Public Building Committee, Oct 5, 2026

Simsbury minutes posted

Documents

TypeDocumentPagesOpen
minutes Public Building Committee Regular Meeting Minutes 5 PDF download · town site
agenda Public Building Committee Regular Meeting Agenda 1 PDF download · town site

Summary

No summary yet. Public Building Committee Regular Meeting Agenda has no extractable text (it may be a scan).

Full text of the documents

View the minutes PDF on this page (Public Building Committee Regular Meeting Minutes) Open the PDF
Text of the minutes (Public Building Committee Regular Meeting Minutes, 5 pages)

Page 1 · open in PDF

 
 
 
 
   
   
 
 
 
Page 1 of 5 
 
Public Building Committee 
Regular Meeting 
October 5, 2026 – 7:00 P.M. 
The meeting was held in person in the Board of Education Conference Room  
at Simsbury Town Hall and via Zoom. 
 
SUMMARY OF MEETING WITHOUT QUORUM 
 
CALL TO ORDER & ROLL CALL 
A quorum not being present, the regular meeting of the Public Building Committee could not be 
called to order for the purpose of conducting official business. Below is the summary of the 
meeting. 
 
☒ Mr. Ryan Burns 
☒ Mr. Richard Derr 
☐ Mr. Lucian Dragulski  
☒ Mr. Michael Egan 
☐ Ms. Dagny Griswold 
☒ Mr. David Moore 
☐ Mr. John Salvatore 
☐ Ms. Marcianne Timm
 
GUESTS 
Simsbury Engineering Department: Thomas J. Roy, PE, Director of Public Works, Town 
Engineer; Adam Kessler, Deputy Town Engineer 
Simsbury Public Schools: Neil Sullivan, Assistant Superintendent for Administration 
Town Counsel for the Town of Simsbury: Robert M. DeCrescenzo, Esq. 
Minutes Recorder: Jessica Campbell, PBC Clerk and Administrative Secretary with the 
Simsbury Water Pollution Control Authority (WPCA) 
Public Guest(s): None 
 
AGENDA ITEMS 
 
1.) PUBLIC AUDIENCE 
 
There were no public audience members or comments. 
 
 
 

Page 2 · open in PDF

Public Building Committee 
Regular Meeting Minutes 
October 5, 2026 
Page 2 of 5 
 
 
 
2.) SIMSBURY MEADOWS PERFORMING ARTS CENTER – BAND SHELL 
EXPANSION 
 
a. Progress Status Report 
Mr. Kessler reported that the project was nearing completion, with only a few remaining items to 
be addressed. The remaining contingency was approximately 5%, totaling $158,000.00, 
reflecting confirmation that Tri-State Materials had no additional invoices and that its final costs 
were lower than estimated. Mr. Kessler stated that the lowest quote for the requested exterior 
stair railings was $2,563.00 from Quality Welding LLC, with scheduling underway and an 
invoice expected at the next meeting. Pavement markings, which had sustained significant wear, 
were repainted by AAA Pavement Markings for $1,750.00; the invoice was included in the 
meeting packet for approval. The as-built survey was also progressing, with costs coming in 
below expectations at $3,110.00.  
 
Mr. Kessler noted that the lighting protection work had experienced scheduling delays and that 
the contractor was being contacted regularly to ensure completion. Fieldwork was reportedly 
completed the previous week, with the work expected to be finished by the end of October. The 
exterior stair railing work was recently authorized. Mr. Kessler noted that the alternative bid was 
approximately $4,000.00 to $5,000.00 and would have required core drilling, while the 
contractor’s proposed cost was approximately $6,000.00. The selected quote of $2,563.00 was 
therefore considered a cost-effective option. Mr. Kessler concluded the project update by noting 
that only two action items remained. 
 
b. Review Pay Applications & Invoices 
i. Pay Application No. 9  
Chairman Derr authorized Payment Application No. 9, dated August 31, 2026, in the certified 
amount of $142,046.62.  
 
ii. AAA Pavement Marking, LLC – Invoice No. 13580 
Chairman Derr authorized payment of AAA Pavement Marking, LLC Invoice No. 13580, dated 
September 23, 2026, in the amount of $1,750.00.  
 
