities, proven public school experience, and commitment to responsive, high-quality service, we are well-equipped to support the Town of Granby through these important services. We understand that these projects demand technical precision, thoughtful coordination, and a strong understanding of both school operations and grant reimbursement processes. Our team brings decades of experience delivering MEP and structural services across Connecticut K–12 environments — including site surveys, existing conditions assessment reports, design from schematic design through permit and construction documents, construction administration, field observation, RFI and submittal review, change order evaluations, and close collaboration with all project stakeholders. Your scope includes: • Mechanical, Electrical, Plumbing, and Fire Protection Engineering services for the investigation, evaluation, assessment, and prioritized recommendations for additions, modifications, and replacement of select MEP system. • Following the initial investigation phase, design and engineering services for the priority MEP improvements to develop engineering plans and specifications suitable for bidding and construction. • Cost estimating. BL Companies is proud to offer: • Comprehensive In-House Expertise – Our team includes licensed engineers and LEED-accredited professionals across MEP, Architecture, Structural, and Civil disciplines, all under one roof. 355 Research Parkway, Meriden, CT 06450 T (203) 630-1406 www.blcompanies.com
Page 56
• Proven K–12 and Municipal Experience – We’ve supported HVAC renovations, system upgrades, and construction phase services at numerous public schools throughout the state. • Dedicated Resources and Local Capacity – With over 30 MEP professionals and more than 384 employees company-wide, we have the capacity and flexibility to fully support both projects over the anticipated 18-month schedule. Thank you for the opportunity to submit. We are enthusiastic about the potential to support the Town of Granby and remain available to discuss our qualifications in more detail. Sincerely, BL Companies Evan Silberquit, PE MEP Manager - Principal 860.760.1907 esilberquit@blcompanies.com 355 Research Parkway, Meriden, CT 06450 T (203) 630-1406 www.blcompanies.com
Page 57
SECTION II Firm Overview
Page 58
About BL Companies Your Partner for Integrated Services & Creative Solutions. Founded in 1986, BL Companies delivers an integrated blend of architecture, engineering, environmental, and land surveying services on projects throughout the United States. Our multidisciplinary teams collaborate daily to plan, design, and develop the spaces and infrastructure that shape everyday life. From small assignments to large, complex programs, we approach each project with the agility and insight needed to provide creative, high‑quality solutions grounded in technical expertise. BL Companies is a leading multidiscipline firm, regularly ranked as a Top 500 Design Firm by Engineering News Record. With over 150 licensed professionals, BL Companies brings the resources and capabilities of a large firm while our employee‑ownership culture and commitment to client care ensures we provide the personal, attentive service of a small firm. Driven by a culture of excellence and responsiveness, we remain firmly committed to total client satisfaction and consistently deliver exceptional results. As a 100% employee‑owned owned company, we believe in the power of teamwork and long‑lasting partnerships. Our dedicated employees are the backbone of our firm and our professional community. Being employee‑owned and team‑oriented means we celebrate each other’s successes as a united force because there are no boundaries to what we can achieve when working together. Our tagline, “Employee Owned. Client Driven.”, isn’t just a phrase to us; it informs our collaborative process and encourages us to deliver solutions that go beyond individual efforts, ensuring a result that surpasses client expectations. SERVICES Architecture Civil Engineering Environmental Services Land Surveying & Geospatial Services Construction Administration Energy Services Landscape Architecture MEP Engineering Planning Structural Engineering Subsurface Utility Engineering Transportation Engineering PEOPLE ESTABLISHED OUR MISSION Our mission is to provide creative solutions that enhance the built and natural environment through the leadership and dedication of our employee owners working in partnership with our clients. EMPLOYEE-OWNED ENR TOP 500 FIRMS OFFICES 18 365+ 1986 100% 231 13 STATES BL Companies
Page 59
BL Companies Office Locations CONNECTICUT Meriden (Corporate HQ) 355 Research Parkway Meriden, CT 06450-7100 Hartford New East Hartford Office opening soon!
Page 60
BL Companies KEY SERVICES Heating, Ventilation & Air Conditioning (HVAC) Central Heating & Cooling Plants Air, Water & Ground Source Heat Pump Systems Variable Refrigerant Flow (VRF) Systems Energy Recovery Systems Sustainable Design Solutions Energy Modeling & Life Cycle Cost Analyses Energy Conservation Studies Indoor Air Quality Analyses & Improvements Code Compliance Studies Integrated Control Systems & Building Management Systems MECHANICAL ENGINEERING Engineering Smarter Spaces from the Inside Out BL Companies delivers integrated solutions for the design, management, and maintenance of building and facility systems. With comprehensive in-house expertise in mechanical, electrical, plumbing (MEP), and fire protection engineering, we support all phases of building design, renovation, and modernization. Our MEP professionals work closely with clients to design comfortable, healthy, and high-performing indoor environments. We take a collaborative approach to understand the unique operational, budgetary, and sustainability goals of each project— whether designing a new system or upgrading an existing one. At the core of every successful project is a well-designed system. Our Mechanical Engineering Team develops energy-efficient, cost- effective, and environmentally responsible solutions that are safe, reliable, and easy to maintain. As a member of the U.S. Green Building Council with LEED accredited professionals on staff, BL is committed to creating flexible, future-ready systems that enhance building performance for years to come.
Page 61
BL Companies KEY SERVICES Renewable, Distributed Generation & Microgrid Systems High & Medium Voltage Substations & Distribution Systems Low Voltage Power Distribution Systems Ups, Emergency, Standby & Mission Critical Systems Fire Alarm & Life Safety Systems Telecommunication & Computer Data Systems Grounding & Lightning Protection Systems Ev Charging Station Design PV System Design ELECTRICAL ENGINEERING Designing Reliability Into Every Connection BL Companies delivers full-service electrical engineering solutions for all phases of building design and renovation. Our team designs safe, reliable, and energy-efficient systems— integrating lighting and power distribution with architectural intent to enhance performance, support sustainability, and reduce carbon footprint. We collaborate closely with clients to create flexible, cost-effective systems that can adapt to future needs. As a member of the U.S. Green Building Council, our work is backed by LEED accredited professionals committed to long-term building resilience. • Public Address, Av And Sound Systems • Architectural Lighting Design • Site Lighting Design • Lighting Controls • Photometric Modeling • Short-Circuit, Coordination & Arc Fault Analysis • Power Quality & Harmonic Analysis • Theater Lighting SPECIALTIES
Page 62
BL Companies KEY SERVICES Domestic Water Distribution Domestic Hot Water Systems Passive Drainage Waste and Vent Systems Sanitary Waste Treatment Systems Pumped Waste and Ejector Systems Storm Water Recycling Systems Fuel Gas Systems Commercial Kitchen Systems Plumbing Code Studies PLUMBING ENGINEERING Efficient Plumbing Engineering for Modern Buildings At BL Companies, we design high-performing plumbing systems that meet the demands of today’s increasingly complex buildings. From efficient domestic water supply and hot water systems to gravity-based waste and vent systems, our “less is more” approach emphasizes reliability, sustainability, and smart design. We offer innovative solutions like vacuum drainage for challenging retrofits, and our team is experienced in specialized systems for hospitals and laboratories—including medical gas and acid waste treatment. Every design incorporates water-saving strategies, reflecting our commitment to conserving resources and protecting the public water supply. • Solar Domestic Hot Water Systems • Vacuum Drainage Systems • Water (Grey Water) Recovery and Recycling • Pharmaceutical RO / DI Water Systems • Bulk Gaseous Storage Systems • Laboratory and Medical Gas Systems • Laboratory Compressed Air and Vacuum • Laboratory Waste Collection / Treatment • Specialty Gas Systems • Hospital and Clinical Piped Services • Process Liquid and Gas Systems • Water Conservation Studies • LEED & HPB Compliant Systems SPECIALTIES
Page 63
BL Companies KEY SERVICES Wet Automatic Fire Suppression Systems Dry, Deluge & Pre-Action Fire Sprinkler Systems Standpipe Systems Fire Alarm and Detection Systems Smoke Evacuation and Exhaust Condition Assessment and Due Diligence Studies Code Compliance Studies Site Distribution Systems FIRE PROTECTION ENGINEERING Engineered for Safety, Designed to Protect BL Companies provides specialized fire protection engineering services tailored to each project’s unique hazards and requirements. Our experienced team designs code-compliant suppression systems—from standard water-based sprinkler and standpipe systems to advanced solutions like clean agent systems and double-interlock pre-action systems with non-ferrous components. Whether designing for new construction or retrofitting systems for renovations and reconfigurations, we deliver safe, effective, and reliable fire protection solutions for every type of building. • Fire Pumps • Fire Water Storage • Hydraulic Piping System Analysis • Foam Special Hazard Systems • Gaseous Extinguishing Systems SPECIALTIES
Page 64
BL Companies KEY SPECIALTIES New Construction & Additions Rehabilitation & Renovation Historic Preservation Adaptive Reuse Prototype Design and Development Interior Architecture Sustainable Design 3D Visualizations ARCHITECTURE Blending Creativity with Technical Expertise By establishing a clear understanding of our client’s objectives, BL Companies delivers thoughtful architectural designs by addressing all of the elements surrounding a project. We talk objectives, vision, schedule, and budget in order to develop designs that serve our client’s needs and enhance their environment. Our talented staff of architects has the benefit of coordinating with our in-house engineering, planning, and landscape architecture staff for seamless client service. Through rigorous cross-discipline collaboration, we deliver designs that balance aesthetics, function, cost and quality. We are also a member of the US Green Building Council, and we are proud of our commitment to sustainable design. Our staff includes multiple LEED Accredited Professionals who have produced numerous LEED-certified designs.
Page 65
BL Companies KEY SERVICES Inspections & Investigations Construction Administration & Support 3D Visualizations STRUCTURAL ENGINEERING Structurally-Sound Designs When it comes to structural engineering, our best work is never seen. This philosophy of invisible excellence seamlessly blends technical, fiscal, and environmental concerns, resulting in structurally sound designs that our clients love. Emphasizing practicality and constructibility, our solutions are as attractive as they are economical. From retail centers to mixed-use constructions, storage facilities to schools, parking structures to building renovations, and warehouse-industrial projects, we have a proven track record of success. Whatever the task, we assemble a specialized team to cater to specific requirements and foster collaboration with the design team for outstanding outcomes. • New Construction & Additions • Rehabilitation & Renovation Foundation for Pre-Engineered Metal Buildings • Retaining Walls & Excavation Support Systems • Supports for Telecommunication Equipment Equipment • Supports for Gas & Electrical Transmission Industry • Bridge Design SPECIALTIES
Page 66
BL Companies KEY SERVICES EPA Tools for Schools Inspections and IAQ Evaluations Water Damage and Moisture Mapping Investigations Microbial Assessments and Post-Remediation Verification Allergen, Odor, and Surface Sampling (Mold, E. coli) VOCs, Chemical Compounds, and Radon Testing Asbestos, Lead, and PCB Sampling (Including PCBs in Air) Construction Dust and Silica Exposure Sampling HVAC and Facility Cleanliness Inspections INDOOR AIR QUALITY Creating Healthy Indoor Spaces for Schools BL Companies provides comprehensive Indoor Air Quality (IAQ) testing and evaluation services, supported by an in-house team of industrial hygienists, scientists, engineers, and licensed field staff. Our experts currently manage IAQ programs for multiple municipalities and school districts across Connecticut and serve as one of Vermont’s primary consultants for PCB evaluations in public schools under Act 74. As part of our commitment to healthy learning environments, BL assists schools in implementing the EPA’s Indoor Air Quality Tools for Schools program—an initiative now required annually in Connecticut beginning January 1, 2024, per Public Act No. 23-167. This program establishes standardized inspection, evaluation, and reporting protocols to ensure cleaner, safer indoor environments for students and staff. BL also supports schools with HVAC inspections, moisture and mold assessments, and environmental testing to meet evolving state and federal standards. Our team partners with districts to interpret new regulations, streamline compliance, and create healthier indoor spaces for every occupant.