3.) TOOTIN’ HILLS ROOF – H.B. FISHMAN REPORT UPDATE 
Mr. Roy reported that the bid package for the Tootin’ Hills School reroofing project was 
prepared in June 2020. Overall, the project proceeded well; however, following completion, 
leaks were discovered in several locations, primarily in the library area beneath one of the 
Kalwall translucent panels. Additional caulking and sealant were applied, which resolved the 
immediate leaking, but these measures were not considered a long-term solution consistent with 
the intended 30-year roof lifespan. Carlisle Roofing, the roofing manufacturer, declined to 
provide a warranty for the affected area. This led to a dispute between the project architect, 
Jacunski Humes, and the roofing contractor, Imperial Roofing. At the Committee’s direction, 
H.B. Fishman, a firm specializing in roofing and waterproofing, was engaged to investigate the  
 

Page 3 · open in PDF

Public Building Committee 
Regular Meeting Minutes 
October 5, 2026 
Page 3 of 5 
 
 
issue and conducted a site inspection with representatives from Kalwall, the translucent panel 
manufacturer. 
 
Mr. Roy reported that the inspection found the Kalwall system includes a track with weep holes 
designed to allow water entering the track to drain onto the roof without adversely affecting the 
building structure. The second finding was that the Kalwall panels, which were more than 22 
years old, had exceeded their expected useful life expectancy, particularly those above the library 
facing south. The panels showed significant deterioration, with fibers becoming exposed and 
coming loose when touched. The inspection report was shared with both parties involved in the 
matter. 
 
Mr. Roy reported that Imperial Roofing disputed four findings outlined in H.B. Fishman’s 
inspection report. In response, H.B. Fishman provided a follow-up letter, included in the meeting 
packet, addressing each of the disputed points and reaffirming its findings. One key 
disagreement concerned Imperial Roofing’s claim that the project specifications required sealant 
to be applied at the level in question; H.B. Fishman indicated that this interpretation was 
inaccurate. Imperial also disputed the presence of weep holes in the Kalwall system, although 
photographs showed weep holes in other sections of the system, and the Kalwall representative 
had access to the original shop drawings. Mr. Roy noted that the conflicting positions had left the 
Committee facing a difficult decision regarding the appropriate corrective solution. 
 
Mr. Roy reported that the digital shop drawings, along with observations from the field, provided 
substantial evidence that the Kalwall system originally included weep holes. However, these 
openings may have been covered by the liquid-applied flashing, making their presence difficult 
to confirm conclusively. During a water infiltration test, investigators sprayed the area with 
water and observed it entering the lower channel. Their assessment was that, as the channel 
filled, the drainage openings became obstructed, allowing water to enter the library. Mr. Roy 
reported that the water infiltration resulted in minor interior damage, including sheetrock repairs 
and repainting. He noted that the temporary liquid-applied flashing may need to be reapplied, 
although a more permanent corrective solution would be preferable.  
 
H.B. Fishman’s initial recommendation was to address the deteriorated Kalwall panels, which 
had exceeded their useful life. A preliminary cost estimate of approximately $220,000 was 
obtained from a Kalwall representative for replacement of the panels. Mr. Roy noted that the 
replacement work would need to be completed by a Kalwall-approved vendor. Mr. Roy reported 
that a preliminary budget of up to $250,000 was being considered to ensure sufficient funding to 
complete the necessary corrective work. One option involved removing the liquid-applied 
membrane from the metal surfaces and implementing an alternative repair; however, he 
expressed reservations about this approach due to the anticipated challenges. Another option 
would involve installing standing-seam metal roofing over the library area. Mr. Roy noted that 
this alternative would have several drawbacks, including altering the original design rather than 
providing a like-for-like replacement and potentially diminishing the architectural quality of the 
library space. 
 