Page 67
SECTION III Project Approach
Page 68
BL Companies Detailed Approach and Methodology BL Companies has assembled a highly qualified team with extensive experience in supporting facility upgrade projects for K-12 schools, who will remain dedicated to this project for its duration to ensure a timely and successful completion. Additionally, our team includes licensed professionals with expertise in architectural, structural, and environmental design, providing a comprehensive and integrated approach should those disciplines be required. To further demonstrate our capabilities, we have included a selection of recent school projects within this proposal. At the start of each project, BL Companies assigns a senior professional as the primary point of contact to ensure seamless communication and effective project execution. This individual meets with the client to gain a clear understanding of project needs, objectives, and established protocols for contracting and implementation. Their role is to ensure that all assigned project staff fully understand the scope of work, contractual obligations, and required procedures. They also serve as the client’s single point of contact, streamlining communication and overseeing the delegation of all project services—regardless of scope or discipline. For Granby’s Memorial Middle School, Jesse Vose, PE, will serve as the Project Lead and primary point of contact, ensuring a responsive and coordinated approach throughout the duration
Page 69
BL Companies of the project. Once work authorization is finalized, the assigned project teams will convene for a kickoff meeting to review the scope, schedule, budget, and expected outcomes. During this meeting, we will also establish clear lines of communication with the designated client representative(s) to ensure alignment throughout the project. This proactive approach allows us to gain a thorough understanding of the Town of Granby’s needs and objectives, helping to ensure seamless and efficient execution.throughout the duration of the project. Once work authorization is finalized, the assigned project teams will convene for a kickoff meeting to review the scope, schedule, budget, and expected outcomes. During this meeting, we will also establish clear lines of communication with the designated client representative(s) to ensure alignment throughout the project. This proactive approach allows us to gain a thorough understanding of Brookfield’s needs and objectives, helping to ensure a seamless and efficient execution. Effective communication is essential at every phase of a project to achieve a successful outcome. Our primary project contact will be responsible for ensuring clear and consistent communication from start to finish. Should any of the Town of Granby’s representatives have any concerns regarding service expectations, our primary point of contact will be readily available to address and resolve any issues. Additionally, a designated principal is assigned to each contract to monitor performance and serve as a high-level liaison, ensuring accountability and client satisfaction. PROJECT SCOPE & OBJECTIVES BL Companies understands that the Town of Granby is seeking a phased approach to address code and MEP needs at Granby Memorial Middle School. The immediate objective is to identify practical repairs and improvements within the proposed $3,000,000 total project budget, while establishing a plan for a larger bond issue in seven years. Our approach will focus on equipment reliability, ventilation, fire protection, and the supporting building systems needed to keep the school operating. We will review the available assessments, record drawings, site photographs, and maintenance history to build on work already completed. The June 2026 HVAC study identifies ventilation and controls deficiencies that will be evaluated together with the equipment condition and operating concerns documented by school staff. Following collaboration with the Town to prioritize and finalize the Phase 1 scope of work, we will prepare construction documents suitable for soliciting competitive public bids. These documents will include plans, elevations, sections, details, schedules, and notes, as required. In addition to the drawings, a complete set of specifications will be prepared. We will also provide a cost estimate based on the construction documents. At all phases of the project, communication will be important to maintaining an agreed scope and budget. We will review findings and recommendations with the Town before advancing the selected improvements into design. Proposed work will account for school occupancy, access to existing equipment, shutdown requirements, and the Town’s longer-term plans for the facility. We will maintain communication with Town staff, school facilities personnel, and the Public Building and Capital Project Committee.
Page 70
BL Companies The goal of this project is to investigate existing conditions, identify applicable code requirements, and prepare a prioritized implementation plan for the Middle School. A general overview of the scope includes the following: • Review the existing assessments, ventilation measurements, record drawings, site notes, and photographs, followed by verifying conditions affecting the proposed improvements. • Evaluate HVAC equipment, outdoor air delivery, exhaust, controls, and supporting electrical and plumbing systems. Review existing fire protection coverage and available water supply information. • Identify near-term repairs and replacements, associated building impacts, and work that can be deferred to the larger capital program. • Develop engineering plans, specifications, and a construction cost estimate for the finalized design scope selected by the Town. PHASING This project will be delivered in the following two phases: • Phase 1 – Investigation • Phase 2 – Design & Engineering Phase 1 - Investigation – BL Companies to meet with the Town and school facilities staff to confirm priorities, funding assumptions, school operating constraints, and the investigation schedule. Gather and review the existing condition assessments, June 2026 HVAC study and testing data, 2025 visual inspection, record drawings, maintenance records, and site documentation. – Visit the site to review accessible equipment and building conditions. Verify equipment identification, recent replacements, roof and mechanical room access, available ceiling space, and installation routes. Document conditions affecting the proposed work, including visible corrosion, insulation, piping, roof penetrations, and maintenance access. – Evaluate air handling units, rooftop units, condensing units, return and exhaust fans, VAV boxes, hydronic systems, and controls. Review outdoor air ventilation requirements for typical listed room uses and occupancies, and assess space heating, cooling, and dehumidification capabilities along with the Town’s priorities for those spaces. Reconcile inconsistencies in the reports and provide recommendations. – Review occupancy, construction type, existing sprinkler coverage, fire alarm interfaces, and code requirements applicable to the proposed sprinkler system work. Review well and water supply records and available flow information to identify whether additional testing, storage, a fire pump, or other infrastructure would be needed to support sprinkler improvements. – Assess electrical capacity, distribution, and equipment connections. Assess the electrical priorities identified in the condition report, including panels, ground-fault protection, and emergency lighting.
Page 71
BL Companies – Review plumbing, domestic hot water heaters, and condensate disposal systems. Verify the condition and capacity of equipment proposed to remain before recommending replacement or reuse. – Develop prioritized repair and replacement options with existing planning-level construction costs up to $3,000,000 as authorized by the Town. – Evaluate controls replacement and repairs, ventilation, selective equipment replacement, and supplemental ventilation where appropriate. – Identify improvements that can remain useful in the longer-term plan and distinguish immediate needs from comprehensive system renewal in the longer term, identifying deferred improvements, remaining service-life risks, and the relationship between near- term work and a future larger bond program. – Issue investigation and assessment results summarizing existing conditions, code considerations, options, recommended priorities, preliminary costs, and implementation sequencing. Review with the Town and PBCPC and confirm the scope, budget, and design criteria to advance into Phase 2. Phase 1 - Schedule For planning purposes, allow approximately four to six weeks after authorization and receipt of available records for investigation and preparation of recommendations, followed by Town review. The schedule will be confirmed at kickoff and will depend on access to occupied areas, operating conditions, and any additional issues identified during the investigation. Phase 2 - Design & Engineering – Confirm the Town-selected scope, available construction budget, and design criteria developed in Phase 1. Establish design review milestones and coordinate the anticipated construction sequence with the school calendar and equipment procurement requirements. – Perform focused field verification for the selected improvements. Confirm connection points, dimensions, existing services, access and rigging routes, and ceiling or finish impacts needed to develop coordinated construction documents. – Develop HVAC and controls designs for the selected work, including equipment selections, ventilation calculations, ductwork and piping modifications, control diagrams, sequences of operation, and testing and balancing requirements. Evaluate packaged replacement units where practical and address moisture control and integration with systems to remain. – Prepare design of electrical modifications required for the selected equipment, including load and capacity checks, power connections, disconnects, associated distribution changes, and controls or fire alarm interfaces as applicable. – Develop plumbing and fire protection modifications included in the selected scope. Address hydronic and condensate connections and, where sprinkler work is selected, establish coverage, design criteria, water supply requirements, calculations, and system interfaces appropriate to the design scope.
Page 72
BL Companies – Prepare coordinated engineering drawings and specifications defining demolition, new work, equipment, system connections, and installation requirements. – Prepare a new construction cost estimate as design progresses. Review the estimate against the agreed construction allowance to identify scope adjustments or alternates for Town consideration before finalizing the documents. – Perform interdisciplinary coordination and professional quality assurance reviews. Resolve conflicts between the proposed work and existing systems to remain. Verify that the plans and specifications reflect the agreed design criteria and budget decisions. Review the design with the Town, school facilities staff, and applicable reviewing officials. Incorporate agreed comments and issue final engineering plans, specifications, and a construction cost estimate for the Construction Documents (100% complete submission). Phase 2 - Schedule For planning purposes, allow approximately ten to fourteen weeks after approval of the Phase 1 recommendations and authorization to proceed with the selected design scope. This schedule allows a two-week period for the Town’s review of the Design Development (50% complete submission) documents. Final timing will be coordinated with Town review periods and the extent of the approved work. These durations are proposed planning allowances and do not establish a construction completion date. Clarifications • The project’s scope of work will be fully defined and authorized by the Town at the end of Phase 1 (Investigation). Any changes to the scope during Phase 2 (Design & Engineering) shall be considered additional services. • Architectural, structural engineering, and environmental services were not required by the Town of Granby’s RFP for this project. As such, they are not included in our fees but could be provided as an additional service. Our architectural, structural, and environmental teams have significant experience with school projects in Connecticut. • Bid Period and Construction Period services were not required by the Town’s RFP for this project. Similarly, they are not included in our fees but could be provided as an additional service as directed and requested by the Town, at BL’s current hourly billing rates. BL can provide construction administration services which include, but are not limited to, construction observation and site visits, review of shop drawings and submittals, responses to Requests for Information (RFIs), and review of contractors’ requests for payment. • Testing and balancing, destructive investigations, and hazardous materials testing / abatement are not anticipated requirements during the design services for Phases 1 and 2, and are not currently included in our fees.
Page 73
BL Companies RELEVANT EXPERIENCE History of Firm’s Experience in the Design of Building Infrastructure for State and Municipal Agencies Throughout its 40-year history, BL Companies has successfully delivered infrastructure design for a wide range of municipal and educational facilities. Our experience includes both recent and long- standing engagements with state and local agencies. Highlights include: • Public K-12 Schools: BL Companies has extensive experience designing HVAC upgrades and infrastructure improvements for public schools across Connecticut. Recent projects include: – Berlin: Griswold Elementary School and Hubbard Elementary School – East Granby: East Granby Middle School and High School – Ellington: Center School, Ellington Middle School, and Ellington High School – Fairfield: Osborn Hill Elementary School, North Stratfield Elementary School, Fairfield Woods Middle School, Tomlinson Middle School, Walter Fitzgerald Campus, Fairfield Ludlowe High School, and Fairfield Warde High School – Madison: Polson Middle School and Daniel Hand High School – Manchester: Illing Middle School – Norwich: Kelly STEAM Magnet Middle School – Stonington: Mystic / Stonington Middle School – Stamford: Scofield Magnet Middle School, Turn of River Middle School, Rippowam Middle School, Stillmeadow Elementary School, and Stamford High School – Waterbury: Driggs Elementary School, Washington Elementary School, M.M. Generali Elementary School, Maloney Interdistrict Magnet School, Walsh Elementary School, Hopeville Elementary School, F.J. Kingsbury Elementary School, Tinker Elementary School, Wilby High School, North End Middle School, Crosby High School, Michael F. Wallace Middle School, John F. Kennedy High School, West Side Middle School, and H.S. Chase Elementary School – Wilton: Cider Mill School In addition to HVAC upgrades, BL Companies has also provided full design services for new construction, renovations, and additions, including: – Meeting House Hill Elementary School (Additions and Renovations) – Mary M. Hooker Environmental Magnet School (New Construction) – New Haven Academy (Renovate-as-New) • Facility Assessments: BL Companies regularly conducts equipment condition assessments, facility condition assessments, and property condition assessments. Recent examples include: – Madison Public Schools: HVAC, Electrical, and Fire Protection Assessments – Stonington High School: HVAC and Building Envelope Assessments
Page 74
BL Companies – Coventry Public Schools: HVAC, Energy Efficiency, and Architectural Assessments – Guilford Public Schools: HVAC and Electrical Assessments – Connecticut Department of Transportation: MEP assessments for all DOT buildings and assets – Connecticut Public Transit Authority: MEP assessments, recommendations, and cost estimating for all transit authority buildings • Government and Judicial Facilities: BL Companies has delivered new construction, renovations, code compliance, energy upgrades, and HVAC improvements for various civic and judicial facilities, including: – Litchfield Courthouse: Cooling Tower Study – New Haven Courthouse: Chiller Replacement – Stamford Courthouse: Chiller Replacement and Parking Garage (New Construction) – Bridgeport Courthouse: AHU Replacement – Hartford City Hall: Code, Energy, and HVAC Improvements – Connecticut General Assembly: Boiler Plant Replacement • Regulatory Agencies: BL Companies has extensive experience coordinating with regulatory bodies such as: – Connecticut Department of Administrative Services (CTDAS) – Bureau of School Facilities / Office of School Construction Grants – Connecticut Department of Energy and Environmental Protection (CTDEEP) – We are also highly experienced in designing to Connecticut High Performance Building Standards, with several successful projects including:
Page 75
SECTION IV Relevant Project Experience
Page 76
BL Companies Polson Middle School Madison, CT BL Companies provided mechanical, electrical, and plumbing design services for the 149,000 SF Polson Middle School. Phase 1 of the renovation included verifying existing conditions and equipment, assessing heating and non-air-conditioned areas, conducting a detailed energy model, specifying three HVAC systems with analysis, evaluating the electrical power system, sizing a generator for the school, studying fire protection impacts, providing professional estimates, and evaluating geothermal system feasibility using existing wells for thermal testing. Schematic design was developed for a system compatible with the proposed HVAC. Phase 2 included construction documents, bidding, and construction administration services to implement the selected improvements of new HVAC systems, electrical power upgrades, and auditorium renovation. PROJECT FACTS KEY SERVICES Architecture MEP Engineering Structural Engineering
Page 77
BL Companies Fairfield Woods Middle School Fairfield, CT The Fairfield Woods Middle School project was a $16.1 million renovation of a 177,000 SF elementary school. Mechanical, electrical, plumbing, fire protection, architectural, and structural design services associated with new and replacement HVAC systems to serve 80,000 SF of the school. New systems included packaged rooftop air-handling units, packaged dedicated outside air systems (DOAS), variable refrigerant flow (VRF) systems, building management system (BMS) upgrades throughout the facility, new electrical service, and structural modifications to support new mechanical equipment. PROJECT FACTS KEY SERVICES MEP Engineering Fire Protection Engineering Structural Engineering Architectural Services Commissioning Support Construction Administration
Page 78
BL Companies North Stratfield Elementary School Fairfield, CT The North Stratfield Elementary School project was a $11.5 million renovation of a 61,000 SF elementary school. Mechanical, electrical, plumbing, fire protection, architectural, and structural design services associated with new and replacement HVAC systems to serve 51,000 SF of the school. New systems included packaged rooftop air-handling units, packaged dedicated outside air systems (DOAS), variable refrigerant flow (VRF) systems, building management system (BMS) upgrades throughout the facility, structural modifications to support mechanical equipment, new electrical service, new lighting, and new ceilings. PROJECT FACTS KEY SERVICES MEP Engineering Fire Protection Engineering Structural Engineering Architectural Services Commissioning Support Construction Administration
Page 79
BL Companies Osborn Hill Elementary School Fairfield, CT The Osborn Hill Elementary School project was a $8.1 million renovation of a 55,000 SF elementary school. Mechanical, electrical, plumbing, fire protection, architectural, and structural design services associated with new HVAC systems to serve 32,000 SF of the school. New systems included packaged dedicated outside air systems (DOAS), variable refrigerant flow (VRF) systems, building management system (BMS) upgrades throughout the facility, structural modifications to support mechanical equipment, new electrical service, new lighting, and new ceilings. PROJECT FACTS KEY SERVICES MEP Engineering Fire Protection Engineering Structural Engineering Architectural Services Commissioning Support Construction Administration
Page 80
BL Companies Tomlinson Middle School Fairfield, CT The Tomlinson Middle School project was a $4.7 million renovation of a 167,000 SF middle school. Mechanical, electrical, plumbing, fire protection, architectural, and structural design services associated with new HVAC systems to serve 17,000 square feet of the school. New systems included packaged rooftop air-handling units, building management system (BMS) upgrades, lighting, ceilings, and structural modifications to support mechanical equipment. PROJECT FACTS KEY SERVICES MEP Engineering Fire Protection Engineering Structural Engineering Architectural Services Commissioning Support Construction Administration
Page 81
BL Companies Illing Middle School Manchester, CT The Illing Middle School project was a $3.3 million rooftop air-handling unit replacement at a 138,000-square-foot middle school. Services included full MEP engineering design for the replacement of existing rooftop air-handling units with custom multi-zone systems, coordination of new distribution and controls integration, and complete new HVAC systems to add air conditioning to the gym. PROJECT FACTS KEY SERVICES Mechanical Engineering Electrical Engineering Plumbing Engineering
Page 82
BL Companies Ellington Schools Ellington, CT The Ellington School projects were a $13.1 million renovation of Center School, Ellington Middle School, and Ellington High School totaling 288,000 SF. Mechanical, electrical, plumbing, architectural, and structural design services associated with HVAC system upgrades and replacement. New systems included packaged dedicated outside air systems (DOAS) for ventilation, a complete replacement of the boiler plant consisting of boilers, pumps, hydronic components, and piping, building management system (BMS) to serve both new and existing equipment throughout the facility, structural modifications to support mechanical equipment, and ceilings as required to install new ductwork. PROJECT FACTS KEY SERVICES MEP Engineering Structural Engineering Architectural Services
Page 83
BL Companies Fairfield Warde High School Fairfield, CT The Fairfield Warde High School project includes a $36 million renovation of a 318,000 SF high school. Mechanical, electrical, plumbing, fire protection, architectural, structural, and civil design services associated with new HVAC systems to serve 142,000 square feet of the school. New systems included packaged rooftop air-handling units, packaged dedicated outside air systems (DOAS), variable refrigerant flow (VRF) systems, building management system (BMS) upgrades throughout the facility, electrical service, lighting, ceilings, and structural modifications to support mechanical equipment. PROJECT FACTS KEY SERVICES MEP Engineering Fire Protection Engineering Structural Engineering Civil Engineering Architectural Services
Page 84
BL Companies Fairfield Ludlowe High School Fairfield, CT The Fairfield Ludlowe High School project includes a $55 million renovation of a 307,000 SF high school. Mechanical, electrical, plumbing, fire protection, architectural, structural, and civil design services associated with new HVAC systems to serve 206,000 square feet of the school. New systems included packaged rooftop air-handling units, packaged dedicated outside air systems (DOAS), variable refrigerant flow (VRF) systems, building management system (BMS) upgrades throughout the facility, electrical service, lighting, ceilings, and structural modifications to support mechanical equipment. PROJECT FACTS KEY SERVICES MEP Engineering Fire Protection Engineering Structural Engineering Civil Engineering Architectural Services
Page 85
BL Companies Walter Fitzgerald Campus Fairfield, CT The Walter Fitzgerald Campus project includes a $6 million renovation of an 18,000 SF high school. Mechanical, electrical, plumbing, fire protection, architectural, structural, and civil design services associated with a new fire protection sprinkler system to serve the entire building, plus new HVAC systems to serve 5,500 square feet of the school. New systems include fire protection sprinkler system, fire water service, packaged rooftop air-handling units, building management system (BMS) upgrades, building management system (BMS) upgrades, electrical service, lighting, ceilings, and structural modifications to support mechanical equipment. PROJECT FACTS KEY SERVICES MEP Engineering Fire Protection Engineering Structural Engineering Civil Engineering Architectural Services
Page 86
BL Companies Scofield Magnet Middle School Stamford, CT The Scofield Magnet Middle School project includes a $2.5 million replacement of packaged rooftop air-handling units totaling 485 tons of cooling, upgrades to the building management system (BMS) throughout the facility, and installation of a new Music Room HVAC system at a 142,000 square foot school. Project included mechanical engineering, electrical engineering, commissioning support, and construction administration services. PROJECT FACTS KEY SERVICES Mechanical Engineering Electrical Engineering Commissioning Support Construction Administration
Page 87
BL Companies Turn of River Magnet Middle School Stamford, CT The Turn of River Middle School project involved the replacement and renovation of the school’s boiler plant serving the heating hot water and domestic hot water systems at a 125,000 SF school. Old cast-iron boilers, standard-efficiency domestic hot water heater, and constant volume pumps were replaced with new high-efficiency condensing boilers, condensing water heaters, and variable speed pumps. PROJECT FACTS KEY SERVICES Mechanical Engineering Electrical Engineering Plumbing Engineering Commissioning Support Construction Administration
Page 88
BL Companies Stonington High School HVAC Evaluation Stonington, CT BL Companies provided Mechanical, Retro-Commissioning, Building Energy Assessment, and Thermal Imaging services for Stonington Public Schools. This study identified HVAC, Building Management System, and Building Thermal Envelope deficiencies through thermal scans and equipment assessments. Recommendations included replacement parts, refurbishment specs, and modernization options. BL Companies helped the Town develop a phased plan for addressing these issues, supporting a comprehensive capital improvements and maintenance strategy. PROJECT FACTS KEY SERVICES Energy Efficiency MEP Engineering Cost Estimating
Page 89
BL Companies Mystic / Stonington Middle School Mystic, CT BL Companies provided mechanical, electrical, and plumbing design services for the 85,000 SF Mystic / Stonington Middle School. The scope of work included new Dedicated Outside Air Systems (DOAS) for ventilation, Variable Refrigerant Flow (VRF) systems for heating and cooling, Rooftop Units (RTU) for heating, cooling, and ventilation of the gym and café, associated duct & piping systems, and a new electrical service including 2000A switchboard, distribution panels, and associated equipment. PROJECT FACTS KEY SERVICES MEP Engineering Architecture Structural Engineering
Page 90
SECTION V Fee Proposal
Page 91
BL Companies Fee Proposal PHASES TASKS FIXED FEE Phase I Investigation $27,500 Phase 2 Design & Engineering (Design Development - 50% Complete) $52,500 Design & Engineering (Construction Documents - 100% Complete) $60,000 TOTAL $140,000
Page 92