 

Page 4 · open in PDF

Public Building Committee 
Regular Meeting Minutes 
October 5, 2026 
Page 4 of 5 
 
 
Providing legal counsel, Mr. DeCrescenzo stated that a thorough review of the relevant 
documentation was necessary before reaching any conclusions regarding liability and damages.  
The review would include the independent report, the architect’s scope of work, the roof repair 
contract, and the response to the independent report. He explained that determining liability 
would require an assessment of the parties’ respective responsibilities, while calculating damages 
would involve comparing the costs of the remediation work undertaken with the expenses that 
could have been avoided had the necessary work been included in the original roof repair and 
replacement scope. 
 
Mr. DeCrescenzo also noted that the installation of new Kalwall panels could be considered a 
betterment, as incorporating them into the original scope of work may have increased the initial 
contract cost. Accordingly, the recoverable damages would need to account for any additional 
costs that would have been incurred regardless of the alleged deficiencies. He concluded that no 
definitive opinion on liability or damages could be provided until the relevant documents and 
repair costs were examined. Based on the information presented during the meeting, he indicated 
that the matter appeared relatively self-contained and that the documentation and actual repair 
history would likely provide the basis for determining the outcome. 
 
Mr. DeCrescenzo observed that the architect may have had an obligation to identify and 
communicate concerns regarding the Kalwall system if it was beyond or nearing the end of its 
useful life when assessing the roof repair or replacement project. He noted that, despite the 
project’s accelerated timeline, the architect should potentially have advised the client of the 
system’s condition and clarified whether its replacement should be included in the scope of 
work. He emphasized that repairing or replacing the roof without addressing an underlying 
system nearing the end of its service life could compromise the longevity and effectiveness of 
the overall repair. 
 
Mr. Sullivan explained that to complete the work, the contractors would need to do it during 
summer vacation and to expedite the project to summer of 2027, paperwork would need to be in 
place relatively soon. The participants discussed whether the project could proceed under the 
same funding allocation if a new architect and contractor were engaged. Mr. Roy noted that a 
contract had already been issued for the project and further explained that the work could remain 
under the same overall funding allocation while being treated as a separate project, potentially 
avoiding procurement complications associated with the existing funding arrangement. The 
participants discussed the grant funding and procurement considerations associated with the 
project, referencing a funding amount of $2,215,000. Mr. Sullivan expressed doubt that the State 
Office of Grants would classify the proposed work as an ineligible expense. The discussion also 
touched on the possibility of proceeding through a sole-source procurement process and seeking 
approval from the Board of Finance. Further clarification is needed regarding the grant eligibility 
determination and the appropriate procurement and approval procedures. Mr. DeCrescenzo 
stated that the alternate item would likely be considered an ineligible expense for State 
Department of Education grant purposes, although it may not be ineligible under the DAS grant. 
He explained that grant programs distinguish between eligible and ineligible expenses, and even 
if the proposed work were ultimately deemed ineligible, the Board and/or the Town could still  
 

Page 5 · open in PDF

Public Building Committee 
Regular Meeting Minutes 
October 5, 2026 
Page 5 of 5 
 
 
pursue approval for funding. He noted that the expert’s assessment indicated that repairing the 
roof would require addressing the Kalwall system, providing a technical basis for requesting that 
the associated work be considered eligible for grant funding. 
 
Mr. DeCrescenzo will review the provided documents and follow-up at the next scheduled 
Public Building Committee meeting. 
 
Mr. DeCrescenzo left the meeting at 8:00 P.M. 
 
Mr. Sullivan left the meeting at 8:05 P.M. 
 
The meeting concluded at 8:08 P.M. 
View the agenda PDF on this page (Public Building Committee Regular Meeting Agenda) Open the PDF