CT H2M Architects, Engineers, Geology, Land Surveying and Landscape Architecture, DPC (NY) offers its services in NY only H2M Architects & Engineers, Inc. (NJ) offers its services in NJ, CT, DE, FL, LA, MA, PA, RI, SC, VA only H2M Associates, Inc. (NJ) offers its engineering, land surveying, landscape architecture services in NJ only h2m.com October 13, 2026 Mr. Michael P. Walsh Granby Town Manager 15 N. Granby Road Granby, CT 06035 Re: Proposal for Granby Middle School HVAC Replacements H2M Proposal No.: LP262054 Dear Mr. Walsh: H2M Architects & Engineers, Inc. (H2M) is pleased to provide this proposal in response to the Granby Public School (GPS) RFP/BOS Resolution received approximately September 24, 2026, and subsequent FCA report dated 2026 to design the replacement of various HVAC systems at the Middle School. The MEP design services to be provided includes evaluation of the scope of work items identified in the 2026 Studio Jaes report and development of construction documents of the highest priority selected equipment. Our project understanding and deliverables are further described as follows. PROJECT UNDERSTANDING Based on the RFP, it is our understanding that most of the HVAC systems under consideration for replacement are original to the building and have exceeded their useful life expectancy. The equipment is on the order of 34 years old and replacement parts are difficult or impossible to obtain. In many cases, the rooftop unit fresh air dampers are set below minimum ventilation, not operating or stuck closed, providing insufficient ventilation air to the spaces served. VAVs are not consistently responding to controls, further negatively impacting occupancy comfort and health. It was stated during the walk-through that the band and chorus rooms exhibit high humidity suspected as the result of oversized rooftop units. The Honeywell Niagara building management system is also in need of replacement. Based on the preliminary information provided, it can be deduced that the building is likely highly negatively pressurized due to insufficient fresh air supply from the rooftop units. With the toilet exhaust fans operating, this results in un-tempered (in the winter) and non-conditioned air to infiltrate the building. Cold drafts in the winter can cause pipe freeze-ups and humid air infiltration in the summer will lead to uncontrolled high humidity and possible mold growth. Furthermore, if MERV-13 filters were installed in the rooftop units in response to COVID without rebalancing the units, the associated spaces likely have insufficient air change rates, further reducing the ability of the HVAC system to dilute and remove odors, humidity, and germs. Our team understands that the success of this project relies on integration of the existing infrastructure and distribution with new modern mechanical, electrical, and control technology systems. The design must provide safe, healthy, and energy-efficient environments within the established construction budget. The project will require careful assessment of existing systems, verification of available capacities, and development of engineering solutions that support both operational requirements and long-term reliability. H2M has the in-house capability to conduct a variety of field testing to verify existing conditions. Although GPS has provided the 1991 bid drawings, we do not simply rely on this information to be accurate, nor as-built. H2M performs extensive field surveys to develop accurate existing conditions plans to mitigate the possibility
Page 93
H2M Proposal #262054 October 13, 2026 Page 2 of 8 of unforeseen problems during construction. Aside from geometric and observable physical characteristics, H2M also deploys special tools to confirm system operation, including but not limited to: 1. Ultrasonic Hydronic Flow Measurement This is a non-destructive tool that is used to measure flow in piping. For this school specifically, it will be imperative to understand the current heating hot water flow to air handling units to confirm the central pumps and distribution are properly balanced to support the new units once installed. During design, the flow data will be used as a diagnostic tool to help identify additional work that may be required. The construction documents will require system balancing by a certified third-party balancer. 2. Turbine and Flow Hood Measurement This is a non-destructive tool used to measure air flow at duct outlets/returns (hood) and at fans or other in-line points (turbine). For this project, and typically for most, we perform specific airflow measurements in specific areas of concern to help identify if the observed conditions are a result of poor airflow, supply air temperature, and control (in conjunction with next item), space pressurization. Similar to above, this is used as a diagnostic tool to help identify additional work that may be required. The construction documents will require system balancing by a certified third-party balancer. 3. Temperature and Humidity Data Loggers These small portable devices (the size of flash drives) can be deployed throughout various spaces and record temperature and humidity and generate trended logs to help identify control and capacity issues. This removed subjective opinions about conditions and provides hard data that can be used to resolve issues.
Page 94
H2M Proposal #262054 October 13, 2026 Page 3 of 8 4. Thermal Imaging and 3D Scanning Thermal imaging is an invaluable tool to locate drafts in negatively pressurized buildings and leaks or deteriorated insulation behind walls and underground. This can reduce the risk of pipe freezing and optimize thermal efficiency. 3D scanning is deployed to provide accurate 3D data point (clouds) of spaces later referenced during design. 5. Energy Modelling and Load Calculations In addition to energy modelling, for which H2M uses Carrier HAP (which is DOE, ASHRAE std. 140 and 90.1 approved), we can perform a screening analysis of the selected systems to better understand how they impact CO2 emissions vs. energy cost. The CO2 analysis has been specifically developed for the NYC Local Law 97 carbon reductions but is applicable to all systems (with or without emissions penalty considerations).
Page 95
H2M Proposal #262054 October 13, 2026 Page 4 of 8 Equipment replacement of the rooftop units cannot be achieved with ‘in kind’ selections. Changes to the energy code will require replacement units to be provided with energy recovery. This results in a larger equipment footprint and different duct connections, curbs and dunnage (as applicable) will require replacement, evaluation, and below-roof duct mains will require partial demolition and rework to mate with the new equipment. While more efficient overall, new equipment using R454 or R32 refrigerant operates at higher pressure and frequently requires larger circuit ampacity. This will require review of existing electrical panels, breakers, feeders, and disconnects to confirm if they can be reused, or require replacement. From an engineering perspective, our understanding is that an assessment of existing infrastructure will be required to determine available mechanical, electrical, plumbing, and fire alarm capacities. The evaluation, equipment selection, and design will include detailed space ventilation calculations in accordance with applicable ASHRAE62.1 standards as referenced in the Connecticut Mechanical Code. The ventilation review will include terminal device locations to define ventilation efficiency in conjunction with the space and occupancy requirements. The need for MERV-13 filtration will be reviewed with the School. The electrical design will include evaluation of the existing electrical service in support of the HVAC equipment replacements. The existing fire alarm system will accommodate the new fire alarm shutdown and interface modules. Plumbing design is limited to miscellaneous piping as required in support of the HVAC and food warming equipment replacement. Due to the $3M budget constraint, the installation of a building fire protection system is not included at this time. The following is anticipated to be required and provided. The base scope of work included in this scope of work is the Priority 1 (D30) HVAC items (P1) identified in the 2026 Jaed Report (see Appendix A), and as noted otherwise below. Mechanical Design 1. Perform field review of existing conditions. 2. Document existing conditions as required for demolition and new work. 3. Develop demolition and construction documents, including: a. Demolition plans including ductwork and piping (as required to fit up to new equipment). b. Construction plans to include: i. Supply, return, and exhaust ductwork to reconnect to new equipment. ii. New cabinet heaters iii. Air flow and pressurization diagrams iv. Piping diagrams to reconnect to new equipment. c. Control diagrams with control sequences d. Equipment schedules e. Construction details f. Technical specifications on drawings g. Submittal requirements
Page 96
H2M Proposal #262054 October 13, 2026 Page 5 of 8 Electrical/Fire Alarm Design 1. Perform field review of existing conditions for scope of work equipment as required. 2. Design of power to include: a. Demolition of existing circuits back to breaker panels. b. New circuity for new HVAC equipment c. New fire alarm devices associated with equipment replacements. General Design 1. Perform field review of two existing food warming stations as required. 2. Specify and design replacement in kind. PROJECT EXECUTION Phase 1: Pre-Design / Field Survey / Schematic Design H2M will perform the following scope of work to gain a full understanding of the project requirements: ▪ Meet with GPS and stakeholders to confirm project requirements and goals ▪ Field survey and document existing conditions ▪ Review existing available reports, documentation, and drawings ▪ Review power sources to supply new equipment from existing panels Deliverables: ▪ Design Narrative ▪ Schematic design plans/sketches as required for design direction. ▪ Develop Schematic Design Cost Opinion Meetings: ▪ Kick-off meeting ▪ Scope review meeting Phase 2: Design and Construction Documents Develop 60% design documents based on the GPS review and comments issued for Phase 1. Review 60% documents with GPS, then proceed to develop 100% construction documents. Mechanical Documents ▪ Prepare drawings and technical specifications ▪ Demolition plans ▪ Construction plans, including equipment locations and piping plans ▪ Equipment schedules ▪ Construction details Plumbing Documents ▪ Prepare drawings and technical specifications ▪ Piping demolition and construction plans ▪ Construction details
Page 97
H2M Proposal #262054 October 13, 2026 Page 6 of 8 Electrical Documents ▪ Design of power and circuiting for new equipment ▪ Design of fire alarm integration of new equipment ▪ Voltage drop calculations for new equipment wiring as needed ▪ Coordination of wiring and conduit from panel boards to new equipment Deliverables: ▪ 60% Design Development Documents and updated cost opinion ▪ 100% Construction Documents (Signed and Sealed for Permit Submission) Meetings: ▪ It is anticipated that three meetings will be held during this phase. KEY STAFF The following key project team members will be involved in this project with supplemental staff as required. This team is highly experienced in this type of work and has worked together for over 10 years on similar projects. The Mechanical Discipline Lead selected for this team, Paul Foerth, is a Licensed Professional Engineer in multiple states (including Connecticut), a Certified Energy Manager (CEM), and has over 15 years’ experience specializing in HAVC projects. Alexander Hochhausl, with over 30 years of experience will provide technical assistance and quality control as Subject Matter Expert. Shannah Sherman has close to 15 years mechanical engineering expertise in HVAC systems and is a CEM. She will be the lead mechanical engineer and has support staff to execute the mechanical design. Electrical engineering support will be provided by Charlie Starke (Licensed Professional Engineer in Connecticut) who has 15 years’ experience in electrical design projects, along with his support staff. ▪ Client Contact/Principal-in-Charge: Gregory Levasseur, P.E. ▪ Subject Matter Expert: Alexander Hochhausl, P.E. ▪ Mechanical Discipline Lead: Paul Foerth, P.E., CEM ▪ Mechanical Project Engineer: Shannah Sherman, P.E., CEM ▪ Electrical Engineer: Charlie Starke, P.E. We have included their resumes in Attachment C for your reference. PRELIMINARY DELIVERABLES SCHEDULE H2M proposes to provide the services noted above within the working days listed in the Notice to Proceed for each phase. Durations represent active consultant effort and exclude durations associated with Town review and approval cycles, which shall be governed by Town. Phase Working Days Phase 1 – Pre Design / Field Survey / Schematic Design 30 Phase 2 – Design and Construction Documents 60
Page 98
H2M Proposal #262054 October 13, 2026 Page 7 of 8 PROFESSIONAL FEES Please see below for a breakdown of proposed fees per Phase. TASK Description Type Total Cost Phase 1 Pre Design / Field Survey / Schematic Design Lump Sum $29,780 Phase 2 Design and Construction Documents Lump Sum $102,520 Subtotal Engineering Design Phase . . . $132,300 The above fees are based on the replacement of the P1 scope of work items listed in Attachment A. Additional scope of work items can be added with an additional fee based on 4.5% of the estimated construction cost. RATE SCHEDULE The above services are to be provided as Lump Sump. For any additional hourly services, the following rate schedule will apply. Billing Category Hourly Billing Rate PIC/Subject Matter Expert $ 259.00 Project Manager $ 242.00 Project Engineer $ 190.00 Staff Engineer $ 150.00 Administrative Support $ 104.00 PROPOSAL ASSUMPTIONS / CLARIFICATIONS ▪ Existing electrical service has sufficient space and capacity for new loads. Electrical service/distribution upgrade will not be required. ▪ Existing fire alarm control panel has sufficient space and capacity for new devices. Replacement of fire alarm control panel will not be required. ▪ It is anticipated that the existing building roof structure has sufficient capacity to support rooftop equipment. H2M has included structural analysis and design of localized re-enforcement of openings, curb bases, or existing dunnage modifications. Structural analysis or reinforcement of roof framing is excluded from base services. ▪ No changes to existing space partitions, function or occupancy. ▪ LEED, green buildings, or rebate programs/applications are excluded. ▪ Alternate energy (geothermal, solar/PV, wind, etc.) systems are excluded. ▪ No emergency, backup power is required. ▪ Fire protection (sprinkler system) design is not included in the current scope of work. ▪ Documents will be issued for one round of technical and code review comments. SERVICES NOT INCLUDED IN THIS PROPOSAL ▪ Any work not specifically outlined above ▪ Bidding, permitting, construction administration/support services ▪ Destructive or third-party testing, analysis, or laboratory testing/services ▪ Troubleshooting of existing systems outside of the scope of work equipment ▪ Space lighting and controls ▪ Tel/Data/IT cabling and final termination design ▪ Construction cost estimating and value engineering
Page 99
H2M Proposal #262054
October 13, 2026
Page 8 of 8
▪ Air or hydronic testing and balancing
▪ Hazardous materials testing and abatement
▪ Main electrical service upgrade and/or replacement
▪ Fire alarm control panel upgrade and/or replacement
▪ Construction phasing and temporary services
▪ As-built plans
▪ Front end and Division 1 documents, contracts, and contractor insurance requirements
▪ Should meetings beyond those listed above be desired, H2M will provide an additional services
proposal for this work. Additional services will be agreed upon in writing prior to the commencement of
work.
PROPOSAL STIPULATIONS
The offer to perform the above services shall remain open for ninety (90) days from the date of this proposal.
Any extensions of this proposal shall be in writing only.
We appreciate the opportunity to work with Granby Public Schools on this project. In the meantime, should
you have any questions, comments, or require further information regarding this proposal or any aspect of the
project, please feel free to contact me at 860.607.9011 x1034 or via email at glevasseur@h2m.com. Thank
you for your consideration.
Respectfully Submitted,
H2M Architects & Engineers, Inc.
Gregory J. Levasseur, P.E. Alexander Hochhausl, P.E.
Vice President, Windsor Office Director Vice President, Mechanical Discipline Lead
SJB/EVI/JLM/ML/AWK
CC: H2M_File
Attachments:
Attachment A - HVAC Equipment Scope
Attachment B – H2M Standard Terms and Conditions
Attachment C – Team Resumes
J:\PROPS\2026\262054 (T.Granby-Eng Svcs-Athletic Fields) Muni-CT\02 Working Files\MEP Proposal Request\LP262054 Granby MS HVAC-
GJL.docx
Page 100
Code Corrective Action Quantity Priority Correction Notes Estimated Cost D3030-04-04C Condensing Unit (20 Tons) Replacement CU-2 1 P1 CU-2 18 Tons connected to RTU-5 73,598$ D3030-04-05C Condensing Unit (30 Tons) Replacement CU-4 1 P1 CU-4 25 Tons connected to RTU-7 100,311$ D3030-04-10C Condensing Unit (80 Tons) Replacement CU-1 1 P1 CU-1 71 Tons connected to AH-1 196,632$ D3040-02-20C AHU Heating Only (2000 CFM) RTU-1 1 P1 RTU-1 53,922$ D3040-02-22C AHU Heating Only (4000 CFM) RTU-8 1 P1 RTU-8 69,850$ D3040-02-25C AHU Heating Only (7000 CFM) RTU-3 1 P1 RTU-3 134,900$ D3040-02-25C AHU Heating Only (7000 CFM) RTU-2 1 P1 RTU-2 134,900$ D3040-13-08C Exterior Ductwork & Insulation Replacement 100 SF P1 Connected to RTU-7 10,637$ D3050-01-06C Packaged Rooftop Unit RTU-6 1 P1 13 Tons 89,563$ D3050-19-01C Cabinet Heater 10 P1 135,552$ D3060-02-03C Electronic Control (DDC) System 55055 SF P1 Honeywell Niagara 1,155,900$ D3060-03-02C Local Control System to DDC 18352 SF P1 360,172$ P1 Sub Total : 2,515,937$ Code Corrective Action Quantity Priority Correction Notes Estimated Cost D3030-04-04C Condensing Unit (20 Tons) Replacement CU-3 1 P2 CU-3 13 Tons connected to RTU-6 73,598$ D3040-01-03C Supply Fan (2 HP) 1 P2 SF-2 1.5 HP 15,743$ D3040-02-15C Air Handling Unit (75 Tons) AH-1 1 P2 AH-1 71 Tons 348,366$ D3040-02-23C AHU Heating Only (5000 CFM) RTU-4 1 P2 RTU-4 82,413$ D3040-02-24C AHU Heating Only (6000 CFM) AH-2 1 P2 AH-2 95,838$ D3040-02-24C AHU Heating Only (6000 CFM) AH-3 1 P2 AH-3 95,838$ D3040-02-25C AHU Heating Only (7000 CFM) AH-4 1 P2 AH-4 134,900$ D3040-02-25C AHU Heating Only (7000 CFM) AH-5 1 P2 AH-5 134,900$ D3040-04-01C VAV Terminal Unit 8 P2 62,861$ D3040-04-03C VAV Terminal Unit with HW Reheat 20 P2 208,056$ D3040-07-03C Return Air or Inline Fan (3 HP) 4 P2 RAF-2,3,4,5 83,730$ D3040-07-07C Return Air or Inline Fan (15 HP) 1 P2 RAF-1 44,351$ D3040-09-03C Exhaust Fan (1/5 HP) 5 P2 EF-2,3,9,13,15 43,732$ D3040-09-05C Exhaust Fan (1/2 HP) 1 P2 EF-4 9,335$ D3040-09-05C Exhaust Fan (1/2 HP) 2 P2 EF-9 & 12 18,669$ D3040-09-05C Exhaust Fan (1/2 HP) 2 P2 EF-6 & 10 18,669$ D3040-09-07C Exhaust Fan (3/4 HP) 3 P2 EF-5,8,11 33,219$ D3040-09-09C Exhaust Fan (1 HP) 1 P2 EF-1 9,293$ D3040-13-04C Ductwork & Insulation Cleaning Building Wide 73406 SF P2 BLDG SF 273,125$ D3050-01-07C Packaged Rooftop Unit RTU-5 1 P2 18 Tons 130,039$ D3050-20-04C Steam & Hot Water Unit Heater (200 MBH) 6 P2 53,560$ D3050-21-11C Ductless Split System Heat Pump (1.5 Ton) 1 P2 Mitsubishi 7,895$ D3050-21-12C Ductless Split System Heat Pump (3 Ton) 1 P2 Mitsubishi 17,986$ D3050-26-01C Fin-Tube Radiation 922 Units P2 410,567$ D3090-06-01C Industrial Air Cleaner 2 P2 Airomax 12,611$ P2 Sub Total : 2,419,294$ Code Corrective Action Quantity Priority Correction Notes Estimated Cost D3050-01-08C Packaged Rooftop Unit RTU-7 1 P3 25 Tons 233,667$ D3090-01-01C Dust Collection System 1 P3 Donaldson 5,487$ D3040-10-01C Roof Mounted Gravity Vent 5 P3 38,430$ D3040-09-11C Exhaust Fan (3 HP) 1 P4 KEF-1 Cook 12,765$ D3040-01-01C Supply Fan (.5 HP) 1 P4 Cook Supply for KEF-1 10,820$ P3 & 4 Sub Total : 301,169$ Note: Red Font indicates note on report to change to priority shown. Scope of Work Recommendations per Studio Jaed Report Dated 2026 Appendix A
Page 101
(Ver 210520) H2M Standard Terms & Conditions Page 1 of 4 Client Site Services Client’s Rep. H2M’s Rep. Phone/E-Mail Phone/E-Mail 1. Applicability of Terms and Conditions. 1.1. Applicable to Scope of Services. The scope of services, pricing and schedules included with H2M’s proposal are contingent upon the Client accepting the terms and conditions (“Standard T&C”) herein. Any changes hereto which affect H2M’s rights, obligations, or risk exposure shall entitle H2M to make appropriate adjustments to its pricing and proposal. 1.2. Applicable to Preliminary Services. These Standard T&C shal l also apply to any services H2M performs prior to the Parties executing a written Contract. In such circumstances, Client’s direction to H2M to render services shall constitute acceptance of these Standard T&C. 2. Authority of Signers and Parties. 2.1. Authority to Contract . The individuals signing the Contract each warrant that s/he is empowered to sign on behalf of and bind the indicated Party to these Standard T&C and all other components of the Contract. 2.2. Authority for Project. Client warrants that it has any authority and permission required from Owner to engage H2M in the Services concerning the Site, and to grant H2M physical access to the Site as needed to perform the Services. 3. Contractual Obligations 3.1. Designated Representative. Each Party shall designate a “Representative” in writing above. Each Representative shall have the authority to transmit and receive instructions and other information, and to render interpretations and decisions concerning the Project and Contract on behalf of the Party s/he represents. Each Party is entitled to rely on communications from the other Party’s Representative as authoritative. Each Representative shall issue decisions, interpretations and communications promptly as to avoid unreasonable delays in delivery of the Services. 3.2. Commencement. H2M is not obligated to commence or continue rendering any Services until both Parties have signed the Contract and Client has paid any required Fee advance specified in the proposal. 3.3. Performance Standards. Each Party shall exercise its rights and perform its obligations in a reasonable and non- negligent manner. H2M shall perform its Services within the Standard of Professional Care. Client shall pay compensation for all Services so rendered. H2M makes nor implies any other warranties or guarantees, herein or otherwise, concerning the Services or the outcome of the Project. 3.4. “Standard of Professional Care” means the standard of care and skill recognized by law to apply to licensed professionals practicing the same profession, under the same circumstances, at the same time and location, as the Services rendered by H2M. Nothing in any part of the Contract is intended, nor shall anything be so interpreted as, to elevate the Standard of Professional Care beyond the definition included here. 3.5. Document Ownership. All information (including but not limited to drawings and specifications) developed by H2M are instruments of service only, and not products produced for sale nor works made for hire. H2M reserves all of its copyright, ownership and other rights with respect to such information. Client shall not modify and shall not apply such information outside of the Project or for any purposes other than that for which it was created. Client shall defend and indemnify H2M against any claims, liabilities and costs associated with such unauthorized treatment of the information. Client may reuse the information for authorized purposes only with advance written consent from H2M that details the scope of, additional compensation for, and appropriate protections associated with such reuse. 3.6. Site Access. Client guarantees full and free H2M access to the Site and shall cooperate with H2M in gaining access to any other real property required for the performance of the Services. 3.7. Preliminary Information. Client shall provide to H2M in writing any pertinent information it possesses that might affect the Project requirements (including but not limited to design objectives and constraints, budgetary limitations, surveys, related reports and studies, environmental, geotechnical, and soil data, preliminary designs, etc.). H2M is entitled to rely on the accuracy of all information that the Client provides. H2M shall not be required to verify any such information, unless such task and information is specifically listed in the Scope of Services. 3.8. Hazardous Materials. Client warrants that to the best of its knowledge there are no constituents of concern on or adjacent to the Site, other than those previously disclosed in writing to H2M. Nothing in this Contract shall be interpreted to give H2M responsibility for the current existence or introduction (including by, but not limited to, dispersal, discharge, escape, release, or saturation, either sudden or gradual) to the Site of any hazardous materials (including but not limited to smoke, vapors, soot, fumes, acids, alkalis, toxic chemicals, liquids, or gases) by anyone other than H2M. Client shall therefore hold H2M harmless as to all such matters. 3.9. Claims Assistance. H2M shall be entitled to hourly compensation as Additional Services for all time spent analyzing, preparing, testifying, and otherwise assisting Client to pursue or defend claims and disputes to which H2M is not a named plaintiff or defendant. 4. Payment Terms 4.1. Fees. The “Fees” are the component of compensation to be paid by Client to H2M for its effort in providing the Services. The Fees pertaining to this Contract, are set forth in the proposal, and any Amendments to the Contract. Additional services, when required will be invoiced at hourly rates of compensation or a negotiated lump sum, plus reimbursable expenses. 4.2. Reimbursable Expenses. The “ Expenses” are the costs H2M incurs in rendering the Services which are to be reimbursed by Cli ent. Expenses authorized by this Contract include but are not limited to: 4.2.1. Transportation, lodging and subsistence incidental to the project, courier charges, reproduction, renderings or models, specialty field equipment and fees paid for securing approval of authorities having jurisdiction over the project; APPENDIX B (4 PAGES)
Page 102
(Ver 210520) Page 2 of 4 4.2.2. Sub-contractor expenses, plus a ten (10) percent mark -up to compensate H2M for its handling and administration costs; 4.2.2. Any other expenses set forth in the proposal. 4.3. Taxes. The amount of any sales, excise, value added, gross receipts or any other type of tax that may be imposed by any taxing entity or authority shall be paid by Client in addition to the Fees and Expenses. 4.4. Invoices. H2M shall provide invoices to Client for al l Fees and Expenses due under this Contract. Payment of invoices shall not be contingent upon the action of any third party. Client shall pay each invoice within thirty (30) days of the invoice date. 4.5. Interest on Past Due Amounts. Invoices, Fees, and Expenses will be past due as of the thirty first (31st) day following the date of the invoice. All past due amounts shall accrue interest at the maximum rate permissible by law until the date upon which they are finally paid. 4.6. Required Fee Advance. As security against the risks and costs of mobilizing to commence performing the Services, H2M may require a Fee advance. Any such Fee advance will be specified in the proposal . The fee advance will be deposited upon receipt and booked as an outstanding credit against accounts receivable from the Client. The Fee advance will be applied to Client’s final invoice. 5. Project Risk Management 5.1. Mutual Waiver. Except as otherwise specifically provided for in these T&C , neither Party shall hold the other responsible for any consequential damages, nor any damages other than direct damages. 5.2. Mutual Indemnification. Subject to the applicable concepts of contributory and comparative fault, and in addition to any other compensation provided by law or this C ontract, each Party shall indemnify the other Party’s “Indemnitees” (the Party, its owners, directors, officers, employees and volunteers) against third- party claims and liabilities (including the reasonable costs of defending such claims) for death, bodily-injury, and property damage, but only to the extent such have been caused by the negligence of the indemnifying Party (including its owners, directors, officers, employees, volunteers, and those contractors for whom it is legally responsible), and not to the extent such are caused by any other means (including but not limited to the negligence of the Indemnitees themselves). 5.3. Insurance Coverage. H2M shall maintain the following insurance coverage while performing the Services. Upon request, H2M will provide a Certificate of Insurance to Client as Certificate Holder reflecting such coverage. 5.3.1. Workers’ Compensation and Disability coverages with limits at least in the amount required by law. 5.3.2. Employers’ Liability coverage with policy limits not less than one million dollars ($ 1,000,000) each accident, one million dollars ($1,000,000) each employee, and one million dollars ($1,000,000) policy limit. 5.3.3. Automobile Liability coverage for H2M owned and non- owned vehicles utilized in performance of its Contract obligations, meeting statutorily required coverage, and with policy limits not less than one million dollars ($1,000,000) each accident for bodily injury, death of any person and property damage. 5.3.4. Commercial General Liability coverage with policy limits of not less than one million dollars ($ 1,000,000) each occurrence and two million dollars ($2,000,000) in the aggregate for bodily injury and property damage. 5.3.5. Professional Liability coverage for negligent acts, errors and omissions in the performance of professional services with policy limits of not less than one million dollars ($1,000,000) per claim and one million dollars ($1,000,000) in the aggregate. 5.3.6. Pollution Liability coverage with policy limits of not less than one million dollars ($ 1,000,000) per claim and one million dollars ($1,000,000) in the aggregate, whenever such would apply to H2M’s Services. 5.4. Additional Insured Coverage. Client shall be covered as Additional Insured under the terms of H2M’s Commercial General Liability policy. 5.5. LIMITATION OF H2M LIABILITY. H2M’s AGGREGATE LIABILITY FOR ALL CLAIMS ARISING FROM AND/OR RELATED TO THIS CONTRACT, THE SERVICES, THE PROJECT, AND/OR THE SITE, SHALL BE LIMITED TO THE GREATER OF THE AMOUNT OF FEES PAID UNDER THIS CONTRACT OR FIFTY THOUSAND DOLLARS ($50,000.00). 6. Dispute Resolution 6.1. Notice of Claim or Dispute. An aggrieved Party shall give the other Party written notice of any claim or dispute arising from the Project, the Services, or this Contract. The Parties shall endeavor in good faith to resolve such matters fairly and amicably through negotiation. If the matter has not been resolved by negotiation within thirty (30) days of receipt of such written notice, either Party may demand mediation of the matter. 6.2. Mediation. Unless the Parties agree to other rules, any mediation shall be conducted under the auspices of the American Arbitration Association (AAA), pursuant to its Construction industry mediation rules. Each Party shall bear its own mediation costs (except as specified in the rules, and except that the AAA fees, mediator fees, and if agreed the venue fees, shall all be borne equally by the Parties). Except as otherwise specifically permitted herein, a prospective plaintiff Party may not file an action before giving the other Party ten (10) day’s written notice and opportunity to demand mediation. Such notice, and a good faith effort in any mediation timely demanded, shall be a condition precedent to the prospective plaintiff Party commencing litigation. 6.3. Waiver of Jury Trial. The Parties hereby waive any and all rights to a trial by jury in any litigation pertaining to the Services or this Contract. 6.4. Certificate of Merit. As a condition precedent to filing any pleading containing a cause of action based on professional liability, Client must include a sworn Certificate of Merit from a similarly licensed professional explaining the applicable Standard of Professional Care and alleging the specific acts or omissions by which H2M violated the Standard. 6.5. Suspension of Services. Upon ten (10) days written notice, H2M may suspend delivery of the Services until any past due invoice is paid. Client shall hold H2M harmless for the impact of any such suspension. 6.6. Collection Efforts. Upon ten (10) days additional written notice, H2M may refer any past due invoice to inside or outside counsel for collection. H2M is entitled to reimbursement by Client for the time and cost involved in such collection efforts. 6.7. Liquidated Damages. Since the actual costs that H2M will suffer in such collection efforts is difficult to ascertain, the Parties agree that Client will pay H2M the following amounts as liquidated damages for such costs: two hundred dollars ($200.00) when H2M refers a past due invoice for collection; plus either an additional six hundred dollars ($600.00) when a collection action is filed in small claims court, or an additional two thousand dollars ($2,000.00) when a collection action is filed in any other court. These liquidated damages are H2M’s only remedy to recover such costs of collection. 6.8. Payment Disputes. H2M’s collection efforts are not subject to the mediation requirements set forth above. In disputing any invoice, Client shall adhere to the Mediation and Certificate of Merit requirements set forth above.
Page 103
(Ver 210520) Page 3 of 4 6.9. Project Suspension. Upon seven (7) days’ written notice to H2M, Client may suspend the Project for any reason. If the aggregate number of Project suspension days exceeds sixty (60) days, such will constitute cause for termination. 6.10. Termination. Either Party may terminate this Contract for cause if the other Party substantially fails to perform its obligations or otherwise breaches a material term of this Contract. Such termination will only be effective upon seven (7) days’ written notice and opportunity to cure. This Contract may also be terminated by the Client without cause by providing H2M thirty (30) days written notice. If this Contract is terminated H2M shall be entitled to invoice and to be paid for any Services performed prior to the termination. Notwi thstanding any other provisions of the Contract, if H2M terminates this Contract for cause, in addition to any direct damages for breach of contract, it shall be entitled to recover from Client any expenses demonstrably attributable to termination 7. Definitions (additional definitions indicated by quotes in context). 7.1. “Client” means the person/entity for which H2M is obliged to perform the Scope of Services set forth in the Contract (and/or for which H2M performs services described in 1.2. above). Client and H2M are each individually a “ Party” and are collectively the “ Parties” to the Contract. 7.2. “H2M” means the entity appropriately authorized to offer and render the services contained in the proposal and Contract. Specifically H2M Associates, Inc.; H2M Architects & Engineers, Inc.; or H2M Architects, Engineers, Land Surveying and Landscape Architecture, D.P.C. (d/b/a H2M architects + engineers), as appropriate. No proposal is intended as, and none should be interpreted to be, an offer to provide any services in any location where H2M is not authorized to provide such services. 7.3. “Contract” means the written agreement by which H2M is obligated to perform services for the Client, and includes all components specified in the proposal or otherwise incorporated by written reference. 7.4. “Services” means those services H2M is required by the Contract to perform for the Client, as such are reflected in the agreed “Scope of Services” set forth in the proposal and any amendments thereto agreed by the Parties in writing. 7.5. “Project” means the Client’s overall endeavor at the Site, of which H2M’s Scope of Services is a component. 7.6. “Site” means the real property to which the Project pertains, or where components of the Project are being built or disposed. 7.7. “Owner” means the owner(s) of the Site, whether or not such owner is also the Client. 7.8. “Contractor” means any person or entity (including the employees and subcontractors at every level thereof), other than H2M (including H2M’s own employees and subconsultants), that provides materials and/or services for the Client relating to the Project or the Site. Any licensed professional or firm engaged by a Contractor, or by the Client directly (rather than as a subconsultant to H2M) is also a Contractor. 7.9. “Contractor Activity” means every activity performed by a Contractor that is in any way related to furthering the Project or otherwise performed on the Site, regardless of whether such activity is required by contract. Contractor Activity also includes a Contractor’s failure to perform any activity required by law or contract. 8. General Terms 8.1. Headings. Paragraph numbering and headings are for navigational purposes only and shall be given no weight in construing the terms and conditions of this Contract. 8.2. Integration. This Contract, the components of which are specified in the proposal, represents the entire and integrated agreement between Client and H2M. This Contract supersedes all prior representations, negotiations, and agreements, written or otherwise. In the event of any conflict between other Contract terms and these T&C , these T&C shall govern, unless the conflicting term specifically states that it is superior in precedence to this these T&C. 8.3. Severability. If any term or condition in this Contract is found to be unenforceable, the enforceable remainder shall be valid and binding upon the Parties. No waiver of any term or condition shall be construed to be a waiver of any subsequent breach. 8.4. Amendment. Any modification or addition to this Contract shall not be enforceable unless agreed upon in writing. 8.5. Delegation. Any delegation of a Party’s right or obligation under this Contract shall be void unless made pursuant to advance written consent from the other Party. 8.6. Force Majeure. Neither Party shall be responsible for damages or delay caused by extraordinary events that are beyond its reasonable control and due care (as nonexclusive examples, war, terrorism, and natural disasters). 8.7. Choice of Law. The Standard of Professional Care applicable to the Services shall be supplied by the law of the state in which the Site is located. The remainder of this Contract shall be governed by the laws of the State of New York when the Site is located in New York, or by the laws of the State of New Jersey for all other Projects. 8.8. Choice of Forum. The Parties agree that the courts of New York State shall have jurisdiction over the Parties and their disputes arising under or related to this Contract as it pertains to any Site in New York State, and consent to the jurisdiction of said courts. Any New York litigation arising under or related to this Contract shall be filed in a court located in Nassau County, New York, or any New York county in which H2M maintains a permanent office at the time such litigation is commenced. The Parties agree that the courts of New Jersey shall have jurisdiction over the Parties and their disputes arising under or related to this Contract as it pertains to any Site outside New York State, and consent to the jurisdiction of said courts. Any non -New York litigation arising under or related to this Contract shall be filed in a court located in Morris County, New Jersey, or any New Jersey county in which H2M maintains a permanent office at the time such litigation is commenced. 9. Construction-Related Terms 9.1. Construction and Site Safety. Client represents that it is the Owner of the Site, or has the Owner’s permission to control the Site. Nothing in this Contract or otherwise shall be interpreted to give H2M responsibility for safety upon the Site, nor for any means, methods, techniques, sequences, or procedures used, or failed to be used, in any Contractor Activity or other activity on the Project or Site (including, but not limited to shoring, bracing, scaffolding, underpinning, excavating, t emporary retaining, erecting, staging, etc.). H2M employees shall comply with Site safety programs, when applicable. 9.2. Contractor’s Insurance. Client is responsible for determining and demanding Contractor insurance that sufficiently protects Client. Additionally, to protect H2M, the Client shall cause any Contractor to procure, prior to commencing any Contractor Activity, at least the following insurance coverage, which must remain in force during all such activity and its associated guarantee: 9.2.1. Workers’ Compensation and Disability coverages with limits at least in the amount required by law. 9.2.2. Employers’ Liability coverage with policy limits not less than one million dollars ($ 1,000,000) each accident, one million dollars ($1,000,000) each employee, and one million dollars ($1,000,000) policy limit.
Page 104
(Ver 210520) Page 4 of 4 9.2.3. Automobile Liability coverage for Contractor owned and non - owned vehicles utilized in performance of the Contract Activity, meeting statutorily required coverage, and with policy limits not less than one million dollars ($1,000,000) each accident for bodily injury, death of any person and property damage. 9.2.4. Commercial General Liability coverage with policy limits of not less than one million dollars ($1 ,000,000) each occurrence and three million dollars ($3,000,000) in the aggregate for bodily injury and property damage, and which includes the following features: 9.2.4.a. Explosion, Collapse and Underground coverage, whenever such would apply to the Contractor Activity; 9.2.4.b. Pollution Liability coverage, whenever such would apply to the Contractor Activity; 9.2.4.c. Contractual Liability coverage sufficient to insure the indemnity required by 7.4. below; and 9.2.4.d. Additional Insured coverage for H2M, by endorsement using ISO Form CG 20 32 04 13, specifying each of the entities listed in 3.2. above, as well as all of their directors, officers and employees. 9.2.5. Professional Liability coverage, whenever such would apply to the Contractor Activity, for negligent acts, errors and omissions in the performance of professional services with policy limits of not less than one million dollars ($1 ,000,000) per claim and one million dollars ($1,000,000) in the aggregate. 9.3. Contractor’s Indemnity. Client shall require each of its Contractors to agree, via a written contract executed prior to commencing any Contractor Activity, to defend and indemnify the Client and the “H2M Indemnitees” (including each of the entities listed in 3.2. above, as well as all of their directors, officers, employees, consultants and agents) against all claims, liabilities and costs arising, or alleged to arise, from the negligence of the Contractor (including its owners, directors, employees, contractors and any others for whom the Contractor is legally responsible) in its Contractor Activity or any of its other activities concerning the Project or Site. This obligation does not apply to such claims, liabilities and costs that are caused by the sole negligence of the H2M Indemnitee itself. 9.4. Cost Opinions. Any opinion of cost that H2M prepares is merely an estimate supplied for the Client’s general guidance. H2M has no control over variations in market conditions, suppliers’ or contractors’ bidding strategies, nor the impacts that these and other variables have on the actual cost of labor and materials. Therefore, H2M cannot guarantee the level of accuracy of any such estimates. If greater accuracy is required, the Client shall separately engage an independent cost estimator. 9.5. Bid Process. If H2M is to participate in Contractor bid process, Client shall provide H2M with standard bid documents required and advertise for proposals from bidders, open the proposals at the appointed time and place and pay costs incident thereto. The Client shall hold all required special meetings, serve all required public and private notices, receive and act upon all protests and fulfill all requirements necessary in the development of the contracts and pay all costs including application and permit fees incident thereto. 9.6. Construction Observation Services. If the Services include H2M providing construction observation services, H2M shall provide such services over a period defined in, and on a frequency defined in the proposal. Regardless of the required frequency, H2M shall observe the Contractors’ work only for general conformance with the plans and specifications. Such Services do not include any obligation to review any Contractors' construction means, methods, techniques, sequences or procedures, or any safety precautions and programs in connection with the Project or Site. H2M is not responsible for any Contractors' failure to carry out its work in accordance with the construction contracts. If the construction schedule is extended for any reason (except due to H2M’s own negligence) H2M shall be entitled to payment for its extended effort as additional services pursuant to 4.1. above, regardless of whether Client seeks reimbursement from the responsible party. Accepted and Agreed Client H2M Signature Signature By: Name By: Name Title Title Date Date
Page 105
Education B.S., Civil Engineering; University of Hartford Certificate in Construction Management Licenses/ Certifications Professional Engineer: CT, NY, RI H2M Project Management Training Program Memberships American Society of Civil Engineers (ASCE) Water Environment Federation (WEF) Awards Board of Director Service Award, NYWEA Ones To Watch, NYWEA Mr. Levasseur brings over 20 years of engineering experience to his role as H2M’s Windsor, CT, Office Director. A licensed Professional Engineer and seasoned project leader, he is widely recognized for his technical expertise in wastewater infrastructure, including the planning, design, and contract administration of treatment plants, gravity sewers, low-pressure systems, force mains, and pumping stations. However, his value to clients and project teams extends far beyond his wastewater credentials. As Office Director, Mr. Levasseur plays a pivotal role in the strategic growth and operational leadership of H2M’s Windsor office. He serves as a key client liaison and trusted advisor across a wide range of municipal and infrastructure projects throughout Connecticut. His deep familiarity with the state’s regulatory landscape, municipal priorities, and funding mechanisms allows him to anticipate client needs and guide teams toward practical, cost-effective solutions. Mr. Levasseur is frequently called upon to serve as Principal-in-Charge, Technical Advisor, or QA/QC Lead on multidisciplinary projects—ranging from water main extensions and environmental assessments to zoning regulation updates, brownfield redevelopment, and more. His ability to bridge technical rigor with client-focused delivery makes him an asset on both proposal teams and project execution. His leadership is grounded in responsiveness, accountability, and a commitment to quality. Whether supporting proposal strategy, mentoring junior staff, or representing H2M in client meetings, he brings a steady hand and a collaborative mindset that aligns with the firm’s mission, vision, and values. Gregory J. Levasseur P.E. Vice President, Windsor Office Director
Page 106
Education B.S., Engineering Science; Stony Brook University Licenses/ Certifications Professional Engineer: NY Memberships American Society of Heating, Refrigerating and Air-Conditioning Engineers American Society of Mechanical Engineers National Society of Professional Engineers Mr. Hochhausl has more than 30 years of experience completing various engineering system design projects for clients in the medical, education, and pharmaceutical industries. This experience includes automated industrial, pharmaceutical, packing equipment, distribution, utility generation, and HVAC systems, from their conception to installation at client facilities. Selected project experience • SUNY Stony Brook; Stony Brook and Southampton, NY: Project Manager for various HVAC upgrade projects including: Tabler Performing Arts HVAC replacements; Hospital BST and HSC buildings multiple research lab renovations; research cage wash facility upgrade; sensitive animals care upgrade; and marine research chiller replacement at Southhampton Campus. • SUNY Farmingdale Gleeson Hall HVAC Replacement; Farmingdale, NY: Senior Discipline Engineer tasked with replacing the HVAC systems in Gleeson Hall (120,000 square feet) at SUNY Farmingdale while keeping the building fully operational. This includes installing a hot glycol systems, chillers, air handling units with energy recovery ventilation, new ductwork, new distribution piping, variable air volume system, and updated controls. Assessed energy usage to ensure building met NYStretch Energy Code and energy use intensity goals. (Ongoing) • Various Public School Districts K-12 Buildings; Long Island, NY: Senior Discipline Engineer for HVAC upgrades, decarbonization, and electrification including thousands of tons of heat pump equipment, VRF, DOAS, and energy recovery systems. • Various School Districts School Reopening Ventilation Systems Reviews; Various Locations, NY: Senior Discipline Engineer responsible for the installation of ventilation dehumidification improvements for various school districts in Long Island and upstate New York. Ventilation improvements included measures to meet COVID-19 filtration requirements as well as energy-efficient measures for the future decarbonization of these facilities via a transition to electric heating and cooling and/or use of alternative fuels. • Massapequa School District H&V Furnace Conversion; Massapequa, NY: Senior Project Engineer responsible for converting an indirect 75,000 cubic-feet-per-minute heating system with dual condensing boilers, hot water coils, new gas services, and improved controls. Also replaced a single fan with wall fan technology and associated filtration settings and controls. Achieved N+1 redundancy for building heating plant and distribution. • Rhode Island College Campus Steam Distribution Study; Providence, RI: Project Engineer responsible for performing a site survey for over 5,000 linear feet of direct buried steam and condensate piping on a 150-acre campus using aerial thermal imaging to map surface temperatures. Following the site survey, performed a physical survey of areas involving temperature mapping of the ground and gradients in surface area. Using heat loss calculations, a formula was developed to correlate the rate of heat loss to level of deterioration of the connective piping and insulation, from which the remaining years of the system’s usable life was approximated. Developed a construction cost estimate for replacement piping which served as the basis of an ESCO to fund the project. • Forest Labs; Hauppauge, NY: Project Engineer tasked with the analyzing and producing the design documents for the replacement of a 1,000-ton air-cooled chiller plant with a 800-ton water-cooled chiller plant. This required the analysis of existing building conditions and requirements, system modifications to change Delta T operation, glycol percentage, and airflow reductions. Conducted economic and BIN analyses to determine if maximum efficiency can be achieved via utilizing a water-cooled chiller plant; resulted in the installation of two 400-ton water-cooled chillers, two cooling towers, and a dry cooler to meet process loads and specifications. • Brooklyn Navy Yard Development Corporation Steamline Relocation; Brooklyn, NY: Senior Project Engineer that led the replacement and relocation of an above-ground high-pressure steamline underground. This involved comprehensive investigation and coordination to avoid interference with underground utilities; constructing new steam pressure-relieve vents MERs; and installing new piping for improved steam distribution and condensate return, requiring minimal building shutdown. Alexander Hochhausl P.E. Vice President, Assistant Department Manager - Mechanical Engineering APPENDIX C (4 PAGES)
Page 107
• Seminole Tribe of Florida Ball Field Renovations; Immokalee, FL: Working with the Seminole Tribe of Florida in Immokalee to design the renovation of athletic facilities as a subconsultant to LTG Sports Turf One. The project includes renovation of existing facilities: ball field, concession/restroom building, dugouts, press box, and bleachers, as well as the addition of a new north ball field. • Estee Lauder Multiple Laboratories; Long Island, NY: Managed the design and construction of multiple laboratories, including the bioferm lab, makeup lab, CDLM-G lab, and the Creams 5 lab, the largest creams laboratory on the east coast. Design included HVAC and mechanical process design involving steam, chilled water, nitrogen, compressed air, and domestic water systems. Responsibilities also included the management of the architectural, structural, and MEP portions of the design. • Mercedes Benz and Competition BMW Showrooms; Smithtown and Huntington, NY: HVAC design for showroom additions. The additions included a complete re-design of their HVAC system utilizing Revit, including the installation of vehicle exhaust systems. • DASNY Samaritan Village at the Highbridge Residential Treatment Center; Bronx, NY: HVAC design in Revit for a five-story treatment center. This included an outdoor air cooled chiller with chilled water, and an indoor boiler system, both with indoor air handling units. • Greybarn Apartment Development; Amityville, NY: HVAC design for seven apartment buildings in Amityville, which included a central laundry and bathroom exhaust system, packaged terminal air conditioners, and VRF systems for the public spaces. • Multiple Fire Districts: Roslyn NY, Massapequa NY, Sanford Heights NY, and Borough of Metuchen NJ: HVAC design for multiple fire houses, including packaged units, VRF, in-floor radiant, snowmelt systems, and vehicle exhaust systems. • Northport American Legion; Northport, NY: HVAC design for additions and alterations to the American Legion building. This included the design of split system air handlers with gas furnaces, as well as elevator exhaust. • Engel Burman Group New Bristal Assisted Living Buildings; Long Island, NY: HVAC design for new assisted living buildings. This included VRF systems, rooftop energy recovery units, dedicated outdoor air units, kitchen exhaust design, and laundry exhaust design. • Village of Ocean Beach Village Office Building Renovation; Ocean Beach, NY: HVAC design of renovated Office Building. This included a VRF system, which would help keep the HVAC system as energy efficient as possible. • Gabrielli Building Canopy; Long Island, NY: This project required the installation of a diesel fuel tank, a dispensing station, and a control system for the dispensing of fuel. • Court Plaza Domestic Water Heater Upgrades; Long Island, NY: Plumbing design for apartment building. This included the selection of new domestic water heaters, as well as selecting a new expansion tank, and re-designing the piping layout for the hot water system in the boiler room. • Ørsted Operations and Maintenance Facility; Setauket, NY: Design of a LEED Certified building utilizing VRF to promote energy efficiency, with a 72 ton data center utilizing Dunham-Bush CRAC units. • Steel Equities Stony Brook Medicine; Lake Grove, NY: Design for the renovation of a former retail store into a medical center following ASHRAE 170 at the Smithhaven Mall. The design included packaged rooftop units with special care on pressurizing code required rooms for medical facilities. Education B.S., Mechanical Engineering; Messiah College Licenses/ Certifications Professional Engineer: NY, NJ, CT, FL Certified Energy Manager (CEM) TRANE Air Conditioning Clinic OSHA 10-Hour Construction Safety & Health Project Management Training Program, H2M H2M Mentoring Program Graduate, Mentee Memberships American Society of Heating, Refrigerating and Air Conditioning Engineers Mr. Foerth is a mechanical engineer with 15 years of experience. His responsibilities include the preparation of heating and cooling load calculations, equipment selection, HVAC system design in AutoCAD and Revit, and shop drawing review. He also assists H2M’s Energy Market with energy modeling and auditing services, as well as assembles real estate proposals and fees for HVAC designs. He is an H2M certified project manager and serves as the manager and client contact for H2M’s Estee Lauder account. Selected project experience Senior Associate, Discipline Engineer - Mechanical Engineering Paul D. Foerth P.E., CEM
Page 108
Education B.S., Mechanical Engineering; Binghamton University Licenses/ Certifications Professional Engineer: NY, NJ Certified Energy Manager (CEM) Memberships American Society of Heating, Refrigerating, and Air conditioning Engineer (ASHRAE) Association of Energy Engineers (AEE) Shannah E. Sherman-Corrado P.E., CEM Senior Project Engineer - Mechanical Engineering Mrs. Sherman-Corrado is a mechanical engineer with 13 years of experience in the HVAC industry focused on residential, commercial, and education projects. Her expertise in HVAC system design includes equipment selection, heating and cooling load calculations, CHP/cogeneration design, fuel conversion, boiler and chiller plant design, and energy audits (Level I, II, LL87). Mrs. Sherman-Corrado often manages multi-disciplinary coordination to deliver projects on time and on budget. Selected project experience • Syosset Central School District Ventilation Upgrades at Various Schools; Syosset, NY: Acted as HVAC system design engineer and project manager for the design and implementation of new ventilation systems at various school buildings through the use of dedicated outdoor air units, energy recovery ventilators, and unit ventilators. • Confidential Client Warehouse and Command Center; Setauket, NY: Designed replacement building mechanical systems to accommodate the owner’s requirements and meet LEED certification. Systems supported the following areas: data center, offices, warehouse, cafeteria, and chemical storage. Designed variable refrigerant flow (VRF) systems, dedicated outdoor air units, energy recovery ventilators, computer room air conditioning (CRAC) units, and new building management system (BMS). • Mineola Union Free School District Mineola Middle School Gymnasium Addition; Mineola, NY: Designed mechanical systems for a new gymnasium addition and interior alterations, including the relocation of the cafeteria, kitchen, locker rooms, and fitness center. Provided HVAC load calculations to support the needs of the new spaces. Designed VRF systems, dedicated outdoor air units, energy recovery ventilators, kitchen exhaust/makeup air, and DX air handling units. • Mineola Union Free School District Mineola Middle School Interior Alterations; Mineola, NY: Designed mechanical systems for the conversion of cafeteria and kitchen spaces to art and science classrooms and renovation of the music wing. Provided HVAC load calculations for the altered spaces and designed ductless split systems, VRF systems, unit ventilators, energy recovery ventilators, and kiln ventilation. • Dormitory Authority of the State of New York (DASNY) City University of New York (CUNY) LaGuardia Community College STEM Lab Renovations; Queens, NY: Designed mechanical systems for new chemistry and biology labs, research space, occupational therapy, and physical therapy labs. Scope focused on adaptation of existing mechanical systems and implementation of additional equipment to meet the HVAC requirements of the new spaces. Performed HVAC load calculations and designed exhaust and makeup air systems for new laboratory equipment. • Longwood Central School District Air Conditioning at Various Schools; Middle Island, NY: Led the engineering design and implementation of the full replacement of HVAC at 10 schools in the District. Provided load calculations and system recommendations. Provided new gas fired rooftop units and rooftop units for air conditioning and ventilation with indoor hot water coils to utilize existing CHP system thermal heat. Design and implementation of a new building addition to the High School for a Career and Technical Education Center (CTE). New specialty spaces included cosmetology, engineering work shops, art rooms, and culinary arts. • Steel Equities Stony Brook Clinical at Smith Haven Mall; Lake Grove, NY: Designed new HVAC systems in accordance with FGI and ASHRAE 170 standards for medical facilities as part of renovation of the Sear’s building for new medicine outpatient treatment facilities (including Article 28 spaces and procedure rooms). Provided design load calculations, analyses of existing mechanical equipment, and mechanical system design. Provided new rooftop units including energy recovery ventilation, ductwork distribution systems, and ductless split units. • Elan Strategy Realty Office Renovations; Levittown, NY: Managed renovation of an office building and multidisciplinary coordination to deliver project on time. Designed HVAC systems including load calculations, equipment selection, and document production. Next
Page 109
• Various Water Districts Emerging Contaminant Removal; Long Island, NY: Senior Project Engineer responsible for preparing electrical plans and specifications for new 1,4 dioxane and/or PFOS/PFOA removal plants, including but not limited to new motor control center, PLC controls, and SCADA integration. Participated in emergency innovative design effort for many water districts required to meet certain maximum contamination level (MCL) in short time frame to continue to deliver potable water to Long Island customers. • Westchester County Port Chester WRRF HVAC and Electrical Upgrades; Port Chester, NY: Senior Project Engineer responsible for preparing electrical plans and specifications for the design and modification of the existing electrical power distribution systems throughout the entire 5 MGD water resource recovery facility (WRRF). The WRRF consists of 10 buildings containing various process- related equipment powered by double-ended MCCs in a main-tie-main configuration. The project also includes replacement of the service entrance main switchgear, two distribution switchgear units, all MCCs, all step-down transformers, and all distribution panel boards. • Nassau County Department of Public Works (DPW) South Shore Water Reclamation Facility Phase E4 Electrical Utility Connections; East Rockaway, NY: As Senior Project Engineer, prepared electrical plans and specifications for the design and modification of the replacement of the existing medium voltage switchgear and associated low voltage distribution switchgear supplying power for a critical process within the South Shore Water Reclamation Facility, formerly known as the Bay Park Sewage Treatment Plant. In addition, the scope included the replacement of an existing Motor Control Center (MCC) in a main-tie-main configuration within a critical process building. All new equipment was elevated above the 500-year flood plan. • Brooklyn Navy Yard Development Corporation (BNYDC) FEMA Boilers, Substations, and Isolated Electrical Work Contract; Brooklyn, NY: Electrical and Substation Designer for various FEMA-funded restoration and resiliency projects to repair Sandy damaged infrastructure and improve the resiliency of the existing infrastructure at Brooklyn Navy Yard. During Hurricane Sandy, floodwater levels averaged four feet throughout the Yard and saltwater caused extensive damage to electrical and mechanical systems. • Farmingdale Union Free School District Howitt Middle School Aquatic Center and Athletic Field Complex; Farmingdale, NY: Senior Project Engineer responsible for electrical design for the District’s new Aquatic Center. Prepared electrical plans and specifications for the design of electrical power systems, pool equipment power and control, HVAC equipment power and control, lighting, fire alarm system, information technology network and system, audiovisual system, public address system, CCTV, and security system for the Aquatic Center. The center consists of a competition pool, public pool, competition locker rooms, public locker rooms, pool equipment room, and miscellaneous office and storage areas. Also designed site lighting for the construction of a new synthetic turf multi-purpose field striped for various sports teams. • Exchange Ambulance of the Islips New Headquarters; East Islip, NY: Senior Project Engineer for the electrical systems of a new facility for the Exchange Ambulance of the Islips to improve the responders’ operations and workflow, living environment, and health and safety; enabling smoother operations and an improved work environment for first responders. • Inc. Village of Mineola New Fire Headquarters; Mineola, NY: Senior Project Engineer responsible for electrical engineering design for the Village’s new state-of-the-art fire headquarters, which replaced the original headquarters built in 1913. Responsibilities included power distribution, lighting, emergency generator, and IT/AV/CCTV design. Education B.S., Electrical and Computer Engineering; New York Institute of Technology Licenses/ Certifications Professional Engineer: NY, NJ, CT, FL Dale Carnegie Training Program H2M Project Management Training Program Mr. Starke is an electrical engineer with 15 years of experience providing electrical design for water, wastewater, and industrial projects. As H2M’s Assistant Department Manager of Electrical Engineering, he is responsible for leading a team of staff in the execution of high-quality electrical designs. Mr. Starke’s areas of expertise include power distribution design, new electrical services and service upgrades, motor control centers, programmable logic controls (PLC), emergency generators and systems, interior and exterior lighting, fire alarm systems, CCTV and access control systems, and security alarm systems. Selected project experience Assistant Vice President, Assistant Department Manager - Electrical Engineering Charles J. Starke P.E.
Minutes: archived copy, SHA-256 2230d7bd3705…. Agenda: archived copy, SHA-256 08368c8a6799…. Packet: sanitized copy, SHA-256 eb73f1516ab9….